Data center profile · Highway 18, about 17 miles north of Fort Stockton, Pecos County, Texas

GW Ranch

Amazon's off-grid data-center campus north of Fort Stockton, Texas, to run on Pacifico Energy's private gas plant, permitted for 7,650 MW, with no grid connection

Early construction. Amazon has cleared land, filed three buildings due in Dec. 2026 and is hiring commissioning staff (press and job posts). The 7,650 MW gas permit is in hand, but no turbine delivery, gas contract or pipeline permit is on record.
The construction core before any work began, Satellite image, March 18, 2025
7,650 MW
gas generation the state air permit allows
gross ceiling; about 5,000 MW nominal in the application
5 GW
dedicated power the developer markets
developer says; gas, batteries and solar combined
8,000 acres
site Amazon bought from Pacifico
Aug. 2026; price not disclosed (press)
3
data-center buildings Amazon has filed with the state
189,000 sq ft each, due Dec. 2026 (press)
OperatorPacifico Energy (power plant); Amazon (data centers)
CustomerAmazon (owns the site and buys the plant's power)
Planned IT capacity4.0 GW at full build-out (our estimate from the company or utility power figure)
First building in serviceOur estimate: 2028 (range 2027 to 2029).
Next deadlineJuly 21, 2027: Air permits void if power-plant construction has not begun
The site

A construction core by Highway 18, away from the permitted plant site

The active construction core on Oct. 11, 2026, seen at coarse 10-meter resolution: a large graded hall complex east of Highway 18 and a power yard west of it. The spot named in the gas plant's air permit, about 1.2 miles southwest, is still untouched rangeland. The newest sharp picture of the ranch dates from March 18, 2025, before any work, so the build so far has been seen only by coarser satellites. No substation has been found on the site.

Satellite overview12
Lower-resolution satellite image, Oct. 11, 2026. Pins placed from site coordinates.
  1. 1Data hall construction core
    east of Highway 18; the complex runs past the edge of this map
  2. 2Power yard
    west of Highway 18: graded pads and about 10 round objects
  3. 3Permitted gas plant site
    about 1.2 miles southwest, off this map; still untouched rangeland
From orbit

Rangeland to a building site in under four months

As late as June 23, 2026 this was rangeland east of Highway 18. By Oct. 11, 2026 a large graded complex had spread across it, with big rectangular structures or pads, internal roads and work yards, and it runs past the edges of this view. At this coarse resolution, finished roofs cannot be told apart from bare pads.

Rangeland to a building site in under four months
Ground map drawn from the lower-resolution image: vegetation, nothing builtbare or graded groundroofsgravel and padsequipment, asphalt or waterEdges are accurate to about 10 m.
Lower-resolution satellite image, Oct. 11, 2026
From orbit

A power yard of pads and about ten round objects

West of the highway, open rangeland as late as June 23, 2026 held a new road grid and graded pads by Oct. 11, one of them carrying about ten dark round objects 10 to 20 meters across. They could be tanks, pads or foundations; no turbine can be made out at this resolution.

A power yard of pads and about ten round objects
Ground map drawn from the lower-resolution image: vegetation, nothing builtbare or graded groundroofsgravel and padsequipment, asphalt or waterEdges are accurate to about 10 m.
Lower-resolution satellite image, Oct. 11, 2026
Quarter by quarter

Rangeland to a graded complex in one summer

Ground first broke in summer 2026: the July 8, 2026 frame shows new haul roads and the first graded pads. By Oct. 1, 2026 one large graded complex straddles Highway 18, with hall pads east of it and power-yard pads west of it, no closed roof yet, and the permitted plant site still untouched.

Satellite view of the campus, Oct. 1, 2026

Sentinel-2 satellite, 10 m resolution (coarser than the photos above).
Construction from orbit

What the satellites see on the ground

From orbit, bright graded ground shows only in the latest images (Oct. 2026), and radar shows no structures rising yet. No new roof shows by Oct. 2026. That fits our stage: site work.

