Data center profile · 200 Technology Way, Butte, Silver Bow County, Montana

Atlas Power Butte

An operating crypto-mining and hosting site outside Butte, Montana, whose utility plans to supply 75 MW and then up to 150 MW, with no service contract signed or approved yet

Bitcoin mining today; data-center plan pending. The site has been in service since 2018 (first as CryptoWatt) and is a NorthWestern Energy grid customer. Growth to 75 MW, then 150 MW, rests on a letter of intent and development agreement, not an executed service agreement.
75 MW
new load NorthWestern expected to serve starting in 2026
company letter of intent, Dec. 19, 2024; later filings show a combined 150 MW across three developers from late 2027
150 MW
possible total load after growth
another 75 MW expected within three to five years (utility)
0
executed electric service agreements on record
the utility says it is working to sign them; the commission must approve any of 50 MW or more
2018
year mining began at the site
shut Dec. 2019 after the owner's indictment, reopened Jan. 2020 as Atlas Power
OperatorAtlas Power Group LLC
CustomerMulti-tenant hosting, mostly Bitcoin mining and GPU rental; no anchor tenant named
Planned IT capacity120 MW at full build-out (our estimate from the company or utility power figure)
First building in serviceOur estimate: 2029 or later (no dated power path yet); company says 2026.
Next stepMontana utility commission ruling on NorthWestern's large-load tariff (filed Mar. 31, 2026; no decision date published)
Power

Power and the grid

75 MW energized

NorthWestern Energy grid (existing transmission service)Operating, no new contract
75 MW
the site holds a reported 75 MW state permit and draws an unmetered amount; 2021 press put actual draw near 25 MW. NorthWestern told regulators the Butte data centers would run on Colstrip coal power from 2026 (press) Company · Oct. 2026
NorthWestern expansion supply (to 150 MW)Planned, not contracted
150 MW
letter of intent for 75 MW from 2026 plus up to 75 MW more; a development agreement is signed, but no service agreement Company · Dec. 2024
Energized nowProposed
Not used, not on record, or dropped

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. Dec. 19, 2024
    Letter of intent
    NorthWestern announces plans to supply Atlas: 75 MW starting 2026, growing by up to 75 MW. Company · Dec. 2024
  2. Feb. 13, 2026
    Development agreement
    NorthWestern says Atlas has moved from a letter of intent to a development agreement; the developers put up to about $500,000 into utility studies. News report · Feb. 2026
  3. March 2026
    Large-load tariff filed
    NorthWestern asks the commission for rules covering new loads of 5 MW or more, with minimum commitments and termination costs. see Permits
  4. April 30, 2026
    Service agreement still unsigned
    The utility's quarterly filing says it is working to execute service agreements with its two developers; none is on record as of Oct. 18, 2026. see Permits
  5. Not set
    Commission decision
    No date is published for the tariff ruling or the consumer-group complaint. see Permits
Permits

Permits checklist

1 denied · 1 contested · 1 pending · 2 checked, nothing on file

Approvals a campus like this normally needs, and what we found.

Risks

What could slow it down

Lawsuits

1 case on record

Money

Money on record

$500,000+
what the developers put into utility studies
per NorthWestern on its Feb. 2026 earnings call (press transcript) News report · Feb. 2026
$250M
cost of the denied Basin Creek solar project
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. 2018
    Site Mining starts at the former technology center as CryptoWatt News report · June 2021
  2. Dec. 2019
    Site Site shuts after its majority owner is indicted over a separate fraud case News report · Jan. 2020
  3. Jan. 27, 2020
    Site Operations resume under new ownership and are renamed Atlas Power News report · Jan. 2020
  4. July 2021
    Permits Zoning board rejects the 300 MW Basin Creek solar array meant to power the site News report · July 2021
  5. Dec. 19, 2024
    Power NorthWestern announces plans to supply 75 MW from 2026, growing up to 150 MW Company · Dec. 2024
  6. Nov. 17, 2025
    Legal Nine groups file a complaint with the state commission over NorthWestern's data center service Court filing · Nov. 2025
  7. Feb. 13, 2026
    Power NorthWestern says Atlas has moved to a development agreement News report · Feb. 2026
  8. March 2026
    Permits NorthWestern files its large-load tariff Utility regulator · April 2026
  9. June 18, 2026
    Permits Governor's energy office moves to join the tariff case State agency · June 2026
  10. 2027
    Power Combined 150 MW across the Atlas, Sabey and Quantica agreements expected from late 2027 (utility) SEC filing · April 2026
The buildings

