Permits checklist
1 restricted · 1 pending · 2 granted
Town and state actions on record. No approval exists.
- ‖Data center ordinance RestrictedSmithfield Town Council · May 5, 2026: data centers not permitted in any zoning district; the planner says this project is reviewed under the prior rules News report · May 2026
- ◷Major land development application PendingTown of Smithfield · June 11, 2026: certified incomplete a second time; appeal postponed to January News report · June 2026
- ✓RI Ready site enrollment GrantedQuonset Development Corporation Board · April 16, 2024: state shovel-ready program State agency · April 2024
- ✓Water and sewer availability letters GrantedTown of Smithfield · Sept. 1, 2026: issued after an April request News report · Sept. 2026
Why it stopped, what could revive it
- HighTown banSmithfield now prohibits data centers in every zoning district; whether the earlier filing escapes it is before the court. News report · Sept. 2026
- HighIncomplete applicationThe application has twice been certified incomplete, and the appeal waits until January 2027. see Permits
- MediumResident oppositionSpeakers at the ban hearing cited the grid, water contamination, energy costs, noise and rural character. Local government · May 2026
1 case on record
- Filed July 4, 2026; amended Sept. 15 Hanton City Investments LLC and ROK LLC v. Smithfield Town Council members and Planning DirectorRhode Island Superior Court News report · Sept. 2026seeks a ruling that data centers were permitted under the zoning before the ban (claim)
Power and the grid
Getting on the grid
- No utility is named for the site; the developers cite the area's transmission capacity. News report · April 2026
- No state siting board application has been found, consistent with no on-site power plant being proposed. State agency · Oct. 2026
- A state bill to make data centers of 50 MW or more pay their full grid costs was held for study in 2026; the project has stated no MW. News report · Sept. 2026
Money on record
$59M town revenue over 30 years the applicants project (about $42M net; applicant claim). News report · May 2026
Not on record: town tax agreement: the developers are lobbying for a state sales-tax break News report · May 2026
What happened, and what is due
- April 16, 2024Site State development corporation enrolls the 235-acre site in its RI Ready program State agency · April 2024
- March 19, 2026Permits Planning Board recommends a town data center ordinance News report · March 2026
- April 20, 2026Money Developers approach the town while lobbying the legislature for a sales-tax break (press) News report · April 2026
- April 22, 2026Permits Applicants request water and sewer availability for six buildings News report · Sept. 2026
- May 4, 2026Permits Major land development application filed News report · May 2026
- May 5, 2026Permits Town Council bans data centers in all zoning districts, 4-1, before a packed room Local government · May 2026
- June 11, 2026Permits Town certifies the application incomplete a second time News report · June 2026
- July 4, 2026Legal Applicants sue the five council members and the planning director in Superior Court News report · Sept. 2026
- Sept. 1, 2026Permits Town issues water and sewer availability letters News report · Sept. 2026
- Jan. 2027Permits Rescheduled zoning appeal of the incompleteness certificate News report · Sept. 2026
Specs
Owners, partners and builders
- Hanton City Investments LLC: applicant, a partnership including Revity Energy's Ryan Polumbo and John Branca (press)
- ROK LLC: co-applicant and property owner
- Smithfield Town Council
- Planning Director Gregory Guertin
- Smithfield Zoning Board (appeal)
- Quonset Development Corporation (RI Ready)
- Smithfield residents who packed the May 5 hearing
Open questions
- Data-center share of the complex and MW.
- Serving utility.
- Outcome of the lawsuit and zoning appeal.
40 records from 8 documents
Drawn from news reports, state agency records and local government records, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (2)
- State framework in play: Senate Bill 2776 (2026 session) would subject data centers with electric demand of 50 MW or more to strict utility-impact rules (full cost of generation/transmission/distribution infrastructure;“Senate Bill 2776 targets data centers with an electric demand of 50 megawatts or greater, establishing strict rules for their utility impacts.”News report · Sept. 2026 · grade C
- No utility is named for this site in any source found and NO MW on any basis exists; a Providence Journal quote cites the area's transmission capacity without naming a utility“We think that that area of the state has a lot of important attributes that would make it a prime target for a data center, specifically the transmission capacity over in that area of the state,”News report · April 2026 · grade C
Money and contracts (7)
- Project status: NOT APPROVED - application filed May 4, 2026, certified incomplete a second time on June 11, 2026; the applicants' appeal of the incompleteness certificate was postponed to January; the applicants are als“An Oct. 7 hearing on an appeal from Hanton City Investments has been postponed to sometime in January.”News report · Sept. 2026 · grade C
- Water/sewer availability request Apr 22 (per complaint summary): six buildings, approx 903,487 sq ft, estimated daily water flow 180,697 gallons/day; town issued availability letters Sep 1“a major land development at the Property consisting of six buildings with a total floor area of approximately 903,487 square feet, with an estimated daily water flow of 180,697 gallons per day.”News report · Sept. 2026 · grade C