Construction from orbit, as a share of the site: bare ground (left scale); roof and very bright radar echoes (right scale)
0123%0255075100%2023Jul2024Jul2025Jul2026Jul▲ Permits▲ Site workBare groundRoofRadar: bright echoes
0123%0255075100%2023202420252026▲ Permits▲ Site workBare groundRoofRadar: bright echoes
Roof: the highest 5-month median so far (roofs do not come down), dots are single months; bare ground: 3-month median; radar: 2-month median. Contains modified Copernicus Sentinel data 2023–2026.

How this works: Sentinel-2 photographs the ground every few days at 10 m. For each month we keep the cloud-free views over a 1.5 km square around the site point (no outline is mapped) (about 560 acres) and count the share that reads as bare ground and the share that reads as roof (very bright, not vegetated). Sentinel-1 radar sees through cloud every 6–12 days; walls and steel bounce the signal straight back, so the share of very bright radar echoes rises as buildings go up. Bright gravel pads and fresh concrete can read as roof, and wet or snowy months dip, so we read the trend, not single months. Black ticks mark our stage dates. Data: Copernicus Sentinel-1 and Sentinel-2, via the Copernicus Data Space Ecosystem.

Power

Power and the grid

None energized or contracted yet · 7,650 MW permitted

Gas turbines (35 units, simple cycle)Permitted, not built
7,650 MW
air-permit ceiling; about 5,000 MW nominal. 21 Siemens SGT-800 units at 62.5 MW plus 14 large-frame units whose maker the Aug. 2025 application left open State agency · Jan. 2026
Battery storagePlanned
1,840 MW
920 MWh in the air-permit application; the developer cites 1.8 GW State agency · Aug. 2025
SolarPlanned (developer)
750 MW
MWac, developer figure; not part of the gas permit Company · Jan. 2026
PermittedProposed

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. Aug. 4, 2025
    Designed to run islanded
    The air-permit application says the plant will neither buy power from nor sell power to the grid. State agency · Aug. 2025
  2. Jan. 21, 2026
    7,650 MW gas permit issued
    Texas issues the air, deterioration-prevention and greenhouse-gas permits; construction must begin by July 21, 2027. State agency · Jan. 2026
  3. Jan. 26, 2026
    Developer says turbines are secured
    Pacifico says turbines are secured and first power comes in the first half of 2027; no turbine delivery has been reported. Company · Jan. 2026
  4. Aug. 7, 2026
    Amazon to buy the plant's output
    Amazon confirms it will buy power from Pacifico's plant; term, price and volume are not public (press). News report · Aug. 2026
  5. Not set
    Gas supply: not signed
    Pacifico plans a 15-mile lateral to the Waha hub carrying 1 Bcf a day; no pipeline permit or gas contract was found. see Permits
  6. Not set
    Grid connection: none sought
    No ERCOT interconnection or large-load request was found; Amazon says the campus is designed to move to grid service later. see Permits

Grid upgrades

No grid upgrade for this campus's load is on record. Related grid records in the area:

What is next door

campus4.48 km · 69 kV line (Oncor)10.61 km · 345 kV line10.89 km · substationcampus4.48 km · 69 kV line (Oncor)10.61 km · 345 kV line10.89 km · substation

The plant is islanded, so none of these lines serves it. No gas pipeline is mapped within 30 km. Distances from mapped lines and plants. OpenStreetMap · Oct. 2026

Is it running?

Evidence from space

NO2 over the site, net of the rural background, was lower in July–September 2026 (5 µmol/m²) than a year earlier (6), a 22% drop that is within normal swings at this level; the rural background rose 11% (13 to 15). The satellite sees no new combustion large enough to stand out here. On record here: Gas turbines (35 units, simple cycle), 7,650 MW, permitted. No rise fits a plant that is not running yet, or runs little; it does not prove either. This campus has no plant running yet; it is here as a check that the method does not invent rises.

