Power and the grid
None energized or contracted yet
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Dec. 13, 2023On-site substation approved with the rezoningThe 2023 plan includes an on-site utility substation and large backup generators (backup only, not supply). News report · Dec. 2023
- March 12, 2025Co-op asks state regulator for a large-load tariffRappahannock Electric files Schedule LP-DF, the rate framework for dedicated-facility loads like this one. Utility regulator · June 2025
- July 1, 2025Tariff in effect on an interim basisThe commission let LP-DF take effect subject to refund, then paused the case for settlement talks in June 2025. see Permits
- Not setCampus service agreement not publicOnly the tariff case is public; no agreement for this campus has been found. Analysis · Oct. 2026
- Under the co-op's large-load rules, customers pay monthly charges based on the size of the dedicated infrastructure and cover 100% of its construction cost up front. Local government · Oct. 2026
- The co-op buys power for data centers separately through PJM, apart from its general membership supply. News report · Oct. 2026
Permits checklist
1 pending · 1 granted · 2 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- ◷Large-load tariff (LP-DF) PendingVirginia State Corporation Commission · June 11, 2025: a utility rate case, not zoning; in effect interim, case stayed for settlement Utility regulator · June 2025
- ✓Rezoning, rural to light industrial GrantedCulpeper County Board of Supervisors · Dec. 5, 2023: approved 5-2 for Cielo; EdgeCore later bought the entitled site News report · Dec. 2023
- –Checked, nothing on file: Building permit, Air permit for backup generators
What could slow it down
- MediumConstruction not confirmedThe only sign of building is a press line from April 2026; no building permit or imagery is on record. see Permits
- MediumNo tenantBuilt for a single hyperscale tenant, but none is announced. Company · Oct. 2026
- MediumTariff case unfinishedThe co-op's large-load tariff is in effect only on an interim basis, subject to refund, while the case is stayed. see Permits
- WatchLocal oppositionPiedmont Environmental Council tracks the campus in its anti-sprawl campaign; two supervisors voted no over undisclosed generator fuel storage. No lawsuit found. News report · Oct. 2026
Money on record
What happened, and what is due
- March 7, 2023Paper trail Cielo Digital Infrastructure LLC registered in Delaware
- May 2023Money Cielo buys four parcels on Nalles Mill Road for a reported $18.75 million News report · July 2024
- Oct. 2023Permits County planning commission tables the Cielo proposal for 60 days News report · Oct. 2023
- Dec. 5, 2023Permits Board of Supervisors approves the rezoning 5-2 News report · Dec. 2023
- July 18, 2024Paper trail EdgeCore announces its purchase of the entitled 120-acre site Company · July 2024
- March 12, 2025Power Rappahannock Electric files its large-load tariff with the state regulator Utility regulator · June 2025
- Sept. 2, 2025Permits County requires conditional use permits for data centers outside the Technology Zone; this campus is not affected News report · Sept. 2025
- April 22, 2026Construction A press report says construction has begun at EdgeCore's Virginia campuses News report · April 2026
- Feb. 2028Power Initial power delivery expected (company says) Company · July 2024
Specs
- Three buildings: 2023 plan: two 96 MW and one 48 MW (300 MW total, as reported) News report · Dec. 2023
- Air-cooled: closed-loop system; water use below 0.01 L/kWh (benchmark) Company · July 2024
Owners, partners and builders
- EdgeCore Digital Infrastructure: developer and operator; owned by Partners Group
- Cielo Digital Infrastructure: original developer, owned by Arroyo Investors; sold the site
- Culpeper County Board of Supervisors: rezoning
- Virginia State Corporation Commission: sets the co-op's rates
- Rappahannock Electric Cooperative: retail utility; Hyperscale Energy Services buys PJM power for data centers
- Piedmont Environmental Council (Save Culpeper)
Open questions
- Tenant and lease terms.
- Whether construction has actually started.
- The campus service agreement with the co-op.
- EdgeCore's purchase price.
