Data center profile · East side of Evergreen Mills Road, south of Leesburg, Loudoun County, Virginia

Spring Valley Technology Park (Leesburg)

Active Infrastructure's proposed 12-building, 3.25 million sq ft campus in Loudoun County, Virginia, with mostly gas fuel cell power; planners unanimously recommended denial July 2026.

Denial recommended, hearing deferred. Loudoun's Planning Commission voted 6-0 in July 2026 to recommend denying the rezoning, following county staff, and the Board of Supervisors hearing set for Oct. 14, 2026 was deferred indefinitely at the developer's request. No decision, utility filing or air permit is on record.
12 buildings
data centers totaling up to 3.25M sq ft
plus three substations and battery storage, in two phases (application)
6-0
Planning Commission vote to recommend denial
July 23, 2026; county staff also recommended denial
780 MW
behind-the-meter campus the developer says it is designing
developer says (press); nothing filed with the county or regulators
~325 acres
site in the rezoning application
362 acres in the 2024 announcement (press)
OperatorActive Infrastructure (developer and applicant)
CustomerNone named
First building in serviceOur estimate: 2029 or later (no dated power path yet).
Next stepBoard of Supervisors public hearing, deferred indefinitely at the developer's request (no new date)
Power

Power and the grid

None energized or contracted yet

On-site gas fuel cells (Bloom Energy, per the developer)Proposed, unpermitted
780 MW
developer's design figure (press); fed by an existing gas pipeline; no MW filed with the county, regulators or an air permit News report · 2025
Proposed
Related generation and energy contracts (context, not added to campus supply)

Getting on the grid

Permits

Permits checklist

1 pending · 2 checked, nothing on file

Approvals the campus needs, and where each stands.

Risks

What could slow it down

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Oct. 21, 2024
    Site Active Infrastructure proposes a 362-acre, 12-building campus near Leesburg powered by gas fuel cells and batteries (press) News report · Oct. 2024
  2. 2025
    Power Developer says it is designing a 780 MW campus, all behind the meter (press) News report · 2025
  3. July 2, 2026
    Site Opponents circulate a petition asking the county to deny the campus News report · July 2026
  4. July 23, 2026
    Permits Planning Commission unanimously recommends denial after a large turnout of opponents News report · July 2026
  5. Oct. 2026
    Permits Board of Supervisors hearing set for Oct. 14 is deferred indefinitely at the developer's request News report · Oct. 2026
The buildings

Specs

3.25M sq ft
data-center space in the application (3.5M in 2024 press)
3 substations
campus-dedicated, plus a utility-scale energy storage facility
362 acres
site size in the Oct. 2024 announcement (press)
Who is involved

Owners, partners and builders

Developer
  • Active Infrastructure: developer and applicant
  • DLA Piper LLP: the developer's land-use attorneys
Government
  • Loudoun County Planning Commission: recommended denial
  • Loudoun County Board of Supervisors: final decision
Power
  • Bloom Energy: fuel cells, per the developer (press)
  • Dominion Energy: area utility
Opponents
  • Piedmont Environmental Council
  • Loudoun Wildlife Conservancy
Still unknown

Open questions

Where this comes from

30 records from 8 documents

Drawn from news reports and local government records, each kept with its date and source. The bar shows documents by type.

News report 7Local government 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (7)
  • Project identity: Spring Valley Technology Park (SVTP): Active Infrastructure's proposed data center campus on about 325 acres along the east side of Evergreen Mills Road south of Leesburg, Loudoun County, VA (county leg
    “The proposal seeks to rezone the site from the Transitional Residential-10 (TR-10) large lot neighborhood place type zoning district to the Industrial Park (IP) zoning district”
  • 12 data center buildings, three campus-dedicated substations and a utility-scale energy storage facility in two phases per the application as heard
    “to permit construction of 12 data centers totaling up to 3.25 million square feet, three campus-dedicated utility substations, and a utility-scale energy storage facility.”
  • Active Infrastructure's principal (Zygler), interviewed by DCD, states the site has electricity infrastructure available for up to 900 MW and is currently designing for a 780 MW campus, all behind the meter, using Bloom
    “Active Infrastructure has the electricity infrastructure available for up to 900MW, but is currently designing for a 780MW campus, all of which will be behind the meter.”
  • The campus would be powered in part by on-site generation: natural gas-powered hydrogen fuel cells forming a low- or zero-emissions microgrid plus battery storage; the applicant's attorney said the reserved generation ar
    “The company plans to power the site with “natural gas-powered hydrogen fuel cells that generate electricity without combustion, creating a low- or zero-emissions microgrid,””
  • Applicant plans natural gas-powered hydrogen fuel cells plus utility-scale battery storage as a low/zero-emissions microgrid; no MW figure is stated for the generation, the storage, or the campus in any fetched source
    “natural gas-powered hydrogen fuel cells that generate electricity without combustion, creating a low- or zero-emissions microgrid”
  • Applicant's counsel says a reserved generation area is large enough to potentially offset a majority, if not all, of the site's demand; an unquantified claim, not a capacity figure
    “the applicant has reserved an area large enough to potentially offset a majority, if not all, of its demand”
  • The applicant's land use attorney (DLA Piper) told WBJ the reserved on-site generation area could potentially offset a majority, if not all, of demand, but offered no figure; the balance of supply would be Dominion Energ
    “the applicant has reserved an area large enough to potentially offset a majority, if not all, of its demand”
Permits and government (8)
  • Project status: REZONING PENDING, ADVERSELY POSITIONED: county staff and the Planning Commission recommended denial; the Planning Commission voted 6-0 on July 23, 2026 to recommend denial to the Board of Supervisors; the
    “It was set to go before the BoS for public hearing on October 14, but has been indefinitely deferred at the request of the applicant.”
  • Loudoun County Board of Supervisors:
    “This application received an unprecedented unanimous recommendation of denial after a massive public turnout of opposition at the Planning Commission.”
  • After the unanimous denial recommendation, the Board of Supervisors hearing (set for Oct 14, 2026) has been indefinitely deferred at the applicant's request; the application remains pending.
    “It was set to go before the BoS for public hearing on October 14, but has been indefinitely deferred at the request of the applicant.”
  • Application covers the ~325-acre Spring Valley Technology Park: 12 data centers : Rezoning application (TR-10 to Industrial Park) with special exceptions and zoning modifications - PENDING; Planning Commission recommende
    “permit construction of 12 data centers totaling up to 3.25 million square feet, three campus-dedicated utility substations, and a utility-scale energy storage facility.”
  • Loudoun County Planning Commission:
    “On July 23, the Loudoun County Planning Commission unanimously recommended that the Board of Supervisors deny the proposed Spring Valley Technology Park”
  • County code: 51107
    “On July 23, the Loudoun County Planning Commission unanimously recommended that the Board of Supervisors deny the proposed Spring Valley Technology Park, a 325-acre data center campus along the east side of Evergreen Mills Road in the Ashburn District.”
  • Project status: rezoning pending board of supervisors planning commission recommended denial July 23, 2026
    “The proposal seeks to rezone the site from the Transitional Residential-10 (TR-10) large lot neighborhood place type zoning district to the Industrial Park (IP) zoning district”
  • Change.org petition asks the county to deny the Spring Valley Technology Park campus; PEC and Loudoun Wildlife Conservancy also campaign against the rezoning
    “This includes denying the proposed Spring Valley Technology Park data center campus along Evergreen Mills Road.”