Data center profile · Midway Industrial Park, unincorporated St. Lucie County, southwest of Fort Pierce, Florida

Atlas Compute Campus (Fort Pierce)

240 MW AI campus near Fort Pierce, Florida, announced in Nov. 2025 with four gas turbines for self-power; no approval ever filed, reported gone dark.

Stalled. Atlas Compute announced the campus on Nov. 6, 2025 and claimed land and utilities were secured. Local press found in Mar. 2026 that it had applied for no county, state or utility approvals, and in Aug. 2026 reported the proposal had gone dark.
240 MW
phase one, company says
full build-out of 1 GW claimed; utility records instead describe a 200 MW project
4 x 40 MW
gas turbines planned (press)
160 MW of on-site generation to supply the campus; never applied for or permitted
~26 acres
vacant industrial land (press)
no deed or purchase record found
123 MW
the local utility's own peak load in 2024
the 200 MW project would have exceeded it (press)
OperatorAtlas Compute (Miami-based startup, developer)
CustomerNo tenant announced
Planned IT capacity160 MW at full build-out (our estimate from the company or utility power figure)
Next stepNone scheduled; no application, tenant or company statement since the Nov. 2025 announcement
Permits

Permits checklist

4 checked, nothing on file

Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.

Risks

Why it stopped, what could revive it

Power

Power and the grid

None energized or contracted yet

On-site gas turbines (4 x 40 MW)Proposed, never permitted
160 MW
proposed behind-the-meter generation; no air permit application or gas supply contract; utility records describe 200 MW of load News report · Oct. 2026
Proposed

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. March 12, 2026
    Gas load exceeds the utility
    Utility records show the developer's gas requirement was beyond what the municipal utility could supply and needed direct pipeline service. see Permits
  2. Not set
    Service agreement: none
    No electric service agreement or contract exists in the public record. see Permits
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Nov. 6, 2025
    Site Atlas Compute announces a 240 MW campus, a 1 GW ceiling, Penguin Solutions as design-build partner and readiness by Q4 2026 to Q1 2027 Company · Oct. 2026
  2. Dec. 2, 2025
    Power The Fort Pierce utility board meets; no Atlas Compute item appears on its agenda Local government · Oct. 2026
  3. March 12, 2026
    Power Utility records reported by TCPalm show the gas supply was beyond the utility's capacity and no approvals had been sought News report · Oct. 2026
  4. March 27, 2026
    Power Press notes the 200 MW project would exceed the entire utility's 123 MW peak load News report · Oct. 2026
  5. July 1, 2026
    Permits Florida's SB 484 takes effect, keeping hyperscale siting with local governments; St. Lucie County adopts no moratorium News report · Oct. 2026
  6. Aug. 4, 2026
    Site TCPalm reports the proposal has gone dark, nine months after the announcement News report · Oct. 2026
The buildings

Specs

100 kW per rack design density claimed by the company. News report · Oct. 2026

Who is involved

Owners, partners and builders

Owners and developers
  • Atlas Compute: developer; Anthony Louie Velasco is CEO
  • Penguin Solutions: announced design-build partner
Power
  • Fort Pierce Utilities Authority: municipal utility, discussions only
  • Florida Gas Transmission: prospective gas transporter
Decision-makers
  • St. Lucie County: land use for the unincorporated site
Still unknown

Open questions

Where this comes from

75 records from 11 documents

Drawn from news reports, company statements, public and commercial datasets and local government records, each kept with its date and source. The bar shows documents by type.