See all campuses checked →

NO2 over the campus and over open country (µmol/m²)
020406080Jan 2025AprJulOctJan 2026AprJulOctOver the campusOpen country
020406080Jan 2025JulJan 2026JulOver the campusOpen country
Lines: 7-day (daily) / 3-week (weekly) averages; gaps from cloud filled by straight-line interpolation; dots are raw readings. Shaded: July–September 2025 and 2026, averaging 6 and 5 µmol/m² above open country (0.8×).

What else could explain it

How this works: the Sentinel-5P satellite measures NO2 in the air over every point on Earth once a day, around 1:30 p.m. local time, in pixels about 5.5 by 3.5 km. NO2 comes from burning fuel (turbines, engines, traffic, power plants), so a rise over a site that open country does not share points to new combustion there. It shows combustion activity, not megawatts. The site box is about 15 km across; the background box is open country about 69 km away. We use only high-quality readings and drop days or weeks when cloud hides more than half of either box. Data: Copernicus Sentinel-5P (ESA), processed with the Copernicus Data Space Ecosystem Sentinel Hub statistics service.

Permits

Permits checklist

1 pending · 3 granted · 4 checked, nothing on file

The power plant carries the big approvals. In unincorporated Pecos County there is no county zoning or building permit step.

Risks

What could slow it down

Money

Money on record

~$12B
developer's estimate of the investment needed
Feb. 2026 comments reported by ENR (press) News report · Aug. 2026
~$300M each
estimated cost of Amazon's three buildings
from state registrations, as reported by ENR (press) News report · Aug. 2026

Not on record: price Amazon paid for the site: not disclosed, no deed or closing date found News report · Oct. 2026; terms of Amazon's power purchase: not disclosed, term, price and volume are not public News report · Aug. 2026; county or state tax abatement: Pacifico markets possible abatement and tax-credit upside Company · Oct. 2026; project financing: none disclosed, neither company named a cost or lender (press) News report · Aug. 2026

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Sept. 2024
    Paper trail Pacifico GW LLC registered in Delaware and Texas
  2. Aug. 4, 2025
    Permits Pacifico files for air permits for a 35-turbine, roughly 5,000 MW islanded gas plant State agency · Aug. 2025
  3. Aug. 20, 2025
    Site Pacifico announces GW Ranch: 5 GW of off-grid power, 1 GW by 2028 and 5 GW by 2030; the county judge backs it Company · Aug. 2025
  4. Jan. 21, 2026
    Permits Texas issues air permits for up to 7,650 MW of gas generation State agency · Jan. 2026
  5. Jan. 26, 2026
    Power Pacifico says turbines are secured and moves first power up to the first half of 2027 (developer says) Company · Jan. 2026
  6. March 13, 2026
    Site Three U.S. senators send Pacifico questions on emissions, carbon capture, gas supply and its data-center partners State agency · March 2026
  7. July 24, 2026
    Construction Satellite imagery shows land clearing under way (press) News report · Aug. 2026
  8. Aug. 7, 2026
    Money Amazon confirms it bought the site and will buy power from the plant News report · Aug. 2026
  9. Aug. 2026
    Construction Amazon files three 189,000 sq ft data-center buildings with the state (press) News report · Aug. 2026
  10. Oct. 14, 2026
    Construction Amazon posts data-center commissioning and controls jobs in Coyanosa, Pecos County Company · Oct. 2026
  11. Dec. 2026
    Construction Amazon's three buildings due for completion (press) News report · Aug. 2026
  12. 2027
    Power Developer's target for first power: Q1 2027 on its website, first half of 2027 in January Company · Oct. 2026
  13. July 21, 2027
    Permits Air permits void if power-plant construction has not begun State agency · Jan. 2026
Construction activity

Building activity by quarter

Since Feb. 2022: 1 FAA filing (Oct. 2026): a 300 ft crane; 75 satellite captures.

