The site from above
Power and the grid
No utility agreement or generation permit is on record yet.
We checked utility filings, regulator dockets and air-permit records for this campus.
Permits checklist
5 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- –Checked, nothing on file: Zoning approval, Site plan, Building permit, Water and wetlands permits, Utility and grid approval
What happened, and what is due
- Nov. 1, 2021Site Project first appears in the public record
- Oct. 2026Power SWI Group/AiOnX's $500M acquisition of a 77% holding in GDA covers 15 crypto data centers (1.3 GW of available power) in the US and Sweden. News report · Oct. 2026
Satellite captures by quarter
Since Sept. 2025: 2 satellite captures.
Owners, partners and builders
- AiOnX, operator
- SWI Group, owner
Open questions
- How the campus will be powered.
- Whether site work has started.
16 records from 4 documents
Drawn from news reports, public and commercial datasets and satellite captures, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (5)
- Campus name: AiOnX Pyote (GDA Pyote)“GDA Pyote is a 370 MW hybrid data center in Pyote, Texas, featuring a 138kV substation”Dataset · Oct. 2026 · grade C
- Stated campus size: 370 MW“GDA Pyote is a 370 MW hybrid data center in Pyote, Texas, featuring a 138kV substation”Dataset · Oct. 2026 · grade C
- Interconnection voltage: 138 kV“GDA Pyote is a 370 MW hybrid data center in Pyote, Texas, featuring a 138kV substation”Dataset · Oct. 2026 · grade C
- County code: 48475“GDA Pyote is a 370 MW hybrid data center in Pyote, Texas”Dataset · Oct. 2026 · grade C
- SWI Group/AiOnX's $500M acquisition of a 77% holding in GDA covers 15 crypto data centers (1.3 GW of available power) in the US and Sweden, which AiOnX says will be converted for AI and HPC workloads“it now has a 77 percent holding in GDA, which operates 15 crypto data centers in the US and Sweden, with a footprint of 1.3GW of available power”News report · Oct. 2026 · grade C
Money and contracts (1)
- Project status: operating cryptocurrency mining facility; AiOnX/SWI completed a $500M majority acquisition of GDA in 2026 and announced conversion of the platform to AI/HPC workloads; no IT capacity in service at Pyote and n“These data centers will now be converted for AI and HPC workloads”News report · Oct. 2026 · grade C
Legal (1)
- Announced: Nov. 1, 2021“Genesis Digital Assets is building a new self-hosted bitcoin mining data center in West Texas with 300 megawatt of capacity”News report · Nov. 2021 · grade C
Site and other (1)
- Street address: 4947 Ranch to Market Rd 2355, Pyote, TX 79777“AiOnX — 4947 Ranch to Market Rd 2355, 79777 Pyote”Dataset · Oct. 2026 · grade C
Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).