News report 7Company 2Dataset 1Local government 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (23)
  • Name: Atlas Compute Campus
    “Atlas Compute Secures Land and Utilities for 240 MW AI Data Center Campus in Central Florida with 1 GW Expansion Capacity”
  • Stated campus size: 240 MW
    “Atlas Compute Secures Land and Utilities for 240 MW AI Data Center Campus in Central Florida with 1 GW Expansion Capacity”
  • Atlas Compute announces the campus by GlobeNewswire release: 240 MW Phase 1, expansion to 1 GW, land and utilities claimed secured, Penguin Solutions selected, operational readiness targeted Q4 2026-Q1 2027. This announc
    “Atlas Compute Secures Land and Utilities for 240 MW AI Data Center Campus in Central Florida with 1 GW Expansion Capacity”
  • Stated campus size: 240 MW
    “Phase 1 construction will deliver 240 MW of operational capacity”
  • Developer: Atlas Compute
    “Atlas Compute — a Miami-based start-up, according to its website — has for months considered building a 200 MW data center on vacant industrial land in Midway Industrial Park”
  • Utility service: 200 MW
    “Atlas Compute, for comparison, is projected to generate and consume 200 MW of electricity by building its own natural gas-fired power plant, according to FPUA records”
  • On-site generation: 160 MW
    “Atlas Compute plans to generate its own electricity using an exceptionally large load of natural gas to power four industrial 40 MW gas turbines”
  • IT capacity: not stated
    “Phase 1 construction will deliver 240 MW of operational capacity, with full build-out to 1 GW across multiple buildings engineered for 100 kW per-rack density”
  • Power plan: behind-the-meter self-generation (proposed; never permitted)
    “Atlas Compute plans to generate its own electricity using an exceptionally large load of natural gas to power four industrial 40 MW gas turbines”
  • Utility: Fort Pierce Utilities Authority (FPUA, municipal), discussions only; no service agreement
    “according to records obtained from Fort Pierce Utilities Authority”
  • Construction stage: none, no application filed, no construction, no site work
    “Atlas Compute, however, has yet to apply for any approvals from St. Lucie County or obtained the natural gas it would need to fuel its power plant”
  • Stage: stalled
    “There was also Atlas Compute, which planned to build its own natural gas powerplant. This proposal, too, has gone dark”
  • Current target date: not stated
    “There was also Atlas Compute, which planned to build its own natural gas powerplant. This proposal, too, has gone dark”
  • Cooling: closed-loop, water-free cooling (company claim)
    “The campus will incorporate next-generation cooling technology that eliminates the need for water use, significantly reducing environmental impact while maintaining optimal thermal performance for dense AI compute environments”
  • utility capacity determination: declined, load beyond FPUA capability
    “The electricity consumption of the city of Fort Pierce at its peak in 2024, according to a report from Fort Pierce Utilities Authority, was 123 MW”
  • TCPalm, working from FPUA records, reveals the substance behind the announcement: months of consideration of a 200 MW data center at Midway Industrial Park, self-supplied by four 40 MW gas turbines; FPUA could not supply
    “Atlas Compute — a Miami-based start-up, according to its website — has for months considered building a 200 MW data center on vacant industrial land in Midway Industrial Park, according to records obtained from Fort Pierce Utilities Authority”
  • Company-claimed full build-out of 1 GW across multiple buildings (100 kW per-rack density, Tier III target). Booked as a signal only, a portfolio-style ceiling for an unbuilt project, never a campus MW field
    “Phase 1 construction will deliver 240 MW of operational capacity, with full build-out to 1 GW across multiple buildings engineered for 100 kW per-rack density”
  • TCPalm's Treasure Coast survey reports the Atlas Compute proposal has gone dark, no application, no gas, no construction, no further company statements since the announcement
    “There was also Atlas Compute, which planned to build its own natural gas powerplant. This proposal, too, has gone dark”
  • Project status: stalled
    “There was also Atlas Compute, which planned to build its own natural gas powerplant. This proposal, too, has gone dark.”
  • Utility service: 200 MW
    “Atlas Compute has for months considered building a 200 MW data center on vacant industrial land in Midway Industrial Park, according to records obtained from Fort Pierce Utilities Authority.”
  • Utility: Fort Pierce Utilities Authority (discussions only; no electric ESA; no gas obtained)
    “Atlas Compute, however, has yet to apply for any approvals from St. Lucie County or obtained the natural gas it would need to fuel its power plant.”
  • Plan to generate its own electricity from natural gas using four industrial 40 MW gas turbines (press description of turbine count/size only
    “Atlas Compute plans to generate its own electricity using an exceptionally large load of natural gas to power four industrial 40 MW gas turbines.”
  • Atlas Compute had yet to apply for any approvals from St. Lucie County or obtain the natural gas needed for its power plant
    “Atlas Compute, however, has yet to apply for any approvals from St. Lucie County or obtained the natural gas it would need to fuel its power plant.”
Money and contracts (13)
  • land position (company claim): scope
    “Atlas Compute Secures Land and Utilities for 240 MW AI Data Center Campus in Central Florida with 1 GW Expansion Capacity”
  • company claim: land and utilities claim
    “Atlas Compute today announced it has secured land and critical utility infrastructure for the development of a 240-megawatt (MW) AI-ready data center campus”