107 records from 18 documents
Drawn from news reports, company statements, local government records, business registries, our own analysis, utility regulator dockets and public and commercial datasets, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (26)
- Rate class: Schedule LP-DF - Large Power Dedicated Facilities (Rappahannock Electric Cooperative)“for approval to implement its proposed Large Power Dedicated Facilities Schedule LP-DF”Utility regulator · June 2025 · grade A
- utility rate schedule: petition filed“On March 12, 2025, Rappahannock Electric Cooperative filed a petition with the State Corporation Commission for approval to implement its proposed Large Power Dedicated Facilities Schedule LP-DF”Utility regulator · June 2025 · grade A
- utility rate schedule: order granting stay“This matter is temporarily stayed, including a temporary pause in formal discovery, through July 11, 2025.”Utility regulator · June 2025 · grade A
- Stated campus size: 216 MW“plans to develop a 1.4 million square foot data center campus capable of initially supporting 216 MW of critical IT load with the potential to support up to 432 MW”Company · July 2024 · grade B
- Stated campus size: 432 MW“plans to develop a 1.4 million square foot data center campus capable of initially supporting 216 MW of critical IT load with the potential to support up to 432 MW”Company · July 2024 · grade B
- Utility: Rappahannock Electric Cooperative“Initial power delivery is expected in early 2028 through Rappahannock Electric Cooperative.”Company · July 2024 · grade B
- Site acres: 120 acres“announced the purchase of 120 acres of land in the Culpeper Technology Zone (CTZ) in Culpeper, Virginia and plans to develop a 1.4 million square foot data center campus capable of initially supporting 216MW of critical IT load”Company · July 2024 · grade B
- IT capacity: 216 MW“announced the purchase of 120 acres of land in the Culpeper Technology Zone (CTZ) in Culpeper, Virginia and plans to develop a 1.4 million square foot data center campus capable of initially supporting 216MW of critical IT load”Company · July 2024 · grade B
- Developer: EdgeCore Digital Infrastructure“announced the purchase of 120 acres of land in the Culpeper Technology Zone (CTZ) in Culpeper, Virginia and plans to develop a 1.4 million square foot data center campus capable of initially supporting 216MW of critical IT load”Company · July 2024 · grade B
- Floor area: 1400000 sq ft“announced the purchase of 120 acres of land in the Culpeper Technology Zone (CTZ) in Culpeper, Virginia and plans to develop a 1.4 million square foot data center campus capable of initially supporting 216MW of critical IT load”Company · July 2024 · grade B
- IT capacity: 216 MW“capable of initially supporting 216MW of critical IT load with the potential to support up to 432MW”Company · July 2024 · grade B
- Stated campus size: 432 MW“capable of initially supporting 216MW of critical IT load with the potential to support up to 432MW”Company · July 2024 · grade B
- Utility: Rappahannock Electric Cooperative“Initial power delivery is expected in early 2028 through Rappahannock Electric Cooperative.”Company · July 2024 · grade B
- Power plan: grid“Initial power delivery is expected in early 2028 through Rappahannock Electric Cooperative.”Company · July 2024 · grade B
- Cooling: closed-loop air-cooled“the company will employ a close-looped air-cooled system in Culpeper that uses very little water to cool its facilities”Company · July 2024 · grade B
- Phases: 2 (initial 216 MW IT capacity; expansion potential to 432 MW)“capable of initially supporting 216MW of critical IT load with the potential to support up to 432MW”Company · July 2024 · grade B
- Original target date: 2028“Initial power delivery is expected in early 2028 through Rappahannock Electric Cooperative.”Company · July 2024 · grade B
- EdgeCore states the campus can support up to 432 MW at full potential, double the initial 216 MW critical IT capacity“plans to develop a 1.4 million square foot data center campus capable of initially supporting 216MW of critical IT load with the potential to support up to 432MW”Company · July 2024 · grade B
- Utility service: not stated“For approval to implement a new Large Power Dedicated Facilities Rate Schedule”Analysis · Oct. 2026 · grade C
- Electric service agreement signed: not stated“On March 12, 2025, Rappahannock Electric Cooperative filed a petition with the State Corporation Commission”Analysis · Oct. 2026 · grade C
