Power and the grid
The plan on record is a grid connection. A serving utility is named, but no signed service agreement is on record.
We checked utility filings, regulator dockets and air-permit records for this campus.
Permits checklist
5 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- –Checked, nothing on file: Zoning approval, Site plan, Building permit, Water and wetlands permits, Utility and grid approval
What happened, and what is due
- Jan. 2026Site Land purchase on record. News report · June 2026
- June 1, 2026Site Project first appears in the public record
Since Oct. 2026: 1 satellite capture. Satellite · Oct. 2026
Owners, partners and builders
- Legacy Investing, developer
Open questions
- Signed electric service agreement and delivery date.
- Whether site work has started.
15 records from 3 documents
Drawn from news reports, satellite captures and public and commercial datasets, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (7)
- Utility: Guadalupe Valley Electric Cooperative (GVEC)“GVEC serves over 76,000 meters throughout 13 counties, primarily in DeWitt, Gonzales, Guadalupe, Lavaca, and Wilson Counties”Dataset · Oct. 2026 · grade C
- Campus name: Legacy Investing - 1000 Bolton Road (Marion)“The company this week announced plans for a 50MW development at 1000 Bolton Rd in Marion, Guadalupe County”News report · June 2026 · grade C
- Stated campus size: 50 MW“The company this week announced plans for a 50MW development at 1000 Bolton Rd in Marion, Guadalupe County”News report · June 2026 · grade C
- Stated campus size: 150 MW“Legacy noted the site has the potential to expand to 150MW”News report · June 2026 · grade C
- Street address: 1000 Bolton Road, Marion, TX“announced plans for a 50MW development at 1000 Bolton Rd in Marion, Guadalupe County”News report · June 2026 · grade C
- County code: 48187“announced plans for a 50MW development at 1000 Bolton Rd in Marion, Guadalupe County”News report · June 2026 · grade C
- Announced: June 1, 2026“The company this week announced plans for a 50MW development at 1000 Bolton Rd in Marion, Guadalupe County.”News report · June 2026 · grade C
Money and contracts (1)
- land purchase: closed“1000 Bolton Road was previously home to the San Antonio Karting Complex, a karting race track that opened in 2020 but was recently up for sale”News report · June 2026 · grade C
Site and other (2)
- Project status: Announced June 2026; under development on the former San Antonio Karting Complex site (the track closed in January 2026 on the sale); expected ready for service in Q4 2027 per the developer via DCD. No co“The project - located some 26 miles east of San Antonio - is currently under development and is expected to be ready for service in Q4 2027”News report · June 2026 · grade C
- Site acreage: 39 acres“The company said the 39-acre site will feature more than 100,000 sq ft (9,290 sqm) of data hall space across approximately 243,000 sq ft (22,575 sqm) total”News report · June 2026 · grade C
Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).