Data center campus proposed by 5C Group in Tarrant County, Texas; about 115 MW of IT capacity planned.

Announced. No local approval or permit is on record yet. No utility agreement or generation permit is on record. Newest record June 2024.
The campus, Lower-resolution satellite image, Oct. 12, 2026
144 MW
campus power the company states
facility power, not split into IT capacity
25
acres in the site
2029
first building in service, our estimate
range 2028 to 2033; no company target on record
Operator5C Group
CustomerNone named
Planned IT capacity115 MW at full build-out (our estimate from the company's 144 MW campus power figure)
First building in serviceOur estimate: 2029 (range 2028 to 2033).
The site

The site from above

Satellite overview
Lower-resolution satellite image, Oct. 12, 2026.
Power

Power and the grid

No utility agreement or generation permit is on record yet.

We checked utility filings, regulator dockets and air-permit records for this campus.

Permits

Permits checklist

5 checked, nothing on file

Approvals a campus like this normally needs, and what we found.

Construction activity

Since Oct. 2026: 1 satellite capture. Satellite · Oct. 2026

Who is involved

Owners, partners and builders

Owners and developers
  • 5C Data Centers, developer
Still unknown

Open questions

Where this comes from

10 records from 2 documents

Drawn from news reports and satellite captures, each kept with its date and source. The bar shows documents by type.

News report 1Satellite 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (2)
  • Project status: Planned: a 25-acre Dallas-Fort Worth metro project reported in June 2024 (240,000 sq ft of data hall space, up to 144 MW at full build-out). No construction start, opening, street address or tenant has be
    “That project is set to encompass 240,000 square feet of data hall space with up to 144 MW at full build-out”
  • Stated campus size: 144 MW
    “That project is set to encompass 240,000 square feet of data hall space with up to 144 MW at full build-out”
Permits and government (3)
  • Campus name: 5C Data Centers DFW01 (5CDC Dallas-Fort Worth)
    “The owner is also planning to develop a 25-acre data center in the Dallas-Fort Worth metro”
  • Site acreage: 25 acres
    “The owner is also planning to develop a 25-acre data center in the Dallas-Fort Worth metro”
  • County code: 48439
    “The owner is also planning to develop a 25-acre data center in the Dallas-Fort Worth metro”

Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).