- Plaintiffs state approx $2.5M invested to date in the property and project (complaint summary)“Plaintiffs have invested approximately $2.5 million to date for the Property and the Project.”News report · Sept. 2026 · grade C
- water sewer availability: availability letters issued“On September 1, the Town issued the water and sewer availability letters. Plaintiffs have invested approximately $2.5 million to date for the Property and the Project.”News report · Sept. 2026 · grade C
- No town tax treaty or stabilisation agreement exists; the applicants are lobbying the General Assembly for a STATE sales-tax break, and their application projects ~$59 million of revenue for Smithfield over 30 years (~$4“According to Hanton City's application, the company projects its business complex to generate about $59 million in revenue for Smithfield over a 30-year period, with a net gain of almost $42 million.”News report · May 2026 · grade C
- Applicant fiscal claim (not MW): business complex projected to generate about $59M revenue for Smithfield over 30 years, net gain almost $42M“the company projects its business complex to generate about $59 million in revenue for Smithfield over a 30-year period, with a net gain of almost $42 million.”News report · May 2026 · grade C
- Developer seeking state tax benefits / sales tax break at General Assembly to pursue the project“the company behind the proposed Smithfield data center is seeking tax benefits to pursue its project.”News report · May 2026 · grade C
Permits and government (9)
- County code: 44007“Town Planner Gregory Guertin explains the following: The proposed amendment defines what a data center is and will be listed in the Table of Uses as not permitted in all zoning districts.”Local government · May 2026 · grade A
- Smithfield Town Council:“Town Clerk Antonuccio takes a roll call, and the following votes were recorded: Member Winfield - nay Member Toppi - aye Member Iannotti - aye Vice President Bovis - aye President Tassoni - aye”Local government · May 2026 · grade A
- Project identity: Hanton City Investments Smithfield Business Complex (data center component) - major land development at 248-364 George Washington Highway, Smithfield, RI, ~235 acres: six buildings totalling ~903,487 sq“248 - 364 George Washington Highway, Smithfield: The approximately 235-acre site off of George Washington Highway in Smithfield was enrolled by the QDC Board on April 16,2024.”State agency · April 2024 · grade A
- Project status: stalled“An Oct. 7 hearing on an appeal from Hanton City Investments has been postponed to sometime in January.”News report · Sept. 2026 · grade C
- Smithfield adopted a Data Center Ordinance adding 'data center' as a defined use and prohibiting it in all zoning districts for two years. Sequence per the applicants' complaint and taxpayer-group tracking: the project a“defined the use and prohibited the use in all zoning districts”News report · Sept. 2026 · grade C
- The incompleteness certificate and the pending Superior Court suit frame the pro: SECOND certificate of incompleteness ISSUED; applicants' appeal to the Zoning Board postponed from Oct 7 to January“Hanton City Investments LLC and ROK LLC, as applicants and owners of the property, seek to appeal the town administrative officer's second certificate of incompleteness on the project, issued June 11.”News report · June 2026 · grade C
- Broad resident opposition: residents packed May 5 2026 Town Council meeting urging officials to stop the data center; council voted 4-1 to ban data centers“Town residents packed the May 5 Smithfield Town Council meeting to urge local officials to stop a data center from being built on an undeveloped site”News report · May 2026 · grade C
- Application filed one day before the Council adopted the Data Center Ordinance; : Major land development application FILED (review under the pre-DCO ordinance, per the Planning Director)“Smithfield Planning Director Gregory Guertin said the project will be reviewed under the zoning ordinance in effect prior to the data center change.”News report · May 2026 · grade C
- Smithfield Planning Board:“The Planning Board voted to recommend that the Town Council adopt the DCO.”News report · March 2026 · grade C
Legal (3)
- Developer: Hanton City Investments LLC (applicant), with ROK LLC (co-applicant and property owner)“Hanton City Investments LLC and ROK LLC, as applicants and owners of the property, seek to appeal the town administrative officer's second certificate of incompleteness on the project, issued June 11.”News report · Sept. 2026 · grade C
- Applicants sued all five Town Council members and the Planning Director in Rhode Island Superior Court (filed Jul 4, 2026, amended Sep 15, 2026), claiming the data center use was permitted under the pre-DCO ordinance - t“The complaint, filed in Rhode Island Superior Court on July 4 and amended on September 15, also names Gregory Guertin, the Town's Director of Planning and Economic Development.”News report · Sept. 2026 · grade C
- Hanton City Investments, LLC and ROK, LLC sued all five Smithfield Town Council members and the town planning director in RI Superior Court (complaint filed Jul 4, 2026; amended Sep 15, 2026), seeking a declaration that“Hanton City Investments, LLC and ROK, LLC have filed a lawsuit against all five members of the Town Council for their opposition to a planned data center on the site of the historic Hanton City site.”News report · Sept. 2026 · grade C
Site and other (2)
- Concept yield: 890000 sq ft“An updated Concept Plan has been prepared illustrating approximately 890,000 SF of industrial building yield.”State agency · May 2026 · grade A
- Announced: March 10, 2026“Revity, along with other partners, has secured a few hundred acres in the town of Smithfield.”News report · March 2026 · grade C