The site from above
The site
Latest clear satellite view, March 3, 2025. What we count on the March 3, 2025 image:
- 1 roofed data hall
Power and the grid
None energized or contracted yet
- On-site generation Backup only, undocumentednone planned in any filing; backup generators not yet in a state air permit; the county discussed Tier 4 units in June 2026 State agency · Oct. 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Jan. 16, 2025STACK announces committed Dominion powerThe announcement cites six 300 MW substations supplied by Dominion, with 19 data centers on 500 acres. Company · Jan. 2025
- Jan. 26, 2026Filing counts six substationsThe federal wetlands notice describes 21 data center buildings and six substations on the site. State agency · Jan. 2026
- As of Oct. 2026No contract on public recordNo service agreement or contracted megawatts appear in any state or county filing; Virginia large loads are served under tariffs. Company · Oct. 2026
- Not setBackup generator air permit: not foundNo state air permit notice for backup generators has been located. see Permits
- Dominion's large-load queue is about 70 GW, with individual delivery points capped near 300 MW (regional context, not this campus's load). News report · Oct. 2026
- The nearest 500 kV line (Ladysmith to Possum Point) is about 2 km from the site. OpenStreetMap · Oct. 2026
Grid upgrades
No grid upgrade for this campus's load is on record. Related grid records in the area:
- Dominion supplemental projects S3701.1 (construct Allman switching station north of the existing Fredericksburg substation, $60.00M) and S3701.2 (rebuild 230 kV line No. 2157 Allman-Cranes Corner ~4.5 miles and line No.… Dataset · Dec. 2025
What is next door
Distances from mapped lines and plants. OpenStreetMap · Oct. 2026
Permits checklist
3 pending · 5 granted
Approvals a campus like this normally needs (including an air permit for backup generators), and what we found.
- ◷Wetlands permit, later phases (404 individual) PendingU.S. Army Corps of Engineers · Jan. 26, 2026: comments closed Feb. 20, 2026; issuance not confirmed State agency · Feb. 2026
- ◷Virginia Water Protection permit 25-2511 PendingVirginia DEQ · May 20, 2026: draft decision is to issue; comments closed June 19, 2026 State agency · May 2026
- ◷Air permit for backup generators PendingVirginia DEQ: no notice found State agency · Oct. 2026
- ✓Rezoning A-1 to M-2 with proffers, plus comprehensive plan amendment GrantedStafford County Board of Supervisors · Sept. 17, 2024: 6-1 vote News report · Sept. 2024
- ✓Expansion rezoning, 34.94 acres GrantedStafford County Board of Supervisors · June 16, 2026: reported; adds one building footprint and fire station land Dataset · Aug. 2026
- ✓Grandfathering under pre-Oct. 2025 rules GrantedStafford County Board of Supervisors · Dec. 2, 2025: unanimous; exempts the campus from the 750-foot setback rule News report · Dec. 2025
- ✓Water and wastewater infrastructure agreement GrantedStafford County · April 1, 2025: phased meters, drought stop clause, high-use penalty News report · April 2025
- ✓Wetlands permit, Phase I GrantedU.S. Army Corps of Engineers · Jan. 26, 2026: authorized earlier under a state programmatic permit State agency · Jan. 2026
What could slow it down
- HighNo tenant or power contractNo tenant, lease, Dominion service agreement or contracted megawatts appears in any public record, so the 1 GW rests on developer statements. State agency · Oct. 2026
- MediumWaterThe campus needs county bridging water until a reclaimed-water system is built, and the agreement lets the county stop supply in a drought. If reuse construction stalls, the developer must restore potable capacity. see Permits
- MediumOpen wetlands permitsThe state water permit is a draft and the later-phase federal permit is not confirmed. The site holds three streams and about 72 acres of protected buffers. Dataset · Aug. 2026
- MediumCounty backlashStafford tightened its data center rules in Oct. 2025 (750-foot setbacks) after resident opposition, and the campus survives only through grandfathering. News report · Oct. 2026
- WatchGeneratorsNo air permit is on record for backup generators, and the county discussed Tier 4 units in June 2026. see Permits
Money on record
Not on record: project-specific incentives: standard regional rate of $1.25 per $100 of equipment value News report · Sept. 2025
2 recorded land documents for the campus company in county records (Feb. 2025); none lists a price. 3 related-party transfers are shown greyed. 2 sales or conveyances by the campus company or to public bodies are not listed. Parcel counts come from the deed; acreage is not recorded.
- Oct. 2024 Stafford Technology LC to Stafford Technology LC · price not recorded · 1 parcel · related-party transfer County deed records · Oct. 2024
- Feb. 2025 SI Nva07a LLC to STACK STC Aggregator LLC · price not recorded County deed records · Feb. 2025
- Feb. 2025 SI Nva07a LLC to STACK STC Aggregator LLC · price not recorded · 1 parcel County deed records · Feb. 2025
- Feb. 2025 STACK STC Aggregator LLC to SI Nva07campus LLC · price not recorded · 1 parcel · related-party transfer County deed records · Feb. 2025
- Oct. 2025 SI Nva07campus LLC and SI Nva07west LLC to SI Nva07campus LLC and SI Nva07west LLC · price not recorded · 5 parcels · related-party transfer County deed records · Oct. 2025
What happened, and what is due
- April 11, 2023Site Peterson Companies' affiliate files to rezone the site for a phased data center campus News report · April 2023
- Sept. 17, 2024Permits Board of Supervisors approves the rezoning 6-1, the county's largest data center project News report · Sept. 2024
- Nov. 26, 2024Paper trail SI Nva07campus LLC registered in Delaware
- Jan. 16, 2025Site STACK announces the 1+ GW Stafford Technology Campus after buying the site Company · Jan. 2025
- Feb. 27, 2025Money Land purchase recorded (no price on the deed): SI Nva07a LLC to STACK STC Aggregator LLC County deed records · Feb. 2025
- March 19, 2025Money STACK closes $4B in green financing that includes Stafford (press) News report · March 2025
- April 1, 2025Permits Supervisors authorize the water and wastewater agreement News report · April 2025
- Dec. 2, 2025Permits County grandfathers the campus under the older, looser data center rules News report · Dec. 2025
- Jan. 26, 2026Permits Army Corps and DEQ issue a joint wetlands notice that says the site is already under construction State agency · Oct. 2026
- May 5, 2026Construction Topping-out ceremony for the first building Local government · Aug. 2026
- May 20, 2026Permits DEQ drafts a decision to issue the state water permit State agency · May 2026
- June 16, 2026Permits Supervisors approve a 34.94-acre expansion rezoning Dataset · Aug. 2026
- Aug. 2026Site A water-quality study documents three streams and protected species on the site Dataset · Aug. 2026
- 2027Construction Company target for the first phase to be complete News report · Oct. 2026
Building activity by quarter
Since March 2022: 129 FAA filings (March 2024 to Oct. 2026): tallest permanent stack 165 ft (filed March 2024) and tallest crane 250 ft (Jan. 2026); 66 satellite captures.