Specs

624 MW Atlas' capacity across three sites in Montana, North Dakota and Kentucky; not this campus alone. Company · Oct. 2026

Who is involved

Owners, partners and builders

Operator
  • Atlas Power Group LLC: runs the site
  • Atlas Power Holdings LLC: signed the development agreement with the utility
Utility and regulators
  • NorthWestern Energy: supplier
  • Montana Public Service Commission
  • Montana DEQ Energy Office: joining the tariff case
History
  • CryptoWatt: earlier operator
  • Madison River Equity: sought the denied solar permit
Opponents
  • Nine groups represented by Earthjustice
Still unknown

Open questions

Where this comes from

102 records from 22 documents

Drawn from news reports, company statements, public and commercial datasets, court filings, securities filings, state agency records and utility regulator dockets, each kept with its date and source. The bar shows documents by type.

News report 10Company 5Dataset 4Court filing 2SEC filing 1State agency 1Utility regulator 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (28)
  • Campus name: Atlas Power Butte
    “announces plans to provide electric supply service to Altas Power Group at its Butte, Montana data center”
  • Developer: Atlas Power Group LLC
    “Atlas Power Group LLC (Atlas) is a specialized infrastructure company”
  • Operator: Atlas Power Group LLC
    “Its primary focus is developing and operating flexible/interruptible load, multi-tenant data center hosting across the U.S., primarily for Bitcoin mining and GPUaaS applications”
  • Operating model: Flexible/interruptible-load multi-tenant hosting, primarily Bitcoin mining and GPU-as-a-service; load can power down or dynamically adjust on grid demand
    “These sites can power down or dynamically adjust load when electrical demand spikes due to weather extremes, unplanned interruptions, or during times of inadequate power generation”
  • Utility: NorthWestern Energy (NorthWestern Corporation, subsidiary of NorthWestern Energy Group, Inc.)
    “NorthWestern Energy Group, inc. d/b/a NorthWestern Energy (Nasdaq: NWE) announces plans to provide electric supply service to Altas Power Group”
  • Power plan: grid
    “Atlas Power Group is a NorthWestern Energy transmission service customer today”
  • IT capacity: not stated
    “Atlas currently has 624 MW of infrastructure capacity across its three hosting facilities located in Montana, North Dakota, and Kentucky”
  • Stated campus size: not stated
    “Atlas currently has 624 MW of infrastructure capacity across its three hosting facilities located in Montana, North Dakota, and Kentucky”
  • Construction stage: operating, existing facility in service; growth is a utility-supply expansion (new bundled supply tranche), with no new building construction documented in primary sources
    “we have signed development agreements with both Sabey Data Centers and Atlas Power Holdings LLC to provide electric supply services for data centers being developed in Montana”
  • Atlas Power portfolio (NOT campus MW): 624 MW of infrastructure capacity across three hosting facilities in Montana, North Dakota and Kentucky, per the operator's own site. Recorded here only, under the rule that portfol
    “Atlas currently has 624 MW of infrastructure capacity across its three hosting facilities located in Montana, North Dakota, and Kentucky”
  • NorthWestern development-agreement portfolio (NOT campus MW): combined requirement across the Atlas, Sabey and Quantica development agreements is 150 MW beginning late 2027, growing to approximately 1,500 MW or more by 2
    “The combined energy service requirement associated with these development agreements is currently expected to be 150 megawatts beginning in late 2027, with growth of up to approximately 1,500 megawatts or more by 2030”
  • Original target date: Jan. 2026
    “NorthWestern also confirmed that it expected to meet Atlas Power Group's 75 megawatts load beginning in January 2026, with expected growth to 150 megawatts”
  • Regulatory jurisdiction: Montana PSC (state) governs electric supply service to retail loads of 5 MW or more under Mont. Code Ann. 69-8-201(1); Butte-Silver Bow (consolidated city-county) zoning board governs land-use sp
    “providing electricity supply service to retail customers with an average monthly demand load of equal to or greater than five megawatts unless the Commission first determines that the provision of such service will not adversely impact the utility's other customers”
  • Project status: operating - existing facility operating today (Atlas is a NorthWestern Energy transmission service customer today); the new 75 MW supply load beginning 2026 is an expansion of service to the operating fac
    “Atlas Power Group is a NorthWestern Energy transmission service customer today.”
  • Utility service: 75 MW