FAA filings
Satellite
’22
’23
’24
’25
’26
Dot size: records in the quarter, largest = 6. Two-digit years mark each first quarter.
The buildings

Specs

8,400 acres
site in the permit application; about 1,500 acres to be built on
567,000 sq ft
three 189,000 sq ft buildings filed by Amazon (press)
35 turbines
21 Siemens SGT-800 plus 14 large-frame units, maker open in the application
33M tons
CO2e a year, the permitted greenhouse-gas ceiling (Senate summary)
Who is involved

Owners, partners and builders

Owners
  • Amazon: bought the site in Aug. 2026 and is building the data centers
  • Pacifico Energy (Pacifico GW LLC): keeps, builds and will run the power plant, selling its output to Amazon
  • Pacifico Group: parent investment firm of Pacifico Energy (press)
Decision-makers
  • Texas Commission on Environmental Quality: issued the air permits
  • Middle Pecos Groundwater Conservation District: well permits
  • Texas Department of Licensing and Regulation: building registrations
  • Pecos County Judge Joe Shuster: endorsed the project; no county vote found
Power partners
  • Siemens Energy: 21 SGT-800 turbines named in the permit application
  • Wärtsilä: two 18.8 MW gas engines named in the application
  • Large-frame turbine maker: not chosen in the application (Doosan, GE, Mitsubishi or Siemens models)
Builders and advisers
  • Gensler: architect for the three buildings (press)
  • TRC Environmental: prepared the air-permit application
Oversight
  • Senators Whitehouse, Heinrich and Van Hollen: oversight letter, March 2026
  • Pacifico CEO Nate Franklin and VP Constantyn Gieskes: letter recipients
Still unknown

Open questions

Where this comes from

321 records from 27 documents

Drawn from news reports, company statements, state agency records, business registries, public and commercial datasets, satellite captures, our own analysis and local government records, each kept with its date and source. The bar shows documents by type.