Specs
- Reclaimed-water cooling: purple-pipe infrastructure is under construction Dataset · Aug. 2026
Owners, partners and builders
- STACK Infrastructure: developer and operator
- SI NVA07Campus, LLC: campus owner and permit applicant (STACK entity)
- IPI Partners, acquired by Blue Owl per press: STACK's owner
- The Peterson Companies: rezoned and sold the site (Stafford Technology LC)
- Stafford County Board of Supervisors
- Virginia DEQ Northern Regional Office
- U.S. Army Corps of Engineers, Norfolk District
- Dominion Energy Virginia: utility
- Hirschler (Charles Payne): land-use counsel
- WSSI: wetlands agent
- Bohler Engineering: civil engineer
Open questions
- Who the tenant is.
- How many megawatts Dominion has contracted.
- Whether the state water permit and later-phase federal permit are issued.
- Whether the building count is 19, 21 or 23.
423 records from 50 documents
Drawn from state agency records, news reports, public and commercial datasets, business registries, securities filings, local government records, company statements, utility regulator dockets and satellite captures, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (26)
- large load interconnection request: Draft permit noticed; DEQ tentative decision is to issue; comment period closed June 19, 2026; issuance not confirmed at capture“The proposed activity is the construction of a data center campus comprised of 21 data center buildings, 6 substations, and associated infrastructure on an approximately 537-acre project site.”State agency · June 2026 · grade A
- Buildings: 21 buildings“construct an approximately 4.5 million square foot data center campus comprised of 21 data center buildings and six substations”State agency · Jan. 2026 · grade A
- Square feet: 4500000 sq ft“construct an approximately 4.5 million square foot data center campus comprised of 21 data center buildings and six substations”State agency · Jan. 2026 · grade A
- Substation count: 6“comprised of 21 data center buildings and six substations”State agency · Jan. 2026 · grade A
- Power plan: grid“comprised of 21 data center buildings and six substations”State agency · Jan. 2026 · grade A
- Nearest power line of 345 kV or more: 1.95 kmMeasured on OpenStreetMap map data.
- Nearest substation of 345 kV or more: none within 16km kmMeasured on OpenStreetMap map data.
- Nearest gas pipeline: 14.32 kmMeasured on OpenStreetMap map data.
- Site area: 537 acres“construction of a data center campus comprised of 21 data center buildings, 6 substations, and associated infrastructure on an approximately 537-acre project site”State agency · May 2026 · grade B
- Stated campus size: 1,000 MW“today announced its largest flagship development to date: the 1+GW Stafford Technology Campus (“STC”) in Stafford County, Virginia.”Company · Jan. 2025 · grade B
- Interconnection status: Company-announced committed Dominion Energy power: STACK states the campus will draw committed power from six 300 MW substations supplied by Dominion Energy; the campus is under construction (firs“will house a total of 19 data centers, drawing committed power from six 300MW substations supplied by Dominion Energy”Company · Jan. 2025 · grade B
- Stated campus size: 1,000 MW“announced its largest flagship development to date: the 1+GW Stafford Technology Campus”Company · Jan. 2025 · grade B
- Buildings: 19 buildings“will house a total of 19 data centers, drawing committed power from six 300MW substations supplied by Dominion Energy”Company · Jan. 2025 · grade B
- Utility: Dominion Energy“drawing committed power from six 300MW substations supplied by Dominion Energy”Company · Jan. 2025 · grade B
- Interconnection status: Developer claims committed power from six Dominion substations; no Dominion or SCC filing states contracted campus MW“drawing committed power from six 300MW substations supplied by Dominion Energy”Company · Jan. 2025 · grade B
- Moved from campus facts field 'substation capacity each': 300 MW. Per-substation delivery-point size as stated by the developer. Dominion's Facility Interconnection Requirements cap direct-connect load at any substation“drawing committed power from six 300MW substations supplied by Dominion Energy”Company · Jan. 2025 · grade B
- IT capacity: not stated“Documented absence: no IT-load figure in STACK announcements, the county application or proffers, DEQ notices, or the USACE notice”Company · Oct. 2026 · grade C
- Utility service: not stated“Documented absence: no executed ESA or contracted MW in any public filing; developer claims committed power via six substations but no Dominion or SCC document states a campus MW”Company · Oct. 2026 · grade C
- On-site generation: not stated“Documented absence: grid-supplied campus; no on-site generation plant in any filing”State agency · Oct. 2026 · grade C
- Backup generators: not stated“Tier 4 generator requirement discussed at the June 2026 rezoning”State agency · Oct. 2026 · grade C
- Electric service agreement signed: not stated“Documented absence: no ESA or special contract for this campus found in the SCC record or county filings; Virginia large-load service is tariff-based (Dominion GS schedules)”Company · Oct. 2026 · grade C
- Paper or real: Real: entitled (2024 rezoning + proffers), land closed, portfolio-level financing closed, vertical construction underway. Paper elements: tenant, MW basis and COD are developer-statement only“the campus spans 500 acres, features four sub-campuses, and will house a total of 19 data centers, drawing committed power from six 300MW substations supplied by Dominion Energy”Company · Oct. 2026 · grade C
- Dominion territory large-load queue is ~70 GW with individual delivery points capped at ~300 MW under the SCC-ordered queue process - portfolio context only, not campus MW“Individual requests would be capped at 300MW and grouped into batches of roughly ten projects”News report · Oct. 2026 · grade C
- Stated campus size: 1,000 MW“At full build-out, STC is expected to deliver more than 1GW of capacity across 19 data centers on a 500-acre site”News report · May 2026 · grade C
- Dominion supplemental projects S3701.1 (construct Allman switching station north of the existing Fredericksburg substation, $60.00M) and S3701.2 (rebuild 230 kV line No. 2157 Allman-Cranes Corner ~4.5 miles and line No.“Construct a second 230 kV double-circuit pole line ~12 miles, Aquia Harbour to Possum Point.”Dataset · Dec. 2025 · grade C
- Buildings: 23 buildings“a data center campus with 23 buildings and six electric substations”News report · Sept. 2024 · grade C
