Power
Power and the grid
Energized, size not disclosed
Sources on record, size not disclosed
- Grant County PUD grid Serving utilityserving utility; no campus-specific power contract appears in the PUD's public records Local government · Oct. 2026
Permits
Permits checklist
2 granted · 1 checked, nothing on file
Approvals on record for the expansion.
- ✓Air permit for the expansion (notice of construction) GrantedWashington Department of Ecology · Oct. 24, 2018: 72 emergency generators and 136 coolers State agency · Oct. 2018
- ✓Air permit revision for renewable diesel GrantedWashington Department of Ecology · Sept. 27, 2022: facility-wide order; lists the expansion's engines State agency · Sept. 2022
- –Checked, nothing on file: Power sales contract for the expansion
Risks
What could slow it down
- WatchTight area gridGrant County PUD needs its transmission program to lift the Quincy-area load limit from about 300 MW to 650 MW. see Permits
- WatchNo public power contractNo campus-specific contract or load figure is public, so the expansion's size cannot be checked. see Permits
Timeline
What happened, and what is due
SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
- March 6, 2018Permits Microsoft applies to the state for the MWH03 to MWH06 expansion State agency · Sept. 2022
- Aug. 27, 2018Permits Public hearing on the 72-generator plan, which press puts at 210 MW of backup power News report · Aug. 2018
- Oct. 24, 2018Permits State issues the air approval order for the expansion State agency · Oct. 2018
- Oct. 2019Construction First expansion generators commissioned State agency · Sept. 2022
- April 22, 2022Permits Microsoft applies to burn renewable diesel in the emergency engines State agency · Sept. 2022
- June 2022Construction Last MWH06 engines commissioned, completing the expansion's backup fleet State agency · Sept. 2022
- Sept. 27, 2022Permits State approves renewable diesel for the site's emergency engines State agency · Sept. 2022
The buildings
Specs
204 MWe
combined rating of the 68 emergency generators (backup, not campus load)
- Renewable diesel: approved in 2022 as fuel for the emergency engines State agency · Sept. 2022
Who is involved
Owners, partners and builders
Owner
- Microsoft: owner, operator and permit holder
Regulator
- Washington Department of Ecology: air permits for the generators
Utility
- Grant County PUD: serving utility
Still unknown
Open questions
- IT or utility load of the four buildings.
- Terms of Microsoft's power supply from Grant County PUD.
Where this comes from
21 records from 8 documents
Drawn from state agency records, news reports and public and commercial datasets, each kept with its date and source. The bar shows documents by type.
State agency 4News report 3Dataset 1
Evidence
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (10)
- Project identity: Microsoft MWH Data Center, 1515 Port Industrial Parkway, Quincy, Grant County, WA: the MWH03, MWH04, MWH05 and MWH06 expansion buildings of Microsoft's Quincy campus, permitted by Washington Department“Microsoft Corporation (Microsoft) MWH Data Center (MWH) is a large data center located at 1515 Port Industrial Parkway in Quincy, WA.”State agency · Sept. 2022 · grade A
- Project status: OPERATING: the MWH03-06 expansion buildings were approved in 2018 and commissioned in stages (MWH06's engines were commissioned April-June 2022 per the 22AQ-E035 order tables); in 2022 Ecology approved th“The Department of Ecology's Air Quality Program (Ecology) has approved the use of renewable diesel fuel for emergency engines at Microsoft Corporation MWH Data Center”State agency · Sept. 2022 · grade A
- County code: 53025“MWH Data Center, herein referred to as the Permittee, is an existing data center located at 1515 Port Industrial Parkway, Quincy, Washington, in Grant County.”State agency · Sept. 2022 · grade A
- Project status: expansion built operating within columbia campus“The Department of Ecology's Air Quality Program (Ecology) has approved the use of renewable diesel fuel for emergency engines at Microsoft Corporation MWH Data Center”State agency · Sept. 2022 · grade A
- Backup generator nameplate ceiling: 210 MW“The 68 3.0-MWe generators will have a combined capacity of 204 MWe”State agency · Oct. 2018 · grade A
- Announced: March 6, 2018“On March 6, 2018, Ecology received a Notice of Construction application from Microsoft Corporation, requesting an expansion of the MWH Data Center - MWH 03/04/05/06.”State agency · March 2018 · grade A
- The MWH03-06 expansion equipment is 68 x 3.0 MWe plus 4 x 1.0/1.5 MWe EMERGENCY backup generator engines and 136 evaporative fluid coolers per the Ecology order; backup engines are never converted to MW rows and the 210“The expansion would include sixty-eight 3.0 MWe emergency backup generator engines, four 1.0 MWe or 1.5 MWe emergency backup generator engines and 136 evaporative fluid coolers.”State agency · March 2018 · grade A
- Microsoft's Malaga project near Quincy (102.5 acres, three 250,000 sq ft buildings) is a separate campus from the Columbia / MWH site“The 102.5-acre campus, also known as the Malaga project, will house three 250K SF server farms on land that Microsoft paid $9.2M for in April.”News report · Oct. 2026 · grade C
- Grant County PUD's Quincy Transmission Expansion is a district-wide capital program (10 sub-projects; $97.3M in the 2026 budget). Per the PUD's own project page it raises the Quincy-area load limit from approximately 300“a collection of 10 sub-projects with a price tag of $97.3 million that is expected to add 650 megawatts of power capacity”News report · Oct. 2026 · grade C
- DCD reported the Ecology-approved MWH03-06 expansion as 72 gensets providing 'a total of 210MW of backup power', matching the 210 MWe permitted nameplate stated in the NOC application (press corroboration only; the agenc“install millions of dollars' worth of power equipment to provide a total of 210MW of backup power”News report · Aug. 2018 · grade C
Permits and government (3)
- Facility-wide order for the MWH Data Center, 1515 Port Industrial Parkway, Quinc: approval order issued - renewable diesel authorized for the facility's emergency engines“The Department of Ecology’s Air Quality Program (Ecology) has approved the use of renewable diesel fuel for emergency engines at Microsoft Corporation MWH Data Center”State agency · Sept. 2022 · grade A
- Approval Order 22AQ-E035 (Sep 27, 2022) approved renewable diesel as a fueling option for the facility's emergency engines“The Department of Ecology's Air Quality Program (Ecology) has approved the use of renewable diesel fuel for emergency engines at Microsoft Corporation MWH Data Center”State agency · Sept. 2022 · grade A
- Approves the MWH expansion at 1515 Port Industrial Parkway, Quincy: sixty-eight : Notice of Construction approval order issued - MWH Data Center expansion (Phases 03/04/05/06)“Sixty-eight (68) Cummins Model C3000 D6e or CAT Model C175 generators. The 68 3.0-MWe generators will have a combined capacity of 204 MWe.”State agency · Oct. 2018 · grade A