- Grid operator: PJM“To serve data centers, REC created Hyperscale Energy Services (HES), which separately procures the significant amounts of electricity they require through the PJM Interconnection, LLC (PJM) wholesale energy market.”News report · Oct. 2026 · grade C
- REC CEO John Hewa: REC has energized 900 MW of new data-center substation capacity across its territory since January 2026, and data-center wholesale supply is kept separate from the general membership via Hyperscale Ene“Since January of this year, REC has energized 900 megawatts of new data center substation capacity.”News report · Oct. 2026 · grade C
- Current target date: 2028“Initial power delivery through Rappahannock Electric Cooperative was expected in early 2028.”News report · April 2026 · grade C
- On-site generation: not stated“The development will also have an on-site REC substation and large backup generators.”Analysis · Dec. 2023 · grade C
- Substation: On-site REC substation (unnamed)“The development will also have an on-site REC substation and large backup generators.”News report · Dec. 2023 · grade C
- Buildings: 3 buildings“the data center will spread across three buildings: two 96MW data centers and one 48MW data center”News report · Dec. 2023 · grade C
Money and contracts (25)
- electric service tariff: scope“On March 12, 2025, Rappahannock Electric Cooperative filed a petition with the State Corporation Commission for approval to implement its proposed Large Power Dedicated Facilities Schedule LP-DF”Utility regulator · June 2025 · grade A
- electric service tariff: term / effectiveness“On April 4, 2025, the Commission issued an Order for Notice and Comment (Procedural Order) setting a procedural schedule for this proceeding.”Utility regulator · June 2025 · grade A
- Tenant status: none announced (speculative; designed for a single hyperscale tenant)“all of which have been designed to accommodate data center campuses for single hyperscale tenants”Company · Oct. 2026 · grade B
- Incentives: Culpeper Technology Zone by-right program: up to 40% of taxes paid rebated over 5 years for qualifying companies“Qualified technology zone companies are eligible for up to 40% of taxes paid over a five year period when making a new $10 million taxable investment and hiring 10 employees in a calendar year.”Local government · Oct. 2026 · grade B
- electric service tariff: minimum bill“For data centers, their monthly charges are based on the size (capacity) of the dedicated infrastructure built to serve them, not simply the amount of energy or electric demand they use in a given month.”Local government · Oct. 2026 · grade B
- electric service tariff: up-front cost contribution 100 %“these large load members cover 100% of the initial construction cost of their dedicated infrastructure (paid up-front)”Local government · Oct. 2026 · grade B
- incentive program: scope 40 % of taxes paid“Qualified technology zone companies are eligible for up to 40% of taxes paid over a five year period when making a new $10 million taxable investment and hiring 10 employees in a calendar year.”Local government · Oct. 2026 · grade B
- incentive program: conditions (qualification) 10000000 USD minimum new taxable investment“when making a new $10 million taxable investment and hiring 10 employees in a calendar year. Employees must earn above the prevailing average wage.”Local government · Oct. 2026 · grade B
- incentive program: term 5 years“including up to 40% tax relief over five years for companies investing $10 million or more and creating 10 jobs at or above the average wage”Local government · Oct. 2026 · grade B
- incentive program: clawback - NONE STATED (finding)“Qualified technology zone companies are eligible for up to 40% of taxes paid over a five year period when making a new $10 million taxable investment and hiring 10 employees in a calendar year.”Local government · Oct. 2026 · grade B
- Square feet: 1400000 sq ft“plans to develop a 1.4 million square foot data center campus”Company · July 2024 · grade B
- land purchase: scope“announced the purchase of 120 acres of land in the Culpeper Technology Zone (CTZ) in Culpeper, Virginia”Company · July 2024 · grade B
- land purchase: price - NOT DISCLOSED (finding)“announced the purchase of 120 acres of land in the Culpeper Technology Zone (CTZ) in Culpeper, Virginia”Company · July 2024 · grade B
- Tenants: not stated“all of which have been designed to accommodate data center campuses for single hyperscale tenants”Analysis · Oct. 2026 · grade C