Money and contracts (37)
- Proffer amendment application (RC25156486): scope Expand campus boundary to incorporate six additional parcels (34.94 acres rezoned A-1/M-1 to M-2); modify utility infrastructure improvement requirements; add new land de“Expansion of the Stafford Technology Campus boundary to incorporate six (6) additional parcels; (2) Modification of utility infrastructure improvement requirements; and (3) Addition of new land dedication requirements”Local government · Oct. 2026 · grade A
- this row cites the 2026-1 filing) name Stack Infrastructure, Inc. as the Company responsible for the Statistical Data File and STACK INFRASTRUCTURE PARENT, LLC as securitizer of record, the same parent entity this campu“Stack Infrastructure, Inc. (the “Company”) is responsible for the information provided to us, including the information set forth in the Statistical Data File”SEC filing · Feb. 2026 · grade A
- Square feet: 5800000 sq ft“includes a phased data center campus which will contain approximately 5.8 million square feet of data center uses at full buildout”Local government · March 2024 · grade A
- Rezoning with proffers (RC23154931): scope“The proposal is to reclassify the Property from A-1, Agricultural, to M-2, Heavy Industrial”Local government · March 2024 · grade A
- Rezoning proffers: scope ~5.8 million sq ft of data center uses at full buildout“includes a phased data center campus which will contain approximately 5.8 million square feet of data center uses at full buildout”Local government · March 2024 · grade A
- Tax revenue stated: 80000000+ USD/yr“the project will generate more than $80 million in local annual tax revenue at full buildout”Local government · Aug. 2026 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: Oct. 1, 2025 · Grantor: SI NVA07CAMPUS LLC · Grantee: SI NVA07CAMPUS LLC · Parcel number: 38-29 · Address: 1352 RICHMOND HWY · City: FREDERICKSBURG”County deed records · Oct. 2025 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: Feb. 27, 2025 · Grantor: SI NVA07A LLC · Grantee: STACK STC AGGREGATOR LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”County deed records · Feb. 2025 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: Feb. 27, 2025 · Grantor: SI NVA07A LLC · Grantee: STACK STC AGGREGATOR LLC · Parcel number: 38-124 · Address: 000 ADDRESS EXCEPTION · City: STAFFORD”County deed records · Feb. 2025 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: Feb. 27, 2025 · Grantor: STACK STC AGGREGATOR LLC · Grantee: SI NVA07CAMPUS LLC · Parcel number: 38-124 · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”County deed records · Feb. 2025 · grade B
- Power supply (developer statement): scope Committed power from six 300MW substations“drawing committed power from six 300MW substations supplied by Dominion Energy”Company · Jan. 2025 · grade B
- Land purchase (recorded deed): contract value 302304000 USD“Recorded: Jan. 9, 2025 · Price: $302,304,000 · Grantor: STAFFORD TECHNOLOGY LC · Grantee: SI NV A07A LLC · Parcel number: 38-124 · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”County deed records · Jan. 2025 · grade B
- Land purchase (recorded deed): contract value 6000000 USD“Recorded: Nov. 8, 2024 · Price: $6,000,000 · Grantor: MONTANO FERNANDEZ · Grantee: SI NVA07A LLC · Parcel number: 38-29 · Address: 1318 RICHMOND HWY · City: FREDERICKSBURG”County deed records · Nov. 2024 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: Oct. 31, 2024 · Grantor: STAFFORD TECHNOLOGY LC · Grantee: STAFFORD TECHNOLOGY LC · Parcel number: 38-124 · City: STAFFORD”County deed records · Oct. 2024 · grade B
- Tenants: not stated“Documented absence: no tenant named in STACK announcements, the county rezoning record, DEQ notices, the USACE notice, or press coverage searched 2026-10-18”Company · Oct. 2026 · grade C
- Tenant status: not stated“while meeting the end user's specific building and site design requirements”State agency · Oct. 2026 · grade C
- Power supply - missing clauses (finding): finding No termination, minimum-billing, collateral, ramp or term clauses for Dominion service are public; no ESA filed with the VA SCC was found“Dominion asserted that the proposed Project is necessary to provide requested service to the Customer's new data center in Stafford County, Virginia”Utility regulator · Oct. 2026 · grade C
- Tenant lease - missing (finding): finding No tenant lease, build-to-suit agreement or end-user contract exists in any public record opened; the campus is being built without a disclosed tenant“while meeting the end user's specific building and site design requirements”State agency · Oct. 2026 · grade C
- Reclaimed-water (purple pipe) infrastructure to serve STC is under construction; STC is a named intended reuse-water customer in the county pipeline permit (the reuse system itself is being built under a separate AWS-cou“purple pipe infrastructure for reclaimed cooling water is currently being built”Dataset · Aug. 2026 · grade C
- Incentives: No project-specific incentive agreement; county data center equipment taxed at $1.25 per $100 of assessed value under the regional recruiting rate“recapped the region's 2019 tax agreement (standardized depreciation schedules and a dollar-1.25 tax rate used for recruiting)”News report · Sept. 2025 · grade C
- Water and Wastewater Infrastructure Agreement: scope“Supervisors unanimously authorized a water and wastewater infrastructure agreement with the developer of the Stafford Technology Campus”News report · April 2025 · grade C
- Water and Wastewater Infrastructure Agreement: condition Phased meter issuance tied to construction milestones of the county reuse system“They don't get just a million gallons, from day 1. It is a gradual controlled increase”News report · April 2025 · grade C
- Water and Wastewater Infrastructure Agreement: condition Developer must restore potable capacity if reuse construction stalls; drought stop clause; high-use penalty“including phased meter issuance, a requirement to restore potable capacity if reuse construction stalls, a drought stop clause and a high-use penalty”News report · April 2025 · grade C
- Financing: $4B green financing closed Mar 2025 covers Stafford plus Portland and Toronto; no campus-level allocation stated“Denver-based STACK Infrastructure has secured $4 billion in green financing for a new 1 gigawatt campus in Stafford, Va.”News report · March 2025 · grade C
- Green financing: scope 4000000000 USD“Denver-based STACK Infrastructure has secured $4 billion in green financing for a new 1 gigawatt campus in Stafford, Va.”News report · March 2025 · grade C
