Data center profile · East of Minute Maid Road, near Fort Pierce, St. Lucie County, Florida

Sentinel Grove Technology Park

Proposed 1 GW, $13.5B campus on 1,218 acres of former citrus grove near Fort Pierce, Florida; stalled at the planning board, withdrawn Feb. 2026.

Cancelled as filed. The Planning and Zoning Commission voted 4-2 on Oct. 16, 2025 to recommend against the land-use change; the applicant withdrew in Feb. 2026 before a county vote. No tenant, utility contract or permit on record; nothing resubmitted by Oct. 2026.
The campus, Aerial photo, Jan. 1, 2026
1 GW
first-phase power the developer cited
press and county reports; no filing states a MW figure
$13.5B
stated cost of the campus
press figure
1,218 acres
former citrus grove, three parcels
up to 15 million sq ft of buildings proposed
4-2
planning board vote against, Oct. 16, 2025
a recommendation; the County Commission never voted
OperatorTimberline Real Estate Partners (applicant); Epic Estates 68 LLC owns the land
CustomerNone named; the developer said it had no tenant
Planned IT capacity800 MW at full build-out (our estimate from the company's 1 GW campus power figure)
Next stepNone scheduled; a revival would need a fresh submission to county staff
The site

The site from above

Satellite overview1
Aerial photo, Jan. 1, 2026. Pin: Sentinel Grove Technology Park, St. Lucie County FL.
Permits

Permits checklist

1 withdrawn · 5 checked, nothing on file

Approvals a campus like this normally needs, and what we found. Nothing past the first county hearing was ever reached.

Risks

Why it stopped, what could revive it

Power

Power and the grid

None energized or contracted yet

Florida Power & Light, grid serviceContemplated, never contracted
1,000 MW
1 GW and a 20-year minimum contract were described in an economic-development report (press); no contract was ever signed News report · Nov. 2025
Approved

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. Nov. 6, 2025
    Utility supply described, not signed
    An economic-development report describes a 20-year minimum FPL contract for 1 GW under the utility's large-load tariff framework (press account). News report · Nov. 2025
  2. As of Oct. 2026
    No interconnection request on record
    No interconnection request, service agreement or state utility-commission filing exists for this campus in any source checked. see Permits
  3. July 1, 2026
    State law changes the rules
    SB 484 takes effect: large-load customers bear their full cost of service (50 MW threshold) and local governments keep land-use authority. State agency · Oct. 2026

What is next door

campus1.17 km · gas pipeline1.31 km · 138 kV transmission line1.85 km · substation8.36 km · 345 kV+ transmission linecampus1234
  1. 11.17 km · gas pipeline
  2. 21.31 km · 138 kV transmission line
  3. 31.85 km · substation
  4. 48.36 km · 345 kV+ transmission line

Distances from mapped lines and plants. OpenStreetMap · Oct. 2026

Money

Money on record

$13.5B
stated capital cost
press; the county report says it would be fully privately financed News report · Jan. 2026
$15M
price paid for the land, July 2024
by Epic Estates 68 LLC, 15 months before the project went public News report · July 2024
~$207M a year
county revenue claimed in that report

Not on record: tenant, lender or fund: no financing or sponsor filing found SEC filing · Oct. 2026

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. April 17, 2024
    Paper trail Epic Estates 68 LLC is formed in Florida SEC filing · April 2024
  2. April 17, 2024
    Paper trail Epic Estates 68 LLC registered in Florida
  3. July 2024
    Site Epic Estates 68 buys the 1,218-acre tract for $15M News report · Oct. 2026
  4. Oct. 16, 2025
    Permits Project unveiled under its EDC codename; county planning board votes 4-2 to recommend against the land-use change News report · Oct. 2025
  5. Nov. 6, 2025
    Power Economic-development report describes a 20-year, 1 GW FPL supply deal (press) News report · Nov. 2025
  6. Dec. 4, 2025
    Site Gov. DeSantis proposes data-center legislation, including local power to reject projects News report · Oct. 2026
  7. Jan. 11, 2026
    Site Commissioner Cathy Townsend says the data center is not coming to the county News report · Oct. 2026
  8. Feb. 2026
    Permits Applicant withdraws the application, ahead of the new state law News report · Oct. 2026
  9. May 12, 2026
    Site Local press finds no developer activity since the withdrawal News report · Oct. 2026
  10. July 1, 2026
    Legal SB 484 takes effect, keeping local land-use authority and requiring large loads to pay full cost of service State agency · Oct. 2026
  11. Aug. 4, 2026
    Site State map lists the project as withdrawn indefinitely; the county has adopted no moratorium News report · Oct. 2026
Construction activity

Satellite captures by quarter

Since March 2022: 70 satellite captures. The chart starts in the first quarter of 2023; 4 earlier records are not drawn.