News report 9Company 9State agency 5Dataset 4Satellite 1Analysis 1Local government 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (34)
  • Senate EPW and ENR ranking members (Whitehouse, Heinrich, Van Hollen) send Pacifico an oversight letter with seven interrogatories on GW Ranch emissions, carbon capture, gas sourcing and undisclosed data-center partners;
    “I write to request information about Pacifico Energy Group's plans to power a campus of hyperscale data centers in Pecos County, TX”
  • Interconnection status: none - off-grid private grid by design: built without a connection to the larger electricity grid, with no ERCOT interconnection request, study or agreement and no PUCT position public. Amazon sta
    “GW Ranch is being built without a connection to the larger electricity grid to enable direct customer control over schedule, energy supply, cost stability, and scalability.”
  • Nearest substation: 10.89 km
    Measured on OpenStreetMap map data.
  • Nearest transmission line: 4.48 km
    Measured on OpenStreetMap map data.
  • Nearest gas pipeline: none mapped within 30 km
    Measured on OpenStreetMap map data.
  • Permitted GHG ceiling (~33M tpy CO2e) would make GW Ranch the largest permitted single source in the US, roughly double the actual 2023 emissions of Plant Miller, the largest current emitter (~16.6M tons). Permitted cei
    “The GW Ranch Project would also be the country's largest air polluter”
  • On-site generation: 750 MW
    “Total Gross Capacity: 7.65 GW (Gas) + 1.8 GW (Battery Energy Storage) + 750 MWac (Solar)”
  • Current target date: H1 2027 (first power); 2028 (first phase online); 2031 (full buildout)
    “GW Ranch will provide customers with power in the first half of 2027 with a guaranteed pathway to scale to over 5 GW”
  • Gas supply: 15-mile, 1 Bcf/d pipeline lateral to Waha hub; multiple laterals (company claim)
    “Gas Supply: Multiple laterals, including a 15-mile 1 BCF/d direct pipeline to Waha for unmatched gas supply optionality”
  • Pacifico states turbines secured and first power H1 2027. Treat as unverified: the Aug 2025 permit application states the large-frame turbine OEM had NOT been selected (envelope permitting), and no turbine delivery at th
    “With all site delineations complete, permits in-hand, and turbines secured, GW Ranch will provide customers with power in the first half of 2027”
  • Portfolio figures are NOT campus facts: Pacifico markets 8,000 MW of US private-grid projects in development and a 10 GW global pipeline; its other Texas project, the 456 MW Ft. Spunky campus near Dallas (subject of sepa
    “In the U.S., Pacifico is developing 8,000 MW of private grid projects supporting AI-Infrastructure or datacenter needs”
  • First announced: Aug. 20, 2025
    “Pacifico Energy today announced plans for the GW Ranch project, an off-grid power generation campus that has been in development since early 2024”
  • Pacifico Energy publicly unveils GW Ranch: 5 GW off-grid private-grid campus in Pecos County, in development since early 2024, TCEQ permitting initiated, county officials supportive. Original schedule: 1 GW online 2028,
    “Pacifico Energy today announced plans for the GW Ranch project, an off-grid power generation campus that has been in development since early 2024”
  • Stated campus size: 5,000 MW
    “GW Ranch's unique approach will provide 5 gigawatts (GW) of dedicated, highly reliable power by combining high-efficiency natural gas turbines and advanced battery storage”
  • Name: GW Ranch
    “The new power plant (the Project) will operate under the name GW Ranch Energy Center (GW Ranch)”
  • IT capacity: not stated
    “The Project's nominal generation capacity will be approximately 5,000 MW”
  • Generating units on the permit: 35 natural gas turbines (mix of small and large-scale) under TCEQ Permit 181033 / PSDTX1672 / GHGPSDTX255, 7,650 MW total permitted gas capacity
    “Permits show that the gas plant would comprise 35 turbines, generating up to 7.65GW of power capacity.”
  • Pacifico met Brewster County officials about a similar data-center and power-plant project on a ~8,400-acre ranch northwest of Alpine (Texas Public Radio reporting), a separate, earlier-stage proposal, not an expansion
    “Pacifico Energy, the company developing a massive natural gas power plant and AI data center for retail giant Amazon in Pecos County, met with officials in neighboring Brewster County on Tuesday”
  • Likewise Pacifico's Sep 2026 Brewster County (Glass Mountains) pitch is a separate proposed site
    “The GW Ranch campus is located about 30 miles from an off-grid data center complex being developed by Chevron and Microsoft”