- Green financing: scope Financing also covers Portland, OR and Toronto expansions; no campus-level allocation stated“The funds will also finance expansions at the firm's Portland, Ore., and Toronto, Canada, sites”News report · March 2025 · grade C
- STACK closed $4B in green financing supporting construction at Stafford, Portland and Toronto; $9B of financing raised for Virginia projects since 2019 (portfolio context, not a campus capex figure)“With $9 Billion of financing supporting Virginia projects since 2019 and new financing for Portland and Toronto”News report · March 2025 · grade C
- Land price: 302300000 USD“Stack Infrastructure has acquired a 504-acre site in Stafford County, Virginia, for $302.3M”News report · Jan. 2025 · grade C
- Conditions of approval: Proffers accepted with the 2024 rezoning: water services agreement before first occupancy; developer-funded bridging water/sewer improvements (county CIP estimate $58M); connector road; ~4-acre fi“The developer, Peterson Cos., has also agreed to fund $58 million in capital improvement projects for the county”News report · Sept. 2024 · grade C
- Rezoning proffers: scope 58000000 USD“The developer, Peterson Cos., has also agreed to fund $58 million in capital improvement projects for the county”News report · Sept. 2024 · grade C
- Rezoning proffers: scope Connector road between Richmond Highway and Eskimo Hill Road“The project includes the construction of a connector road between Richmond Highway and Eskimo Hill Road”News report · Sept. 2024 · grade C
- Rezoning proffers: scope 4 acres“A late proffer also includes about four acres of land for a new fire station on State Shop Road”News report · Sept. 2024 · grade C
- Rezoning proffers: condition“The Water Service Agreement shall be approved prior to the issuance of the first occupancy permit (temporary or final) on the Property”News report · Sept. 2024 · grade C
- Rezoning proffers: condition Water services agreement shall include a capped maximum capacity for bridging water and bridging sewer until reuse water becomes available“shall include a capped maximum capacity for bridging water and bridging sewer until reuse water becomes available”News report · Sept. 2024 · grade C
- Rezoning proffers: deadline“the water service agreement will be submitted to the county within 60 days of approval of the rezoning”News report · Sept. 2024 · grade C
- Rezoning proffers: condition“if construction of the reuse water system has not begun by December 31, 2028, the Stafford Technology Center applicants shall undertake reasonable good faith efforts to assume the responsibility of constructing the system”News report · Sept. 2024 · grade C
- Stated capital cost: 1500000000 USD“general development plans that indicate the Stafford Technology Campus will be developed across five phases, with an estimated investment of more than $1.5 billion”News report · April 2023 · grade C
Permits and government (155)
- permit type=large load interconnection request; the grid-relevant state permit a: Draft permit noticed; DEQ tentative decision is to issue; comment period closed June 19, 2026; issuance not confirmed at capture“The proposed activity is the construction of a data center campus comprised of 21 data center buildings, 6 substations, and associated infrastructure on an approximately 537-acre project site.”State agency · June 2026 · grade A
- Owner companies: SI NVA07Campus, LLC“SI NVA07Campus, LLC; 1700 Broadway, Suite 1750, Denver, Colorado 80290; VWPP Permit Application No. 25-2511”State agency · May 2026 · grade A
- Virginia Water Protection Permit: draft permit noticed; tentative decision to issue“DEQ's tentative decision is to issue the permit”State agency · May 2026 · grade A
- Section 404 wetlands (Phase I): Phase I authorized under the 22-SPGP“Phase I of the project was previously authorized under the 22-SPGP”State agency · Jan. 2026 · grade A
- Section 404 individual permit: public notice issued; comments due March 18, 2026“The overall impacts for the proposed projects are: 2.20 acres of permanent impacts to wetlands and 4,733 linear feet (0.80 acre) of impacts to stream channel”State agency · Jan. 2026 · grade A
- CZM consistency review: public notice; comment period Jan 26 - Feb 20,2026“The applicant certifies that the project is consistent with the enforceable policies of the Virginia Coastal Zone Management Program”State agency · Jan. 2026 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed building project near Fredericksburg VA”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed building project near Fredericksburg VA”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed building project near Fredericksburg VA”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed building project near Fredericksburg VA”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed building project near Fredericksburg VA”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed building project near Fredericksburg VA”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed building project near Fredericksburg VA”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed building project near Fredericksburg VA”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed building project near Fredericksburg VA”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed building project near Fredericksburg VA”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed building project near Fredericksburg VA”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed building project near Fredericksburg VA”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Reevaluating“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Reevaluating“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Reevaluating“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Reevaluating“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Reevaluating“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Reevaluating“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Reevaluating“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Reevaluating“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Reevaluating“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Reevaluating“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Reevaluating“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Reevaluating“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Proposed cranes for building project in Fredericksburg VA. (2025-AEA-11027:11038-OE-ASNs for building