Power and the grid
None energized or contracted yet
Getting on the grid
- Under Utah's SB 132 the data center pays for grid upgrades outside the general rate base; the minutes say the applicant passed the utility's financial screening and holds a letter of credit. Local government · March 2026
- A Williams gas representative has asked a Mona resident for an easement for a gas line, pointing to planned gas service (press). News report · Oct. 2026
Permits checklist
1 appealed · 2 checked, nothing on file
Approvals the campus needs, and where each stands.
- !Conditional use permit AppealedJuab County Planning Commission · April 15, 2026: approved with road-impact and other conditions; residents appeal over notice to neighbors Local government · April 2026
- –Checked, nothing on file: Large-load tariff with PacifiCorp, Air permit
What could slow it down
- HighPermit under appealResidents say the permit was approved without notice to landowners within 1,000 feet; the county has not ruled (press). News report · Oct. 2026
- MediumPower not contractedThe 750 MW is a request; the separate tariff with PacifiCorp has not been filed. see Permits
- MediumWater and rural impactsOpponents cite transparency, water use and effects on the rural community (press). News report · Oct. 2026
- WatchDeveloper behind the applicant unclearNo source ties the Mona site to the developer or project name in other listings; the only party on record is Nebo North LLC. News report · Oct. 2026
Money on record
$10B+ potential overall investment (applicant) (no financing disclosed). Local government · March 2026
What happened, and what is due
- March 18, 2026Permits Nebo North presents a six-to-eight-building, 750 MW campus to the county planning commission Local government · March 2026
- April 15, 2026Permits Planning commission approves the conditional use permit with conditions Local government · April 2026
- Oct. 11, 2026Legal Residents' coalition Mona Cares has an appeal pending, saying neighbors were not told before approval (press) News report · Oct. 2026
- Oct. 11, 2026Power A gas company representative seeks a pipeline easement from a resident (press) News report · Oct. 2026
Specs
Owners, partners and builders
- Nebo North LLC: permit holder; Jonathan Vanica presented the plan
- Juab County Planning Commission: approved the permit
- Juab County: hearing the appeal
- Rocky Mountain Power (PacifiCorp): serving utility
- Williams: gas company seeking a line easement (press)
- Mona Cares: residents' coalition that filed the appeal
Open questions
- Who is behind Nebo North, and any tenant.
- Outcome of the residents' appeal.
- Utility tariff and contracted load.
29 records from 6 documents
Drawn from news reports, local government records and state agency records, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (4)
- At the Juab County Planning Commission on March 18, 2026, Nebo North LLC presented a campus west of Mona: 6-8 buildings of about 300,000 sq ft and 100 MW each on 361 acres, total requested load 750 MW, potential $10+ bil“describes a plan for 6–8 data center buildings on 361 acres, each about 300,000 sq ft and 100 MW, with a total requested load of 750 MW”Local government · March 2026 · grade B
- Serving utility is Rocky Mountain Power (PacifiCorp). Under Utah SB 132 the data center pays for all grid upgrades outside the general rate base, under a separate tariff to be negotiated with PacifiCorp; per the minutes“so electricity rates for other customers should not go up, subject to a separate tariff negotiated with PacifiCorp.”Local government · March 2026 · grade B
- Opposition is organized and contentious: a public meeting saw a resident removed by police and the Juab County Commission chairman reported receiving death threats related to the project; residents cite transparency, wat“A public meeting became contentious, with a resident removed by police and Juab County Commission Chairman Clinton Painter saying he had received death threats related to the project.”News report · Oct. 2026 · grade C
- A Williams Gas representative sought permission from a Mona resident to run a gas line across his backyard, indicating planned gas service to the project (Deseret News reporting)“One Mona resident first heard about the project only after a Williams Gas representative knocked on his door, asking for permission to run a gas line across his backyard”News report · Oct. 2026 · grade C
Money and contracts (2)
- Project status: CONDITIONAL USE PERMIT APPROVED by the Mona Planning and Zoning Commission; appeal by the Mona Cares coalition PENDING before Juab County officials; approval was granted without requiring notice to landow“an appeal filed by the coalition remains pending before Juab County officials”News report · Oct. 2026 · grade C
- A $10 billion figure circulates for the Mona campus (Medium/YouTube headline) with no named basis, developer filing or capacity behind it“Neighbors are appealing a $10 billion campus near Mona in Juab County”News report · Oct. 2026 · grade C
Permits and government (4)
- CUP approved Apr 15, 2026 after public hearing. Conditions include compliance wi: conditional use permit approved with conditions“Commissioner Mike Kramer moved that the Planning Commission approve the Conditional Use Permit for Nebo North LLC (data center project), subject to the following conditions:”Local government · April 2026 · grade B
- Project identity: Data center campus at Mona, Juab County, UT (queue name 'Granite Fortress'); the Mona Planning and Zoning Commission approved a conditional use permit for a roughly 3-million-square-foot data center; re“Mona residents are opposing a 3-million-square-foot data center after the town approved its conditional use permit without notifying nearby landowners.”News report · Oct. 2026 · grade C
- Project status: proposed conditional use permit approved appeal pending“Mona residents are opposing a 3-million-square-foot data center after the town approved its conditional use permit without notifying nearby landowners.”News report · Oct. 2026 · grade C
- Project Stratos (Box Elder County, MIDA-related) is a different Utah project covered in the same backlash reporting; Granite Fortress is only the Mona, Juab County site“Mona residents are opposing a 3-million-square-foot data center after the town approved its conditional use permit without notifying nearby landowners.”News report · Oct. 2026 · grade C
Legal (3)
- County code: 49023“Residents organized by Mona Cares say they were unaware of the project until after approval, and an appeal filed by the coalition remains pending before Juab County officials.”News report · Oct. 2026 · grade C
- Mona Cares coalition appeal of the conditional use permit remains pending before Juab County; residents cite transparency, water use and rural impacts“Residents organized by Mona Cares say they were unaware of the project until after approval, and an appeal filed by the coalition remains pending before Juab County officials.”News report · Oct. 2026 · grade C
- Residents organized as Mona Cares are appealing the $10B campus approval near Mona; the appeal remains pending before Juab County, citing transparency, water consumption and rural impacts.“The project's appeal remains pending, with residents citing concerns about transparency, water consumption, and impacts on the rural community.”News report · Oct. 2026 · grade C