- rezoning / entitlement: conditions / proffers - NOT RETRIEVABLE (finding)“Board documents suggests that the data center will spread across three buildings: two 96MW data centers and one 48MW data center.”News report · Oct. 2026 · grade C
- electric service agreement: termination - NOT PUBLIC (finding)“For approval to implement a new Large Power Dedicated Facilities Rate Schedule”Analysis · Oct. 2026 · grade C
- electric service agreement: collateral“Those protections may include upfront infrastructure payments, collateral and obligations established through their service agreements.”News report · Oct. 2026 · grade C
- It is not Culpeper financing and no part of it is booked to this campus; the same Virginia Business article is the source for construction work having begun at Culpeper“Denver-based data center developer EdgeCore Digital Infrastructure secured $1.5 billion in financing toward building two data centers in Sterling, it announced Tuesday.”News report · April 2026 · grade C
- EdgeCore announced a $17B, 3.9M sq ft campus on 697 acres in Louisa County, VA - a separate campus; none of its figures are booked here. Together with Ashburn/Sterling it frames the sponsor's Virginia build-out“EdgeCore announced in June 2025 it had purchased 697 acres in Louisa County to build a $17 billion, 3.9 million-square-foot data center campus.”News report · April 2026 · grade C
- Land price: 18750000 USD“Cielo reportedly purchased the four Nalles Mill Road parcels in May 2023 for $18.75 million from two owners”News report · July 2024 · grade C
- land purchase: scope 18750000 USD“Cielo reportedly purchased the four Nalles Mill Road parcels in May 2023 for $18.75 million from two owners”News report · July 2024 · grade C
- Stated capital cost: 5400000000 USD“approved plans for Cielo Digital Infrastructure to construct a $5.4 billion data center”News report · Jan. 2024 · grade C
- rezoning / entitlement: scope“The County also voted in favor of rezoning the land from Rural Area to Light Industrial.”News report · Dec. 2023 · grade C
- rezoning / entitlement: conditions (as reported)“Among those against the project is Jefferson District Supervisor Brad Rosenberger, due to concerns that Cielo did not state how big the fuel tanks would need to be for the generators.”News report · Dec. 2023 · grade C
- Cielo purchased the four Nalles Mill Road parcels in May 2023 for $18.75 million; EdgeCore later acquired the approved Cielo campus“Cielo reportedly purchased the four Nalles Mill Road parcels in May 2023 for $18.75 million from two owners; the Fishbach family and Kenneth Dowder/Eastern View.”News report · May 2023 · grade C
Permits and government (10)
- Piedmont Environmental Council's Save Culpeper - Stop Data Center Sprawl campaign tracks this campus as 'Cielo (Edgecore)' among nine approved/proposed Culpeper projects (PEC's own load estimates, all campuses). No litig“Cielo (Edgecore) | Approved - 2023 | 122 | 2,400,000 | 300”News report · Oct. 2026 · grade C
- Culpeper County zoning text amendment: new data centers on industrially zoned land OUTSIDE the Culpeper Tech Zone now require a conditional use permit (previously by-right). This campus - inside the CTZ, rezoned in 2023“On Sept. 2, the Culpeper Board of Supervisors passed a zoning text amendment requiring a conditional use permit for all new data centers on industrially zoned land outside the Culpeper Tech Zone.”News report · Sept. 2025 · grade C
- Culpeper County Board of Supervisors: Zoning text amendment - conditional use permit required for new data centers on industrially zoned land outside the Culpeper Tech Zone“On Sept. 2, the Culpeper Board of Supervisors passed a zoning text amendment requiring a conditional use permit for all new data centers on industrially zoned land outside the Culpeper Tech Zone.”News report · Sept. 2025 · grade C
- Opposition: Piedmont Environmental Council opposition (Save Culpeper campaign); generator fuel-storage disclosure concerns raised at approval“Among those against the project is Jefferson District Supervisor Brad Rosenberger, due to concerns that Cielo did not state how big the fuel tanks would need to be for the generators.”News report · Dec. 2023 · grade C
- rezoning: approved“The Board of Supervisors voted 5-2 in favor.”News report · Dec. 2023 · grade C