filings)”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Project involves installation of 2 composite style water storage tanks. Each tank is 107 ft above ground level with a final overall height of 321 ft AMSL.”FAA · June 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2472-OE: Building C North Campus, Building, 140 ft AGL, 315 ft AMSL, 38.388225,-77.43143333, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2473-OE: Building C North Campus, Building, 140 ft AGL, 315 ft AMSL, 38.38884722,-77.43078056, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2474-OE: Building B North Campus, Building, 140 ft AGL, 315 ft AMSL, 38.38893333,-77.42897222, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2475-OE: Building A North Campus, Building, 140 ft AGL, 315 ft AMSL, 38.38984167,-77.42769722, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2476-OE: Building A North Campus, Building, 140 ft AGL, 315 ft AMSL, 38.38882222,-77.42613333, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2477-OE: Building B North Campus, Building, 140 ft AGL, 315 ft AMSL, 38.38756111,-77.42708889, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2478-OE: Building D North Campus, Building, 140 ft AGL, 315 ft AMSL, 38.38670278,-77.42748889, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2479-OE: Building D North Campus, Building, 140 ft AGL, 315 ft AMSL, 38.38616667,-77.42805556, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2480-OE: Building A South Campus, Building, 120 ft AGL, 280 ft AMSL, 38.38171667,-77.43284167, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2481-OE: Building A South Campus, Building, 120 ft AGL, 280 ft AMSL, 38.38333889,-77.43131667, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2482-OE: Building B South Campus, Building, 155 ft AGL, 315 ft AMSL, 38.38411389,-77.43180833, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2483-OE: Building B South Campus, Building, 155 ft AGL, 315 ft AMSL, 38.38473611,-77.43115278, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2484-OE: Building D South Campus, Building, 155 ft AGL, 315 ft AMSL, 38.38313333,-77.4287, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2485-OE: Building E South Campus, Building, 155 ft AGL, 315 ft AMSL, 38.38200556,-77.42667778, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2486-OE: Building F South Campus, Building, 155 ft AGL, 315 ft AMSL, 38.38073611,-77.42279722, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2487-OE: Building F South Campus, Building, 155 ft AGL, 315 ft AMSL, 38.37975556,-77.42326667, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2488-OE: Building C South Campus, Building, 135 ft AGL, 295 ft AMSL, 38.38023889,-77.430975, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2489-OE: Building C South Campus, Building, 135 ft AGL, 295 ft AMSL, 38.38104167,-77.43086389, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2490-OE: Building B East Campus, Building, 150 ft AGL, 315 ft AMSL, 38.38268611,-77.42156389, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2491-OE: Building A East Campus, Building, 150 ft AGL, 315 ft AMSL, 38.38350278,-77.42408889, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2492-OE: Building A East Campus, Building, 150 ft AGL, 315 ft AMSL, 38.38498056,-77.42331944, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2493-OE: Building C East Campus, Building, 150 ft AGL, 315 ft AMSL, 38.38563611,-77.42479722, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2494-OE: Building E East Campus, Building, 150 ft AGL, 315 ft AMSL, 38.387625,-77.42376111, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2495-OE: Building G East Campus, Building, 150 ft AGL, 315 ft AMSL, 38.38814167,-77.42148889, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2496-OE: Building G East Campus, Building, 150 ft AGL, 315 ft AMSL, 38.387375,-77.41911944, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2497-OE: Building D West Campus, Building, 115 ft AGL, 265 ft AMSL, 38.38065833,-77.43678611, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2498-OE: Building A West Campus, Building, 110 ft AGL, 260 ft AMSL, 38.38130833,-77.4395, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2499-OE: Building B West Campus, Building, 105 ft AGL, 255 ft AMSL, 38.38413611,-77.43718889, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2500-OE: Building C West Campus, Building, 100 ft AGL, 250 ft AMSL, 38.38561944,-77.43597778, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Evaluating“ASN 2024-AEA-2502-OE: Building F West Campus, Building, 165 ft AGL, 315 ft AMSL, 38.38833889,-77.43693333, Evaluating, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AEA-2503-OE: Building E West Campus, Building, 115 ft AGL, 265 ft AMSL, 38.38348611,-77.434475, Determined - No Hazard, submitted 2024-03-06”FAA · March 2024 · grade A
- FAA stack cases: 19 cases“2026-AEA-2424-OE Stack SDC Campus S1-S4; 2026-AEA-2425-OE Stack SDC Campus S1-S4; 2026-AEA-2426-OE Stack SDC Campus S1-S4; 2026-AEA-685-OE Stack Stafford S3&4 #2”FAA · Oct. 2026 · grade B
- Tallest structure filed with the FAA (ft): 85 ft“ASN 2026-AEA-12014-OE: BUILDING W-1, Building, 85 ft AGL, 243 ft AMSL, 38.38517,-77.43815, Studying, submitted 2026-10-13”FAA · Oct. 2026 · grade B
- FAA obstruction evaluation (7460-1): Studying“ASN 2026-AEA-12014-OE: BUILDING W-1, Building, 85 ft AGL, 243 ft AMSL, 38.38517,-77.43815, Studying, submitted 2026-10-13”FAA · Oct. 2026 · grade B
- FAA obstruction evaluation (7460-1): Evaluating“ASN 2026-AEA-11637-OE: Water Tower STC Reuse Water Storage Tanks, Derrick/Gantry Crane, 143 ft AGL, 357 ft AMSL, 38.39173,-77.42788, Evaluating, submitted 2026-09-28”FAA · Sept. 2026 · grade B
- expansion rezoning and proffer amendment: approved (reported)“The additional rezoning was approved by the board on June 16th, where a discussion around Tier 4 generators took place and was verbally accepted by STC's attorney”Dataset · Aug. 2026 · grade B