  • design build: services
    “Atlas Compute has selected Penguin Solutions, a global leader in high-performance computing and AI factory infrastructure, to design, build, deploy, and manage the AI infrastructure”
  • Tenants: not stated
    “the campus will provide a scalable platform for AI companies, hyperscalers, and cloud providers seeking sustainable, low-latency compute capacity on the U.S. East Coast”
  • Tenant status: none announced
    “Atlas Compute has selected Penguin Solutions, a global leader in high-performance computing and AI factory infrastructure, to design, build, deploy, and manage the AI infrastructure”
  • design-build / infrastructure services (announced): scope
    “Atlas Compute has selected Penguin Solutions, a global leader in high-performance computing and AI factory infrastructure, to design, build, deploy, and manage the AI infrastructure in our new state-of-the-art data center campus”
  • design-build / infrastructure services (announced): missing-clause finding
    “Atlas Compute has selected Penguin Solutions, a global leader in high-performance computing and AI factory infrastructure, to design, build, deploy, and manage the AI infrastructure”
  • land position (company claim): missing-clause finding
    “Atlas Compute — a Miami-based start-up, according to its website — has for months considered building a 200 MW data center on vacant industrial land in Midway Industrial Park”
  • gas supply (company claim): scope
    “The Central Florida site offers strategic advantages, including confirmed gas supply, diverse fiber connectivity, and access to Florida's robust power grid and port infrastructure”
  • gas transport discussions (no agreement executed): scope
    “Atlas Compute plans to generate its own electricity using an exceptionally large load of natural gas to power four industrial 40 MW gas turbines”
  • gas transport discussions (no agreement executed): condition
    “Atlas Compute, however, has yet to apply for any approvals from St. Lucie County or obtained the natural gas it would need to fuel its power plant”
  • electric service agreement: missing-clause finding
    “Without a finalized proposal, any assessment would be speculative, said FPUA spokesperson Calvin Daniels in a statement”
  • county development / incentive agreement: missing-clause finding
    “St. Lucie County commissioners have provided no policy direction on a data center moratorium, county spokesperson Erick Gill said”
Permits and government (8)
  • Fort Pierce Utilities Authority Board: Regular meeting agenda reviewed for any Atlas Compute / data-center item, none appears in the agenda; the campus was never the subject of a public FPUA board action
    “FORT PIERCE UTILITIES AUTHORITY BOARD REGULAR MEETING AGENDA”
  • Jurisdiction: St. Lucie County (unincorporated site); Florida SB 484 confirms local-government authority over hyperscale data-center siting
    “signed SB 484 into law, which gives local governments authority over planning and land development regulations for hyperscale data centers”
  • county development approval / site plan: never filed
    “Atlas Compute, however, has yet to apply for any approvals from St. Lucie County or obtained the natural gas it would need to fuel its power plant”
  • county development approval / site plan: still none, proposal reported gone dark
    “There was also Atlas Compute, which planned to build its own natural gas powerplant. This proposal, too, has gone dark”
  • air permit (on-site gas plant): never filed
    “Atlas Compute, however, has yet to apply for any approvals from St. Lucie County or obtained the natural gas it would need to fuel its power plant”
  • TCPalm's SB 484 coverage repeats the FPUA-records figure, the project would generate and consume 200 MW, against FPUA's own 123 MW system peak (2024): the single project would have exceeded the entire municipal utility
    “The electricity consumption of the city of Fort Pierce at its peak in 2024, according to a report from Fort Pierce Utilities Authority, was 123 MW”
  • Florida SB 484 takes effect: local governments keep authority over hyperscale data-center planning and land development, and large customers must bear their own infrastructure costs. St. Lucie County adopts no moratorium
    “signed SB 484 into law, which gives local governments authority over planning and land development regulations for hyperscale data centers”
  • A separate new Fort Pierce data-center proposal is reported in Aug 2026 press (and a fall-2026 rezoning under the name Project Neptune at a different site). No opened source connects it to Atlas Compute; it is not booked
    “a new data center was reportedly being planned for Fort Pierce”
Legal (1)
  • First announced: Nov. 6, 2025
    “November 06, 2025 11:12 ET | Source: Atlas Compute Campus”
Site and other (6)
  • Atlas Compute announced the Fort Pierce campus on Nov 6 2025, targeting operational readiness between Q4 2026 and Q1 2027
    “The project is targeting operational readiness between Q4 2026 and Q1 2027.”
  • Company claims planned expansion of up to 1 GW at full build-out
    “with a planned expansion of up to 1 gigawatt (GW) of high-performance computing capacity”
  • City: Fort Pierce (site in unincorporated St. Lucie County, southwest of the city)
    “The site is in unincorporated St. Lucie County southwest of Fort Pierce”
  • Site: Midway Industrial Park, vacant industrial land, about 26 acres
    “Atlas Compute: 200-megawatt data center on 26 acres of vacant industrial land in Midway Industrial Park in Fort Pierce”
  • County code: St. Lucie County, FL (12111)
    “The site is in unincorporated St. Lucie County southwest of Fort Pierce”
  • Original target date: 2026-Q4 to 2027-Q1
    “The project is targeting operational readiness between Q4 2026 and Q1 2027”