The site from above
Power and the grid
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Sept. 9, 2026Utility MW on record460 MW. News report · Sept. 2026
Permits checklist
1 granted · 4 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- ✓Zoning approval GrantedCity of Rockingham · Sept. 8, 2026: Rezoning approved by City of Rockingham. News report · Sept. 2026
- –Checked, nothing on file: Site plan, Building permit, Water and wetlands permits, Utility and grid approval
What happened, and what is due
- Aug. 10, 2026Site Project first appears in the public record
- Sept. 8, 2026Permits Rezoning approved by City of Rockingham. News report · Sept. 2026
Since Oct. 2026: 1 satellite capture. Satellite · Oct. 2026
Owners, partners and builders
- Terra Nexus Ventures, developer
- Duke Energy, utility
- City of Rockingham, public agency
Open questions
- Signed electric service agreement and delivery date.
- Whether site work has started.
20 records from 4 documents
Drawn from news reports, public and commercial datasets and satellite captures, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (4)
- Utility service: 460 MW“Terra Nexus will be paying Duke Energy for the upgraded infrastructure related to the project, which will require 460 megawatts by full build-out of the four buildings”News report · Sept. 2026 · grade C
- Role of the on-site plant: backup“no air quality permit would be required for the 192 backup diesel generators, that would be used only in emergencies”News report · Sept. 2026 · grade C
- On-site power technology: diesel generators (192 units, backup)“no air quality permit would be required for the 192 backup diesel generators, that would be used only in emergencies”News report · Sept. 2026 · grade C
- Utility: Duke Energy“Terra Nexus will be paying Duke Energy for the upgraded infrastructure related to the project”News report · Sept. 2026 · grade C
Money and contracts (2)
- grid upgrade cost responsibility: stated at rezoning hearing Sept. 8, 2026“Terra Nexus will be paying Duke Energy for the upgraded infrastructure related to the project, which will require 460 megawatts by full build-out of the four buildings”News report · Sept. 2026 · grade C
- The project was presented to the City Council as a $1.2 billion investment with no incentives offered by the city, more than doubling the city's current tax base.“the proposed data center project would be a $1.2 billion investment — with no incentives being offered by the city”News report · Sept. 2026 · grade C
Permits and government (5)
- Project status: conditional rezoning approved Sept. 8, 2026 (4-1); pre-construction; four-building build-out expected over about six years“The motion carried 4-1, with Mayor John Hutchinson thanking those concerned for their calls and emails as they filed out of the chamber”News report · Sept. 2026 · grade C
- Site acreage: 165 acres“At issue was the rezoning of 165 acres of land from high density residential to conditional light industrial”News report · Sept. 2026 · grade C
- County code: 37153“a majority of the City Council voted to rezone property on Old Cheraw Highway for a proposed data center”News report · Sept. 2026 · grade C
- rezoning: approved 4-1“At issue was the rezoning of 165 acres of land from high density residential to conditional light industrial”News report · Sept. 2026 · grade C
- At the hearing, residents challenged the assertion that no air quality permit would be required for the campus's 192 backup diesel generators (emergency use only, tested 8 a.m.-5 p.m. weekdays under the conditions). No a“no air quality permit would be required for the 192 backup diesel generators, that would be used only in emergencies”News report · Sept. 2026 · grade C
Site and other (2)
- Campus name: Terra Nexus Rockingham“the landowners and developers, Terra Nexus, had made several adjustments to the plan”News report · Sept. 2026 · grade C
- Announced: Aug. 10, 2026“Terra Nexus Land Fund I, LLC has submitted an application to rezone just more than 165 acres on Old Cheraw Highway — from high density residential to conditional light industrial — to develop a data center”News report · Aug. 2026 · grade C
Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).