  • Planned first power: Q1 2027 - press reporting (Aug 2026) of the project target; land clearing was under way in late Jul 2026 and no generation equipment was installed as of Oct 20, 2026
    “The campus, Amazon's first off-grid AI data center, is designed to skip clogged grid interconnection queues and targets first power by Q1 2027”
  • Owner current: Amazon (site owner)
    “We reached out to Amazon and the company confirmed it had acquired the GW Ranch site and plans to buy power from the plant”
  • Water use stated: Non-potable brackish groundwater; initial phase requires no water for power-generation cooling (Amazon)
    “we'll use water that isn't suitable for drinking or irrigation, custom cooling technology that minimizes water use wherever possible”
  • Amazon confirms it acquired the GW Ranch site from Pacifico and will buy power from the plant, its first major off-grid data-center investment. Pacifico remains plant developer/operator. PPA terms (tenor, price, volume)
    “We reached out to Amazon and the company confirmed it had acquired the GW Ranch site and plans to buy power from the plant”
  • Site owner current: Amazon acquired the GW Ranch site from Pacifico Energy in 2026 and is building the data centers
    “the company acquired the GW Ranch site in Pecos, Texas, from Pacifico Energy, where it intends to construct a behind-the-meter powered data center”
  • Pecos County pocket context: TPIT 93226 expands the Fort Stockton Switch 345 kV station (three 345/138 kV autotransformers, AEP TNC, Planning Charter Tier 1, projected in-service April 30, 2029); Fort Stockton Switch is the
    “Fort Stockton Switch: Expand 345 kV Station. Install three 345/138 kV autotransformers at the Fort Stockton Switch 345/138 kV station.”
  • On-site generation: 7,650 MW
    “The site's developer Pacifico, obtained a 7.65GW air permit from the Texas Commission on Environmental Quality.”
  • Stated campus size: 5,000 MW
    “GW Ranch's unique approach will provide 5 gigawatts (GW) of dedicated, highly reliable power”
  • Developed acres: 1500 acres
    “The Project involves the development of approximately 1,500 acres devoted to the power generation facilities and data center campus”
  • On-site generation: 5,000 MW
    “The Project's nominal generation capacity will be approximately 5,000 MW”
  • Turbine fleet: 35 combustion turbines: 14 large-frame (OEM unselected; envelope Doosan DGT6-300H S2, GE 7HA.03, Mitsubishi M501JAC, Siemens SGT6-9000HL) + 21 Siemens SGT-800 at 62.5 MW
    “The Project will consist of the installation of 35 combustion turbines and ancillary equipment”
  • On-site generation: 1,840 MW
    “The Project will utilize an approximately 1,840 MW (920 MWh) battery energy storage system (BESS) to support the variable nature of the data center load”
  • Utility service: not stated
    “the Project will not be capable of selling electricity to or purchasing it from the local utility power grid”
  • Power plan: off-grid private grid (behind-the-meter, islanded)
    “The Project will be constructed as fully independent, operating in islanding mode”
  • Utility: none (off-grid; ERCOT region, not interconnected)
    “the Project will not be capable of selling electricity to or purchasing it from the local utility power grid”
Money and contracts (16)
  • Incentives: none located
    “Robust permits & local support de-risk execution; ITC & tax-abatement upside”
  • tax abatement chapter312: absence finding
    “Robust permits & local support de-risk execution; ITC & tax-abatement upside”
  • gas supply: absence finding
    “Gas Supply: Multiple laterals, including a 15-mile 1 BCF/d direct pipeline to Waha for unmatched gas supply optionality”
  • site acquisition: consideration missing finding
    “Amazon has acquired an 8,000-acre plot of land in Texas, where it plans to develop a data center”
  • Stated capital cost: 12000000000 USD
    “the developer estimated its needed investment at about $12 billion, in comments in February to Forbes”
  • Square feet: 567000 sq ft
    “Amazon filed building permits for three 189,000-sq-ft data center buildings to be located on the 8,000-acre remote Pecos County campus”
  • Financing: not disclosed
    “Neither Amazon nor Pacifico disclosed any project cost”
  • power purchase agreement: terms missing finding
    “Public information available does not reveal full details of Amazon's power purchase agreement with Pacifico Energy, including contract length, pricing or exact electricity volumes”
  • Amazon files three TDLR TABS building registrations (189,000 sq ft each, Gensler architect, ~$300M each per ENR, completion scheduled December 2026), the paper trail that surfaced Amazon's role