- FAA obstruction evaluation (7460-1): Evaluating“ASN 2026-AEA-3974-OE: W-6 CRANE CORNER 4, Crane, 139 ft AGL, 297 ft AMSL, 38.38600,-77.44054, Evaluating, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Evaluating“ASN 2026-AEA-3975-OE: W-6 CRANE CORNER 3, Crane, 139 ft AGL, 297 ft AMSL, 38.38501,-77.43854, Evaluating, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Evaluating“ASN 2026-AEA-3976-OE: W-6 CRANE CORNER 2, Crane, 139 ft AGL, 297 ft AMSL, 38.38571,-77.43788, Evaluating, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Evaluating“ASN 2026-AEA-3977-OE: W-6 CRANE CORNER 1, Crane, 139 ft AGL, 297 ft AMSL, 38.38674,-77.43994, Evaluating, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3978-OE: W-5 CRANE CORNER 4, Crane, 155 ft AGL, 313 ft AMSL, 38.38088,-77.43854, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3979-OE: W-5 CRANE CORNER 3, Crane, 155 ft AGL, 313 ft AMSL, 38.38250,-77.43724, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3980-OE: W-5 CRANE CORNER 2, Crane, 155 ft AGL, 313 ft AMSL, 38.38297,-77.43818, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3981-OE: W-5 CRANE CORNER 1, Crane, 155 ft AGL, 313 ft AMSL, 38.38140,-77.43945, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3982-OE: W-4 CRANE CORNER 4, Crane, 155 ft AGL, 313 ft AMSL, 38.38044,-77.43676, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3983-OE: W-4 CRANE CORNER 3, Crane, 155 ft AGL, 313 ft AMSL, 38.38163,-77.43580, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3984-OE: W-4 CRANE CORNER 2, Crane, 155 ft AGL, 313 ft AMSL, 38.38215,-77.43670, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3985-OE: W-4 CRANE CORNER 1, Crane, 155 ft AGL, 313 ft AMSL, 38.38091,-77.43769, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3986-OE: W-3 CRANE CORNER 4, Crane, 155 ft AGL, 313 ft AMSL, 38.38318,-77.43784, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3987-OE: W-3 CRANE CORNER 3, Crane, 155 ft AGL, 313 ft AMSL, 38.38216,-77.43579, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3988-OE: W-3 CRANE CORNER 2, Crane, 155 ft AGL, 313 ft AMSL, 38.38289,-77.43519, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3989-OE: W-3 CRANE CORNER 1, Crane, 155 ft AGL, 313 ft AMSL, 38.38389,-77.43719, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3990-OE: W-2 CRANE CORNER 4, Crane, 155 ft AGL, 313 ft AMSL, 38.38330,-77.43610, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3991-OE: W-2 CRANE CORNER 3, Crane, 155 ft AGL, 313 ft AMSL, 38.38487,-77.43483, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3992-OE: W-2 CRANE CORNER 2, Crane, 155 ft AGL, 313 ft AMSL, 38.38539,-77.43574, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3993-OE: W-2 CRANE CORNER 1, Crane, 155 ft AGL, 313 ft AMSL, 38.38377,-77.43704, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3994-OE: W-1 CRANE CORNER 4, Crane, 155 ft AGL, 313 ft AMSL, 38.38454,-77.43734, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3995-OE: W-1 CRANE CORNER 3, Crane, 155 ft AGL, 313 ft AMSL, 38.38577,-77.43634, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3996-OE: W-1 CRANE CORNER 2, Crane, 155 ft AGL, 313 ft AMSL, 38.38624,-77.43728, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-3997-OE: W-1 Crane Corner 1, Crane, 155 ft AGL, 313 ft AMSL, 38.38506,-77.43824, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-AEA-3998-OE: W-6 CRANE CORNER 4, Crane, 200 ft AGL, 358 ft AMSL, 38.38600,-77.44054, Reevaluating, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-AEA-3999-OE: W-6 CRANE CORNER 3, Crane, 200 ft AGL, 358 ft AMSL, 38.38501,-77.43854, Reevaluating, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-AEA-4000-OE: W-6 CRANE CORNER 2, Crane, 200 ft AGL, 358 ft AMSL, 38.38571,-77.43788, Reevaluating, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-AEA-4001-OE: W-6 CRANE CORNER 1, Crane, 200 ft AGL, 358 ft AMSL, 38.38674,-77.43994, Reevaluating, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-4002-OE: W-5 CRANE CORNER 4, Crane, 181 ft AGL, 339 ft AMSL, 38.38088,-77.43854, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-4003-OE: W-5 CRANE CORNER 3, Crane, 181 ft AGL, 339 ft AMSL, 38.38250,-77.43724, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-4004-OE: W-5 CRANE CORNER 2, Crane, 181 ft AGL, 339 ft AMSL, 38.38297,-77.43818, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-4005-OE: W-5 CRANE CORNER 1, Crane, 181 ft AGL, 339 ft AMSL, 38.38140,-77.43945, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-4006-OE: W-4 CRANE CORNER 4, Crane, 200 ft AGL, 358 ft AMSL, 38.38044,-77.43676, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-4007-OE: W-4 CRANE CORNER 3, Crane, 200 ft AGL, 358 ft AMSL, 38.38163,-77.43580, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-4008-OE: W-4 CRANE CORNER 2, Crane, 200 ft AGL, 358 ft AMSL, 38.38215,-77.43670, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-4009-OE: W-4 CRANE CORNER 1, Crane, 200 ft AGL, 358 ft AMSL, 38.38091,-77.43769, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-4014-OE: W-2 CRANE CORNER 4, Crane, 200 ft AGL, 358 ft AMSL, 38.38330,-77.43610, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-4015-OE: W-2 CRANE CORNER 3, Crane, 200 ft AGL, 358 ft AMSL, 38.38487,-77.43483, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-4016-OE: W-2 CRANE CORNER 2, Crane, 200 ft AGL, 358 ft AMSL, 38.38539,-77.43574, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-4017-OE: W-2 CRANE CORNER 1, Crane, 200 ft AGL, 358 ft AMSL, 38.38377,-77.43704, Determined - No Hazard, submitted 2026-03-26”FAA · March 2026 · grade B
- Section 404 Individual Permit (joint public notice with VA DEQ): Joint public notice issued; comment period Jan. 26, 2026 to Feb. 20, 2026; Phase I previously authorized under the 22-SPGP; final issuance not confirmed at captu“Stafford Technology Campus; VWP Permit No.25-2511; applicant SI NVA07Campus, LLC; VWPP Permit Application No. 25-2511”State agency · Feb. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-2424-OE: Stack SDC Campus S1-S4, Crane, 240 ft AGL, 313 ft AMSL, 38.38144,-77.43458, Determined - No Hazard, submitted 2026-02-17”FAA · Feb. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-2425-OE: Stack SDC Campus S1-S4, Crane, 240 ft AGL, 375 ft AMSL, 38.38717,-77.43344, Determined - No Hazard, submitted 2026-02-17”FAA · Feb. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-2426-OE: Stack SDC Campus S1-S4, Crane, 240 ft AGL, 384 ft AMSL, 38.38861,-77.43197, Determined - No Hazard, submitted 2026-02-17”FAA · Feb. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-2427-OE: Stack SDC Campus S1-S4, Crane, 240 ft AGL, 386 ft AMSL, 38.38353,-77.42344, Determined - No Hazard, submitted 2026-02-17”FAA · Feb. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-2428-OE: Stack SDC Campus S1-S4, Crane, 240 ft AGL, 355 ft AMSL, 38.37853,-77.42769, Determined - No Hazard, submitted 2026-02-17”FAA · Feb. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-1896-OE: Stack Stafford S1, Building, 65 ft AGL, 222 ft AMSL, 38.38036,-77.42924, Determined - No Hazard, submitted 2026-02-05”FAA · Feb. