Permits checklist
1 granted · 2 checked, nothing on file
Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.
- ✓Joint development agreement and purchase option GrantedAppalachian Industrial Development Authority · March 2026: an authority act, not a county or city approval; 18-month term (press) News report · July 2026
- –Checked, nothing on file: County or city approval of the project, Air permit
Why it stopped, what could revive it
- HighCounty moratoriumThe Fiscal Court halted new data center construction for two years, in direct response to the proposal. News report · July 2026
- HighSite not provenNo tenant is targeted because the plot has not been deemed viable. News report · Oct. 2026
- MediumLocal mistrustThe county judge said officials learned of the proposal only after documents surfaced through an open records request. News report · July 2026
Power and the grid
None energized or contracted yet
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- As of Oct. 2026No air permit or utility caseNo state air permit application and no Kentucky PSC case names the project; it is designed to supply its own power. see Permits
- Because the plant would not sell power to the public, the state utility commission has nothing to certify, which is the project's design premise. News report · Oct. 2026
What happened, and what is due
- March 2026Site The development authority, Diversified and Maverick Holdings sign an 18-month joint development agreement (press) News report · March 2026
- July 17, 2026Site The agreement becomes public; officials call it early-stage and Jenkins says it was not involved in planning News report · July 2026
- July 20, 2026Permits Letcher's Fiscal Court votes unanimously for a two-year moratorium after nearly two hours of public comment News report · July 2026
- Sept. 2026Legal Residents ask how the county will enforce the moratorium; no further data center action is reported News report · Sept. 2026
Specs
- Feasibility stage: work is under way on possible on-site generation (press) News report · July 2026
Owners, partners and builders
- Diversified Gas and Oil Corporation: gas producer and counterparty
- Maverick Holdings: local real estate developer
- Appalachian Industrial Development Authority: owns the business park
- Letcher County Fiscal Court: moratorium
- Terry Adams: county judge/executive
Open questions
- Tenant.
- Site viability and land purchase.
- Data center load in MW.
- Air permit and gas supply terms.
27 records from 8 documents
Drawn from news reports and company statements, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (4)
- Diversified Energy's off-grid data center power venture with FuelCell Energy and TESIAC (announced March 10, 2025: in-basin gas + captured coal-mine methane delivered by pipeline to fuel cells; up to 360 MW across three“announced a strategic partnership intended to address the urgent energy needs of data centers by supplying as much as 360 megawatts of electricity to three distinct locations in Virginia, West Virginia and Kentucky”Company · March 2025 · grade B
- On-site generation: 100 MW“He pointed to an effort to build a 100-megawatt natural gas-fired power plant at a Letcher County industrial park for a potential data center”News report · Aug. 2026 · grade C
- Project status: proposed“Reports suggest that the project is in the early stages of planning, with work currently ongoing to explore the possibility of onsite power generation.”News report · July 2026 · grade C
- MW basis named: mw generation onsite (proposed gas plant, press summary only, NOT an agency figure) - a secondary trade summary describes a 100 MW off-grid power plant using an existing natural gas compressor station“aiming to use an existing natural gas compressor station to fuel an off-grid, 100-megawatt power plant that could attract data centers or manufacturers”News report · July 2026 · grade C
Money and contracts (2)
- Appalachian Industrial Development Authority joint development agreement (reported in secondary summaries as signed March 2026 with an 18-month term) gives Diversified and Maverick Holdings a path to purchase approximate“the documents that have been shared from the industrial authority include a joint development agreement”News report · July 2026 · grade C
- An 18-month joint development agreement was signed in March 2026 (publicly reported Jul 17, 2026): AIDA, Diversified and Maverick Holdings, with an option to potentially purchase approximately 100 acres at the Gateway Bu“The documents that have been shared from the industrial authority include a joint development agreement.”News report · March 2026 · grade C
Permits and government (3)
- Kentucky data-center resources tracker lists Letcher among the Appalachian Kentucky counties with moratoriums in its August 2026 update, corroborating that the two-year halt remained the standing county position“Letcher | County orders two-year halt on data centers [July 22, 2026]”News report · July 2026 · grade C
- Jul 22, 2026: the Letcher County Fiscal Court voted unanimously to place a two-year moratorium on construction of new data centers in the county and to require environmental impact studies before future projects, respond“Responding to concerns raised by residents over a proposed natural gas-fired power plant intended to attract artificial intelligence data centers, the Letcher Fiscal Court voted unanimously Monday to place a two-year moratorium on the construction of new data centers”News report · July 2026 · grade C
- Letcher County Fiscal Court:“the Letcher Fiscal Court voted unanimously Monday to place a two-year moratorium on the construction of new data centers in the county”News report · July 2026 · grade C
Legal (1)
- Nearly two hours of resident testimony (water use, noise, pollution, wildlife, tourism, neighborhood impacts) preceded the Fiscal Court's moratorium vote; residents who spoke to WYMT off camera were mixed, some opposed a“The action came after nearly two hours of public comments, during which residents expressed concerns about water use, noise, pollution, wildlife”News report · July 2026 · grade C
Site and other (2)
- Judge/Executive Terry Adams told the July 20 meeting that county officials learned about the proposal only after documents became public through an Open Records Act request; AIDA, which owns Gateway Regional Business Par“Judge/Executive Terry Adams said county officials learned about the proposal only after documents became public through an Open Records Act request.”News report · July 2026 · grade C
- County code: 21133“A new proposal to explore a data center at the Gateway Business Park in Letcher County is sparking discussion across Eastern Kentucky about the region's future.”News report · July 2026 · grade C