    “Amazon filed building permits for three 189,000-sq-ft data center buildings to be located on the 8,000-acre remote Pecos County campus”
  • Tenants: Amazon
    “Amazon has acquired an 8,000-acre plot of land in Texas, where it plans to develop a data center”
  • Tenant status: confirmed
    “We reached out to Amazon and the company confirmed it had acquired the GW Ranch site and plans to buy power from the plant”
  • power purchase agreement: scope
    “We reached out to Amazon and the company confirmed it had acquired the GW Ranch site and plans to buy power from the plant”
  • site acquisition: scope
    “the company acquired the GW Ranch site in Pecos, Texas, from Pacifico Energy”
  • Land clearing under way at the site in Airbus satellite imagery dated Jul 24, 2026 (Cleanview). First physical construction evidence located; no turbine deliveries or plant construction reported
    “Land clearing begins at GW Ranch. Captured July 24, 2026. (Airbus DS 2026)”
  • hosting / colocation: scope not named end customer (Anthropic tie)
    “Our new planned data center campus in Pecos County does just that: it's powered by new on-site generation that won't raise electricity costs for Texas families”
  • permit condition: construction deadline
    “This permit will be automatically void upon the occurrence of any of the following, as indicated in 30 TAC 116.120(a): 1. Failure to begin construction within 18 months of the date of issuance”
Permits and government (24)
  • U.S. Senate Committee on Environment and Public Works and Committee on Energy and Natural Resources (oversight correspondence): Letter to Pacifico CEO Nate Franklin and VP Constantyn Gieskes with seven interrogatories on
    “To help us better understand your decision-making process and plans related to the GW Ranch Project, please provide responses to the following interrogatories and document requests by March 27, 2026”
  • Air quality permit public notice: notice of application and preliminary decision published
    “application 2025-08-04 (P001 hand-work); final 2026-01 (P001 hand-work)”
    grade B
  • FAA obstruction evaluation (7460-1): Studying
    “ASN 2026-ASW-16783-OE: MDD150 Crane Working Area, Mobile Crane, 300 ft AGL, 2844 ft AMSL, 31.18078,-102.86772, Studying, submitted 2026-10-13”
    FAA · Oct. 2026 · grade B
  • FAA OE/AAA filing for a 300-ft mobile crane working area (submitted Oct. 13, 2026, status Studying) inside the 8,000-acre GW Ranch site evidences crane work at the campus in Oct 2026.
    “ASN 2026-ASW-16783-OE: MDD150 Crane Working Area, Mobile Crane, 300 ft AGL, 2844 ft AMSL, 31.18078,-102.86772, Studying, submitted 2026-10-13”
    FAA · Oct. 2026 · grade B
  • Air permit number: 181033 (PSDTX1672)
    “Pacifico Energy has obtained a 7.65GW air permit from the Texas Commission on Environmental Quality (TCEQ)”
  • NSR air quality permit: issued
    “In accordance with Title 30 Texas Administrative Code (TAC) Chapter 116 your permit is hereby issued”
  • PSD permit: issued
    “Permit Numbers: 181033, PSDTX1672, and GHGPSDTX255”
  • GHG PSD permit: issued
    “All preconstruction authorizations (including the pending authorization, permit GHGPSDTX255) must be obtained prior to start of construction”
  • Air permits, construction-start condition: condition deadline
    “This permit will be automatically void upon the occurrence of any of the following, as indicated in 30 TAC 116.120(a): 1. Failure to begin construction within 18 months of the date of issuance”
  • Pecos County officials (statements published in the developer's announcement; no commissioners-court vote located): Public endorsement of GW Ranch by County Judge Joe Shuster and Economic Development Director Remie Ramos
    “Pecos County's continued effort to diversify the local economy directly aligns with the development of GW Ranch”
  • Pacifico GW LLC application for the GW Ranch Energy Center, Pecos County: NSR/PS: air quality permit application received
    “The project has initiated permitting with the Texas Commission on Environmental Quality (TCEQ)”
  • Air quality NSR/PSD/GHG permit (consolidated application): application filed
    “Pacifico GW LLC (Pacifico) is submitting this permit application to authorize the construction of a natural gas-fired simple cycle power plant at a greenfield site in Pecos County, Texas”
  • Stage: building (early stage)
    “In August, Amazon filed building permits for three 189,000-sq-ft data center buildings to be located on the 8,000-acre remote Pecos County campus”