Satellite
’23
’24
’25
’26
Dot size: records in the quarter, largest = 6. Two-digit years mark each first quarter.
The buildings

Specs

Up to 15 million sq ft
buildings in the filed plan (an earlier version was 20 million)
60 ft
maximum building height proposed
3 phases
as presented by the applicant's planning consultant
370 jobs
full-time, plus 2,000 remote, per the county economic-development report
Who is involved

Owners, partners and builders

Developer and owners
  • Timberline Real Estate Partners (Texas): applicant and developer
  • Epic Estates 68 LLC (Tallahassee): landowner, part of a land-banking group
  • HJA Design Studios: planning consultant
Decision-makers
  • St. Lucie County Planning and Zoning Commission: recommended against
  • St. Lucie County Commission: never voted
  • Commissioner Cathy Townsend: disclosed the withdrawal
Power
  • Florida Power & Light: contemplated supplier, no contract
Promoters
  • St. Lucie Economic Development Council: held the project under a codename and wrote the economic report
Still unknown

Open questions

Where this comes from

271 records from 24 documents

Drawn from news reports, public and commercial datasets, securities filings, business registries, satellite captures and state agency records, each kept with its date and source. The bar shows documents by type.

News report 16Dataset 6SEC filing 2Satellite 1State agency 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (15)
  • Jurisdiction: Unincorporated St. Lucie County; county BOCC holds land-use authority; state law preserves (does not preempt) local authority over large load customers
    “Local governments shall maintain the authority to exercise the powers and responsibilities for comprehensive planning and land development regulation granted by law with respect to large load customers”
  • Stated campus size: 1,000 MW
    “a proposed 1GW, 1,200-acre data center campus called Project Jarvis”
  • Nearest substation: REFERENCE: 1.85 km - FPL substation (230 kV) at 27.44463,-80.45093
    Measured on OpenStreetMap map data.
  • Nearest power line of 345 kV or more: REFERENCE: 8.36 km - Fort Drum Sub FPL to Midway Sub FPL 500 kV line
    Measured on OpenStreetMap map data.
  • Nearest power line of 138 kV: REFERENCE: 1.31 km - Emerson Sub FPL to Midway Sub FPL 230 kV line (nearest line in the 100-345 kV band)
    Measured on OpenStreetMap map data.
  • Nearest gas pipeline: REFERENCE: 1.17 km - Florida Gas Transmission Mainline Loop Station 19-20 gas pipeline
    Measured on OpenStreetMap map data.
  • IT capacity: not stated
    “with up to 15 million square feet of buildings and a first phase of 1,000 megawatts of power”
  • Gov. DeSantis announced proposed AI / hyperscale data-center legislation (Dec 4, 2025), including empowering local governments to reject data centers - the state-level turn that preceded the withdrawal.
    “Today (Dec. 4th) I proposed new legislation on artificial intelligence and AI data centers to protect Floridians' privacy, security and quality of life, DeSantis said”
  • Interconnection status: none - the land-use application was withdrawn in February 2026 before any utility filing existed: no FPL interconnection request, study or service agreement was ever made or is public for Sentinel
    “the applicants behind a proposed 1GW, 1,200-acre data center campus called Project Jarvis are choosing to hold back and watch the legislative process play out.”
  • Sentinel Grove Technology Park (Project Jarvis) was withdrawn at the land-use stage: St. Lucie County Planning & Zoning voted 4-2 on Oct 16, 2025 to recommend against the required comprehensive-plan amendment, and the ap
    “News of the applicant's withdrawal came from St. Lucie County Commissioner Cathy Townsend, who told WPTV that the data center pulled out because they knew that there was going to be legislation coming out in Tallahassee.”
  • Utility: Florida Power & Light
    “The data center operator will also enter a 20-year contract at minimum with FPL to generate the 1 gigawatt, or 1 billion watts, of power it needs daily, the report said”
  • Power plan: grid
    “Construction permitting includes Florida Power & Light (FPL), the South Florida Water Management District and U.S. Army Corps of Engineers, among others”
  • On-site power technology: not stated
    “Construction permitting includes Florida Power & Light (FPL), the South Florida Water Management District and U.S. Army Corps of Engineers, among others”