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-1897-OE: Stack Stafford S2, Building, 65 ft AGL, 220 ft AMSL, 38.38129,-77.43044, Determined - No Hazard, submitted 2026-02-05”FAA · Feb. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-1899-OE: Stack Stafford S3, Building, 65 ft AGL, 232 ft AMSL, 38.38309,-77.43152, Determined - No Hazard, submitted 2026-02-05”FAA · Feb. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-1901-OE: Stack Stafford S4, Building, 65 ft AGL, 235 ft AMSL, 38.38431,-77.43211, Determined - No Hazard, submitted 2026-02-05”FAA · Feb. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-683-OE: Stack Stafford S3&4 #1, Crane, 220 ft AGL, 398 ft AMSL, 38.38328,-77.43154, Determined - No Hazard, submitted 2026-01-20”FAA · Jan. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-685-OE: Stack Stafford S3&4 #2, Crane, 220 ft AGL, 315 ft AMSL, 38.38162,-77.43314, Determined - No Hazard, submitted 2026-01-20”FAA · Jan. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-689-OE: Stack Stafford S3&4 #3, Crane, 220 ft AGL, 318 ft AMSL, 38.38112,-77.43237, Determined - No Hazard, submitted 2026-01-20”FAA · Jan. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-692-OE: Stack Stafford S3&4 #4, Crane, 220 ft AGL, 388 ft AMSL, 38.38363,-77.42962, Determined - No Hazard, submitted 2026-01-20”FAA · Jan. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-693-OE: Stack Stafford S3&4 #5, Crane, 250 ft AGL, 361 ft AMSL, 38.38493,-77.43169, Determined - No Hazard, submitted 2026-01-20”FAA · Jan. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-694-OE: Stack Stafford S3&4 #6, Crane, 220 ft AGL, 326 ft AMSL, 38.38429,-77.43236, Determined - No Hazard, submitted 2026-01-20”FAA · Jan. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-677-OE: Stack Stafford S1&2 #1, Crane, 220 ft AGL, 372 ft AMSL, 38.38148,-77.42708, Determined - No Hazard, submitted 2026-01-15”FAA · Jan. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-679-OE: Stack Stafford S1&2 #2, Crane, 220 ft AGL, 367 ft AMSL, 38.37986,-77.42874, Determined - No Hazard, submitted 2026-01-15”FAA · Jan. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-680-OE: Stack Stafford S1&2 #3, Crane, 220 ft AGL, 358 ft AMSL, 38.38128,-77.43068, Determined - No Hazard, submitted 2026-01-15”FAA · Jan. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-681-OE: Stack Stafford S1&2 #4, Crane, 220 ft AGL, 374 ft AMSL, 38.38291,-77.42902, Determined - No Hazard, submitted 2026-01-15”FAA · Jan. 2026 · grade B
- FAA OE/AAA filings evidence vertical construction at STACK Infrastructure's Stafford Technology Campus (Stafford VA): 61 filings fall inside the campus outline or within 1 km of it - 19 filed under the developer's own na“ASN 2026-AEA-680-OE: Stack Stafford S1&2 #3, Crane, 220 ft AGL, 358 ft AMSL, 38.38128,-77.43068, Determined - No Hazard, submitted 2026-01-15”FAA · Jan. 2026 · grade B
- air permit (backup generators): not found“No DEQ air permit public notice for SI NVA07Campus / Stafford Technology Campus appears on the VA DEQ air public notices page as of 2026-10-18”State agency · Oct. 2026 · grade C
- site plan: not verified“No text-accessible site-plan record for the Stafford Technology Campus was available from the Stafford County development review page as checked”Local government · Oct. 2026 · grade C
- Board of Supervisors moving to remove data centers from Technology Zone incentives; county EDA director stated no data center developer had applied for those incentives - consistent with STC holding no county incentive a“Stafford Economic Development Director Liz Barber said the county hasn't seen any data center developers apply for the incentives Vanuch questioned”News report · Oct. 2026 · grade C
- Stafford County Planning Commission: RC25156486 expansion rezoning (34.94 acres) public hearing“On May 13th,2026, STACK Infrastructure went before the planning commission in request to rezone an additional 34.94 acres”Dataset · Aug. 2026 · grade C
- Stafford County Board of Supervisors: RC25156486 expansion rezoning and proffer amendment“The additional rezoning was approved by the board on June 16th”Dataset · Aug. 2026 · grade C
- grandfathering ordinance: adopted“The Stafford Board of Supervisors voted unanimously to allow the Stafford Technology Campus, Potomac Church Tech Center, Centreport Gateway/Pemberton development, the Vantage VA-4 development, and the Cranes Corner Data Center to continue”News report · Dec. 2025 · grade C
- STC grandfathered under pre-Oct 21, 2025 county rules (ordinance O25-29R); later changes limited to those directly attributable to the approved project“developers could make later changes that were directly attributable to the already approved project”News report · Dec. 2025 · grade C
- Stafford County Board of Supervisors: Stricter data center ordinance adopted (750-ft residential setbacks, generator and noise rules)“supervisors made strict changes, the most significant of which requires data center buildings to be 750 feet from adjacent homes, schools, or the Rappahannock and Potomac rivers”News report · Dec. 2025 · grade C
- Stafford County Board of Supervisors: Grandfathering ordinance O25-29R“The supervisors' Tuesday vote was necessary because their October decision didn't address grandfathering, which is common when regulations change after projects have already been approved”News report · Dec. 2025 · grade C
- Stafford County Board of Supervisors: Water and Wastewater Infrastructure Agreement authorization“Supervisors unanimously authorized a water and wastewater infrastructure agreement with the developer of the Stafford Technology Campus”News report · April 2025 · grade C
- Rezoning date: Sept. 17, 2024“In a 6-to-1 vote, the supervisors approved the county's largest data center project to date”News report · Sept. 2024 · grade C
- rezoning: approved 6-1“In a 6-to-1 vote, the supervisors approved the county's largest data center project to date”News report · Sept. 2024 · grade C
- comprehensive plan amendment: approved“That resolution also altered the future land use map to designate the area as being in a targeted development area for business and industry”News report · Sept. 2024 · grade C
- Stafford County Board of Supervisors: COM23154932 comp plan amendment and RC23154931 rezoning approval“History was made Tuesday night at the Stafford County Board of Supervisors meeting. In a 6-to-1 vote, the supervisors approved the county's largest data center project to date”News report · Sept. 2024 · grade C