- Rezoning date: Dec. 5, 2023“On Dec. 5, the Culpeper County Board of Supervisors voted to approve Cielo Digital Infrastructure, a 300-megawatt data center proposal with three, two-story buildings on Nalles Mill Road”News report · Dec. 2023 · grade C
- Data center campus approval: Approval“On Dec. 5, the Culpeper County Board of Supervisors voted to approve Cielo Digital Infrastructure, a 300-megawatt data center proposal with three, two-story buildings on Nalles Mill Road”News report · Dec. 2023 · grade C
- Culpeper County Board of Supervisors: Rezoning Z-459-23-1 (Rural Area to Light Industrial) - Cielo 3-building campus, Nalles Mill Road“The Board of Supervisors voted 5-2 in favor.”News report · Dec. 2023 · grade C
- Data center campus application: Recommendation for approval“On Nov. 9, the Culpeper County Planning Commission voted to forward Cielo Digital Infrastructure to the Culpeper Board of Supervisors with a recommendation for approval.”News report · Nov. 2023 · grade C
- Culpeper County Planning Commission: Cielo Digital Infrastructure data center proposal, Nalles Mill Road (Case Z-459-23-1)“the Culpeper County Planning Commission held a hearing on this proposal and ultimately decided to table the application for 60 days”News report · Oct. 2023 · grade C
Site and other (16)
- County code: Culpeper County, VA (51047)“announced the purchase of 120 acres of land in the Culpeper Technology Zone (CTZ) in Culpeper, Virginia”Company · Oct. 2026 · grade B
- Minimum bill terms: Monthly charges based on the capacity of dedicated infrastructure built to serve the customer, regardless of energy used; customer pays 100% of the initial construction cost of dedicated infrastructur“these large load members cover 100% of the initial construction cost of their dedicated infrastructure (paid up-front)”Local government · Oct. 2026 · grade B
- Stage: building“EdgeCore Digital Infrastructure is building a 1.4-million-square-foot data center campus within the CTZ, capable of supporting up to 216 megawatts of critical IT load”Local government · Feb. 2025 · grade B
- County name: Culpeper County, VA“We look forward to helping generate economic growth and jobs for Culpeper County while remaining mindful of topics that are important to the community”Company · July 2024 · grade B
- Name: EdgeCore Culpeper Campus“announced the purchase of 120 acres of land in the Culpeper Technology Zone (CTZ) in Culpeper, Virginia”Company · July 2024 · grade B
- Developer: EdgeCore Digital Infrastructure“EdgeCore Digital Infrastructure, a wholesale data center developer, owner, and operator”Company · July 2024 · grade B
- Acres: 120 acres“announced the purchase of 120 acres of land in the Culpeper Technology Zone (CTZ) in Culpeper, Virginia”Company · July 2024 · grade B
- Water use stated: WUE below 0.01 L/kWh (benchmark)“carrying a benchmark water usage effectiveness (WUE) rating below .01 L/kWh”Company · July 2024 · grade B
- Announced: July 18, 2024“announced the purchase of 120 acres of land in the Culpeper Technology Zone (CTZ) in Culpeper, Virginia”Company · July 2024 · grade B
- Owner companies: EdgeCore Internet Real Estate, LLC“announced the formation of EdgeCore Internet Real Estate, LLC (the Company), an investment vehicle with fully integrated operational capabilities formed to develop, acquire, and operate data centers across North America”Company · Feb. 2018 · grade B
- Project status: clearing - construction work begun“Construction work has begun at both campuses.”News report · April 2026 · grade C
- Construction stage: clearing“Construction work has begun at both campuses.”News report · April 2026 · grade C
- County code: 51047“Data center firm EdgeCore is expanding in Virginia again with plans for a new campus in Culpeper County.”News report · July 2024 · grade C
- Aliases: Culpeper Technology Zone (CTZ) campus, Nalles Mill Road; formerly the Cielo Digital Infrastructure campus“The Culpeper Star-Exponent reports Edgecore acquired Cielo's planned campus in Culpeper.”News report · July 2024 · grade C
- Address: Nalles Mill Road, Culpeper, VA (Culpeper Technology Zone)“Cielo Digital Infrastructure is set to develop a 1.4 million sq ft (130,065 sqm) data center on a 121-acre parcel along Nalles Mill Road”News report · Dec. 2023 · grade C
- Site location: Nalles Mill Road, Culpeper Technology Zone, Culpeper, VA“In late 2023, Cielo Digital Infrastructure was granted permission to develop a 1.4 million sq ft (130,065 sqm) data center campus on a 121-acre parcel along Nalles Mill Road.”News report · Dec. 2023 · grade C