  • Square feet: 15000000 sq ft
    “with up to 15 million square feet of buildings and a first phase of 1,000 megawatts of power”
  • Stated campus size: 1,000 MW
    “with up to 15 million square feet of buildings and a first phase of 1,000 megawatts of power”
Money and contracts (22)
  • finding no executed agreements: finding No executed agreement of any kind exists in the record: no ESA, interconnection agreement, development agreement, PILOT, incentive or host agreement was ever executed. The applicat
    “No vote has taken place before the Board of County Commissioners (BOCC), and no final decision has been made, according to county leadership”
  • Epic Estates 68 LLC (Tallahassee land-banking vehicle) bought the 1,218-acre former citrus grove for $15M - the land play preceded any public data-center plan by ~15 months.
    “The land is owned by Epic Estates 68 LLC, a Tallahassee firm that bought it for $15 million in July 2024”
  • County declassified the plans and the project was unveiled at the P&Z hearing; until then it existed only as the EDC codename Project Jarvis under NDA.
    “Included in the list is Project Jarvis, which has been identified as Sentinel Grove Technology Park, a $13.5 billion, 15 million-square-foot data center proposed on Orange Avenue”
  • Timberline-linked donors gave more than $230,000 to Florida politicians in the 2026 cycle, including $70,000 bundled from nearly two dozen Timberline-connected people/entities to Byron Donalds on a single day, at least $
    “Records show that Byron Donalds has raised $70,000 from nearly two dozen people and corporate entities connected to Timberline”
  • Portfolio context only (not a campus agreement): the FPL Large Load Contract Services (LLCS) tariff structure the EDC report contemplated for this campus was the subject of FPL rate testimony by VP Tiffany C. Cohen on Fe
    “according to testimony given by FPL vice president of rate and revenue strategy Tiffany C. Cohen Feb. 28”
  • Address: East side of Minute Maid Road, approx. 2,600 ft north of Orange Avenue (SR 68), south and east of the SFWMD C-25 Canal, unincorporated St. Lucie County outside Fort Pierce
    “located on the east side of Minute Maid Road, extending approximately 2,600 feet north of Orange Avenue, and south and east of the South Florida Water Management District's C-25 Canal”
  • non disclosure arrangement: status change SB 484 (2026) removed large-scale data center information from extended economic-development confidentiality and added fines for agency NDAs, effective Jul 1, 2026
    “SB 484 would require data center developers to shoulder the cost of utility upgrades; fine government agencies that enter into non-disclosure agreements (NDAs)”
  • Stated capital cost: 13500000000 USD
    “The proposed $13.5 billion, 1,218-acre data center - known as Sentinel Grove Technology Park”
  • Building height ft: 60 ft
    “Their proposal would allow up to 15 million square feet of buildings, each up to 60 feet tall”
  • Incentives: not stated
    “No vote has taken place before the Board of County Commissioners (BOCC), and no final decision has been made, according to county leadership”
  • Financing: not stated
    “The center, which will focus on artificial intelligence model training, will have its construction fully financed with private capital, the report said”
  • Jobs claimed: 370 full-time jobs plus 2,000 remote jobs (EDC report)
    “Sentinel Grove is touted to generate approximately 370 full-time jobs; 2,000 remote jobs; and around $207 million in annual county revenue, according to a report compiled by the St. Lucie Economic Development Council”
  • power supply contemplated not executed: scope Supply of 1,000 MW for the campus MW
    “The data center operator will also enter a 20-year contract at minimum with FPL to generate the 1 gigawatt, or 1 billion watts, of power it needs daily, the report said”
  • power supply contemplated not executed: term Minimum 20-year contract term years
    “The data center operator will also enter a 20-year contract at minimum with FPL to generate the 1 gigawatt, or 1 billion watts, of power it needs daily, the report said”
  • power supply contemplated not executed: termination Cancellation on two years advance notice years
    “Contract cancellations must be given two years in advance”
  • power supply contemplated not executed: cost responsibility FPL to cover all incremental costs; funding via Large Load Contract Services (LLCS) tariffs; generation associated with the Sunbreak Farms area