- Stafford County Board of Supervisors: Stafford Technology Campus comp plan amendment and rezoning (public hearing)“Stafford Technology Campus comp-plan and rezoning deferred to Sept. 17 with application extension (unanimous)”News report · Aug. 2024 · grade C
Legal (2)
- Source record“COM26157239; Amendment to the Stafford County Comprehensive Plan - Eskimo Hill Technology Center”Local government · Oct. 2026 · grade A
- Opposition: County-wide organized opposition to data center growth (e.g., Save Stafford); residents opposed STC grandfathering in Dec 2025; no STC-specific lawsuit found“Five Stafford data center projects that were approved before the locality enacted stricter regulations were grandfathered Tuesday night”News report · Oct. 2026 · grade C
Site and other (28)
- Parcel IDs current: 38-124; 38-124A; 38-124B; 38-29A; 38-29B; expansion: 38-122; 38-122A; 38-123A; 38-29; 38-30“These amendments pertain to Tax Map Parcel Nos. 38-124,38-124A,38-124B,38-29A and 38-29B, which collectively consist of 503.84 acres”Local government · Oct. 2026 · grade A
- Address: 1318 Richmond Highway, Stafford County, VA“The project is located at 1318 Richmond Highway in Stafford County, Virginia”State agency · May 2026 · grade A
- Aliases: STC; Stafford Technology Center (USACE and 2024 county-era name)“The applicant requests authorization to construct a Data Center Campus to be known as Stafford Technology Center and associated infrastructure”State agency · Jan. 2026 · grade A
- Acres: 537 acres“The project site is approximately 537 acres and would affect waters of the United States associated with Accokeek Creek”State agency · Jan. 2026 · grade A
- Construction stage: under construction (earlier phases)“The existing site is currently under construction according to earlier phases of the proposed project”State agency · Jan. 2026 · grade A
- Parcel IDs: 38-124; 38-29A“is the owner of the properties identified as Tax Map Numbers 38 124 and 38 29A, which is comprised of approximately 503.84”Local government · March 2024 · grade A
- Acres: 503.84 acres“The proposal is to reclassify the Property from A-1, Agricultural, to M-2, Heavy Industrial”Local government · March 2024 · grade A
- Full build-out date: 2030“The Site is anticipated to be complete and in operation by 2030”Local government · Feb. 2024 · grade A
- Topping-out ceremony for the first building, per Stafford County EDA Year End Review“Stafford Technology Campus Topping Out Ceremony May 5,2026”Local government · Aug. 2026 · grade B
- Construction stage: first building topped out; fit-out and later phases ongoing“Stafford Technology Campus Topping Out Ceremony May 5,2026”Local government · May 2026 · grade B
- Name: Stafford Technology Campus“STACK Infrastructure today announced its largest flagship development to date: the 1+GW Stafford Technology Campus (STC) in Stafford County, Virginia”Company · Jan. 2025 · grade B
- Developer: STACK Infrastructure“today announced its largest flagship development to date: the 1+GW Stafford Technology Campus (STC) in Stafford County, Virginia”Company · Jan. 2025 · grade B
- Operator: STACK Infrastructure“STACK, the digital infrastructure partner to the worlds most innovative companies and a leading global developer and operator of data centers”Company · Jan. 2025 · grade B
- Acres: 500 acres“the campus spans 500 acres, features four sub-campuses, and will house a total of 19 data centers”Company · Jan. 2025 · grade B
- Phases: 4 sub-campuses“the campus spans 500 acres, features four sub-campuses, and will house a total of 19 data centers”Company · Jan. 2025 · grade B
- Announced: Jan. 16, 2025“today announced its largest flagship development to date: the 1+GW Stafford Technology Campus”Company · Jan. 2025 · grade B
- Construction jobs peak: 1000+ jobs“creating hundreds of well-compensated full-time jobs and over 1,000 construction jobs during peak development”Company · Jan. 2025 · grade B
- Current target date: 2027“The first phase is expected to break ground this year and be completed by 2027”News report · Oct. 2026 · grade C
- Stage: building - real construction, speculative tenancy“Stack Infrastructure has completed external construction work on the first building at its new campus in Stafford County”News report · Oct. 2026 · grade C
- Dominion Energy Virginia reports approximately 70 GW of large-load delivery points in its interconnection queue (about 25 GW assigned projected connection dates through end-2031; a further 45 GW under study) under the qu“The utility, which serves most of Virginia, said it has approximately 70GW of large-load delivery points (DP) within its interconnection queue”News report · Oct. 2026 · grade C
- Source record“The 116-acre Copper Ridge Data Center Campus could see up to eight two-story data center buildings developed totaling 2.36 million sq ft”News report · Aug. 2026 · grade C
- Cooling: reclaimed (reuse) water cooling planned; potable bridging supply initially“purple pipe infrastructure for reclaimed cooling water is currently being built”Dataset · Aug. 2026 · grade C
- Independent water-quality study of the site documents three streams,~72 acres of Resource Protection Areas, and listed species on site (northern long-eared bat, tricolored bat, monarch butterfly, small whorled pogonia)“several endangered and threatened species have inhabited the STC property, including: the Northern long-eared bat, tricolored bat, monarch butterfly, and the small whorled pogonia”Dataset · Aug. 2026 · grade C
- Construction stage: under construction first building topped out“Stack Infrastructure has completed external construction work on the first building at its new campus in Stafford County”News report · May 2026 · grade C
- Workforce estimate: 425,000+ work hours; ~3M cubic yards of earth moved; 4,000 ft of retaining walls in the first year“project teams have recorded more than 425,000 hours of work, moved around three million cubic yards of earth”News report · May 2026 · grade C
- Land control date: Jan. 2025“STACK announced the STC development in January, after acquiring more than 500 acres from Peterson Cos.”News report · March 2025 · grade C
- Original target date: 2027“The first phase is expected to break ground this year and be completed by 2027”News report · March 2025 · grade C
- Water use stated: ~1 MGD bridging (potable) water until reuse water becomes available“these upgrades will not only bring the 1 million gallons of water the project needs until the reuse water is available”News report · Sept. 2024 · grade C
Imagery and records: Aerial imagery: local aerial photography via Esri World Imagery Wayback. County deeds: ATTOM.