  • Jurisdiction: Unincorporated Pecos County, state-led permitting; no county zoning or building permit applies
    “The site is located on Highway 18, approximately 17 miles north of Fort Stockton, in Pecos County, Texas”
  • Building registration (architectural barriers, TABS): filed
    “Amazon filed building permits for three 189,000-sq-ft data center buildings”
  • Pecos County Commissioners Court: Regular session: proposed tax abatement items were tabled (Fort Stockton Pioneer). The accessible report does not name GW Ranch or Pacifico, NOT attributed to this campus; logged for fo
    “Pecos County Commissioners Court met Monday, Sept. 28, for a regular session that lasted approximately one hour, with proposed tax abatements, swimming pool repairs and recognition of local 4-H member”
  • Buildings permitted: 3 buildings
    “Amazon filed building permits for three 189,000-sq-ft data center buildings”
  • Texas Gov. Abbott directs a pause on new data-center grid connections pending PUCT/ERCOT ownership, financial, water and community-impact audits (provisionally qualified large-load audits due Dec 10, 2026). GW Ranch is i
    “It's also uncertain if or how the project would be affected by a statewide pause on new data center projects connecting to the state grid, announced Aug. 3 by Texas Gov. Greg Abbott”
  • Ghg permitted: 33000000 tpy CO2e
    “33 million tons per year of climate-warming greenhouse gases”
  • Criteria pollutants permitted: 12000 tpy
    “The TCEQ permit authorizes (i) 12,000 tons per year of dangerous health-harming pollutants including soot, ammonia, carbon monoxide, and volatile organic compounds”
  • a: air quality permit issued (final)
    “Pacifico Energy has obtained a 7.65GW air permit from the Texas Commission on Environmental Quality (TCEQ) for its planned 5GW GW Ranch project in West Texas”
  • Developer: Pacifico Energy (Pacifico GW LLC)
    “Pacifico GW, LLC has requested an initial permit concerning the above-referenced project”
  • Permit construction deadline: July 21, 2027
    “Failure to begin construction within 18 months of the date of issuance”
  • TCEQ issues Permits 181033, PSDTX1672 and GHGPSDTX255 to Pacifico GW LLC, the largest US air permit by capacity. Construction must begin by Jul 21, 2027 or the permits void (30 TAC 116.120(a))
    “In accordance with Title 30 Texas Administrative Code (TAC) Chapter 116 your permit is hereby issued”
Site and other (11)
  • Data Center Controls Tech, Coyanosa, Texas - Amazon Data Services posting located in Pecos County, live on amazon.jobs (posted October 15, 2026)
    “Data Center Controls Tech, Coyanosa, Texas | US, TX, Coyanosa | posted October 15, 2026”
  • Data Center Controls Tech, Coyanosa, Texas - second concurrent requisition, live on amazon.jobs (posted October 15, 2026)
    “Data Center Controls Tech, Coyanosa, Texas | US, TX, Coyanosa | posted October 15, 2026”
  • Commissioning Engineer, AWS Commissioning (AMER-West) located at Coyanosa, TX, live on amazon.jobs (posted October 14, 2026) - commissioning hiring is consistent with buildings approaching delivery
    “Commissioning Engineer, AWS Commissioning, AMER-West | US, TX, Coyanosa | posted October 14, 2026”
  • Engineering Operation Technician, DCC Communities, located at Pecos, TX, live on amazon.jobs (posted August 19, 2026)
    “Engineering Operation Technician, DCC Communities | US, TX, Pecos | posted August 19, 2026”
  • Infra Delivery Install Technician located at Pecos, TX, live on amazon.jobs (posted August 13, 2026)
    “Infra Delivery Install Technician | US, TX, Pecos | posted August 13, 2026”
  • Original target date: 2028 (first phase online); 2030 (full buildout)
    “Modular design enables scalable buildout: 1 GW online in 2028, full 5 GW in 2030”
  • Site acres: 8000 acres
    “The project, sited within 8,000+ acres in Pecos County, Texas, is purpose-built to support hyperscale data centers”
  • Construction stage: clearing (land clearing under way Jul 2026; three data-center buildings registered with the state Aug 2026)
    “Cleanview reviewed satellite imagery to look for the project and discovered that land clearing had begun at the site”
  • County: Pecos County
    “GW Ranch Energy Center, Fort Stockton, Pecos County”
  • Location: Highway 18, approximately 17 miles north of Fort Stockton
    “The site is located on Highway 18, approximately 17 miles north of Fort Stockton, in Pecos County, Texas”
  • Acres: 8400 acres
    “The Project will be situated on an approximately 8,400-acre site in Pecos County, Texas”

Imagery and records: Satellite imagery: Maxar via Esri World Imagery Wayback; Sentinel-2 (ESA Copernicus).