    “FPL funding would come from tariffs imposed by the Large Load Contract Services (LLCS) initiative with power generated near Sunbreak Farms further out west”
  • Square feet: 20000000 sq ft
    “Originally, it would have been 20 million square feet”
  • Tenants: not stated
    “The property developer also said there was no tenant at the time”
  • Tenant status: not stated
    “Timberline Real Estate Partners, which filed the request with HJA Design Studios, said it had no tenant”
  • non disclosure arrangement: scope Project identity held confidential under the codename Project Jarvis until the county declassified the plans in Oct 2025
    “The St. Lucie Economic Development Council referred to the center as Project Jarvis before its unveiling”
  • Land price: 15000000 USD
    “The land is owned by Epic Estates 68 LLC, a Tallahassee firm that bought it for $15 million in July 2024”
  • Land control date: July 2024
    “The land is owned by Epic Estates 68 LLC, a Tallahassee firm that bought it for $15 million in July 2024”
Permits and government (13)
  • SB 484 took effect: s.163.326 preserves local land-use authority over large load customers; s.366.043 requires PSC large-load tariffs ensuring each large load customer bears its full cost of service (50 MW threshold); s.
    “Local governments shall maintain the authority to exercise the powers and responsibilities for comprehensive planning and land development regulation granted by law with respect to large load customers”
  • Project status: Withdrawn - applicant pulled the land-use application in February 2026 after the St. Lucie County Planning and Zoning Commission voted 4-2 on Oct. 16, 2025 to recommend against the required land-use change;
    “The one large data center proposed in St”
  • land use amendment and rezoning: Recommended AGAINST 4-2 by the P&Z on Oct 16, 2025; withdrawn by the applicant in Feb 2026 before any BOCC hearing; never approved
    “The county's Planning and Zoning Commission voted 4-2 on October 16, 2025 to recommend against the land-use change it needed”
  • environmental resource and consumptive use permit: Never applied for in any source checked; hearing coverage cites stormwater runoff without SFWMD permits. SB 484 (2026) s.373.262 now sets a large-scale data center CUP s
    “9 million gallons of stormwater runoff without permits from South Florida Water Management District”
  • section 404 wetlands: Listed among the construction permitting agencies in the EDC report; no application or public notice found
    “Construction permitting includes Florida Power & Light (FPL), the South Florida Water Management District and U.S. Army Corps of Engineers, among others”
  • large load service request: No interconnection request, ESA or campus-specific PSC filing in any source checked; supply was contemplated only under FPL's Large Load Contract Services framework as described in the EDC rep
    “FPL funding would come from tariffs imposed by the Large Load Contract Services (LLCS) initiative with power generated near Sunbreak Farms further out west”
  • Do not merge them into Sentinel Grove.
    “Fort Pierce Planning Board tabled a request to rezone 200 acres on Midway Road just north and west of I-95”
  • St. Lucie County Board of County Commissioners: Sentinel Grove land-use amendment - adoption hearing (never held)
    “No vote has taken place before the Board of County Commissioners (BOCC), and no final decision has been made, according to county leadership”
  • Development stage: CANCELLED as filed - St. Lucie County P&Z voted 4-2 on Oct 16, 2025 to recommend AGAINST the land-use change; the applicant withdrew in Feb 2026 ahead of Florida SB 484 (enacted Jul 1, 2026); revival r
    “The county's Planning and Zoning Commission voted 4-2 on October 16, 2025 to recommend against the land-use change it needed”
  • Land use status: AG-5 agricultural zoning retained; requested change to a Special District never approved; application withdrawn Feb 2026
    “Developers Timberline Real Estate Partners seek to rezone approximately 1,200 acres of former citrus grove land from Agricultural-5 to Special District”
  • Announced: Oct. 2025
    “the St. Lucie County planning and zoning commission last week voted 4-2 to recommend against approving an amendment to the area’s comprehensive plans that would allow the development of the Sentinel Grove Technology Park”
  • Aliases: Project Jarvis
    “The St. Lucie Economic Development Council referred to the center as Project Jarvis before its unveiling”
  • St. Lucie County Planning & Zoning Commission: Sentinel Grove Technology Park - comprehensive-plan (land-use) amendment and rezoning, Agricultural-5 to Special District, 1,218.4 acres, up to 15M sq ft data center campus
    “The county's Planning and Zoning Commission voted 4-2 on October 16, 2025 to recommend against the land-use change it needed”
Site and other (18)
  • County code: 12111
    “FCC census block API: campus anchor -> St; Lucie County FL 12111; on-site facilities (same tract, none built) -> St; Lucie County; Lucie County 12111.”
  • Construction stage: not stated
    “It faced opposition from nearby rural landowners and was withdrawn indefinitely”
  • Stage: withdrawn
    “It faced opposition from nearby rural landowners and was withdrawn indefinitely”
  • Original target date: not stated
    “County officials confirmed with Sunland News the developer has not indicated when they will resubmit their application”
  • Current target date: not stated
    “County officials confirmed with Sunland News the developer has not indicated when they will resubmit their application”
  • Commissioner Townsend on her podcast Townsend Unplugged: the data center is not coming to St. Lucie County; the developer pulled it because it lacked commission support.
    “The data center is not coming to St. Lucie County, Commissioner Cathy Townsend said Jan. 11 in the inaugural YouTube video of her podcast”
  • County told the developer it is studying peer data centers (Loudoun County, VA - where data-center tax revenue is ~38 percent of property tax revenue) before entertaining any resubmission; no resubmission timeline was gi
    “We've told them we are looking to visit and find out more information from other data centers in other states, the administrator said”
  • Applicant withdrew the land-use application ahead of Florida data-center legislation (SB 482 / SB 484), per Commissioner Townsend to WPTV; the developer did not comment.
    “Townsend said the developer of Sentinel Grove is waiting to see what happens in Tallahassee before officially cutting ties with the project”
  • TCPalm: no developer activity since the withdrawal; project on hold for months per county records. Townsend's understanding was that the developer planned to return to the BOCC once the bill was signed - no return had oc
    “My understanding was that once the bill was signed, they planned to return to the BOCC to seek approval, Townsend said”
  • TCPalm state data-center map: Sentinel Grove withdrawn indefinitely. St. Lucie County has adopted no moratorium (spokesperson Erick Gill) and Townsend opposes a blanket moratorium - the door is formally open, but nothing
    “St. Lucie County commissioners have provided no policy direction on a data center moratorium, county spokesperson Erick Gill said”
  • Phases: 3
    “Patty Tobin of HJ Design Studio, who spoke about the project to the commission, explaining how the center would be built in three phases”
  • Water use stated: not stated
    “We anticipate a very large decrease in water consumption. The technology today is using a fraction of existing data centers”
  • Owner companies: Epic Estates 68 LLC
    “Sentinel Grove would be built on approximately 1,218.4 acres of vacant agricultural land split across three plats owned by Epic Estates 68, LLC. of Tallahassee, according to the St. Lucie Property Appraiser database”
  • Acres: 1218.4 acres
    “Sentinel Grove would be built on approximately 1,218.4 acres of vacant agricultural land split across three plats owned by Epic Estates 68, LLC. of Tallahassee, according to the St. Lucie Property Appraiser database”
  • Name: Sentinel Grove Technology Park
    “The one large data center proposed in St. Lucie County, Sentinel Grove Technology Park, also called Project Jarvis, has been withdrawn”
  • Developer: Timberline Real Estate Partners
    “Timberline Real Estate Partners, which filed the request with HJA Design Studios, said it had no tenant”
  • Announced: Oct. 16, 2025
    “The project has been dormant since it was first proposed Oct. 16”
  • Opposition: Rural landowners and residents near Orange Avenue / Minute Maid Road
    “That's the last agricultural area we have left in St. Lucie County, please don't destroy it”

Imagery and records: Aerial imagery: local aerial photography via Esri World Imagery Wayback.