    “The new energy supply load is expected to be 75 megawatts beginning in 2026, with forecasted growth of up to another 75 megawatts in the subsequent three to five years.”
  • Utility: NorthWestern Energy - transmission service customer today; new electric supply service planned from 2026, with a development agreement signed by Q1 2026
    “announces plans to provide electric supply service to Altas Power Group at its Butte, Montana data center.”
  • Utility service: 75 MW
    “The new energy supply load is expected to be 75 megawatts beginning in 2026, with forecasted growth of up to another 75 megawatts in the subsequent three to five years”
  • Utility service: 150 MW
    “The new energy supply load is expected to be 75 megawatts beginning in 2026, with forecasted growth of up to another 75 megawatts in the subsequent three to five years”
  • Site history: Occupies the former Mike Mansfield Advanced Technology Center, about 6 miles southeast of Butte; originally owned by Cryptowatt, later acquired by Atlas Power after closure and reopening
    “The Atlas Power: Butte cryptocurrency mining and data processing center occupies the former Mike Mansfield Advanced Technology Center about 6 miles southeast of Butte, Montana.”
  • State-permitted consumption is up to 75 MW, while actual power consumption has been reported as low as 25 MW after the facility switched from Bitcoin to Ethereum mining - evidence that the queue's 150 MW is not the exist
    “The State of Montana has permitted the operation to consume up to 75 MW, yet it has been reported that upon the facility changing from mining Bitcoin to mining Ethereum, actual power consumption has been as low as 25 MW.”
  • The Basin Creek Solar Project, proposed to power and scale the Atlas facility to as much as 300 MW, was denied a conditional use permit; the 300 MW was a proposed solar project figure, never campus generation
    “Montana's biggest solar farm -- the Basin Creek Solar Project -- was proposed near Butte to power and scale the Atlas Power facility to as much as 300 MW”
  • Site history: Former Mike Mansfield Advanced Technology Center; mining operation began 2018 as CryptoWatt; shut down Dec 2019 after majority owner Matthew Goettsche was indicted in the BitClub Network case; reopened Jan
    “he switched over to crypto by 2018 when the mining operation fired up at the Atlas Power project (which was initially called CryptoWatt)”
  • Stage: operating
    “Atlas Power also operates a site in Butte”
  • Reported existing draw: Global Energy Monitor puts the facility's maximum power consumption at 75 MW, and a 2026 mining-inventory review describes about 75 MW operating. No metered or contracted current-draw figure exist
    “an operating cryptocurrency and data processing center located near Butte, Montana, USA, with a maximum power consumption of 75 MW”
  • On-site generation: not stated
    “A Montana zoning board voted down a special use permit to build a $250 million, 300 MW solar array in Butte”
  • CryptoWatt begins cryptocurrency mining at the former Mike Mansfield Advanced Technology Center southeast of Butte, in the site later renamed Atlas Power.
    “he switched over to crypto by 2018 when the mining operation fired up at the Atlas Power project (which was initially called CryptoWatt)”
  • Atlas plans eight additional GPU buildings and the 300 MW Basin Creek Solar array to use its full reported 75 MW state permit; actual draw had fallen to about 25 MW after the switch from Bitcoin ASICs to Ethereum GPUs.
    “the end game for the project would be for Atlas Power to buy the solar array to power its mining operations, for which it has a 75 megawatt permit from the state”
  • Operations resume under part-owner Kevin Washington and operator Rick Tabish after litigation moved to federal court transferred ownership to Washington; the project is renamed Atlas Power.
    “part-owner Kevin Washington and operator Rick Tabish started up crypto mining business CryptoWatt once again”
Money and contracts (20)
  • Tenants: Multi-tenant hosting customers (Bitcoin mining and GPUaaS); no named anchor tenant disclosed in any primary source
    “developing and operating flexible/interruptible load, multi-tenant data center hosting across the U.S., primarily for Bitcoin mining and GPUaaS applications”
  • Tenant status: Hosting operator with unnamed customers; no third-party anchor tenant identified
    “multi-tenant data center hosting across the U.S., primarily for Bitcoin mining and GPUaaS applications”
  • Proposed tariff, Large New Load Rule (Docket 2026.04.023): term / minimum commitment
    “NorthWestern Energy's filing, submitted March 31, 2026, proposes minimum service commitments, demand and energy billing requirements, performance assurance and collateral, and termination cost provisions for qualifying large new loads”
  • Proposed tariff, Large New Load Rule (Docket 2026.04.023): termination
    “proposes minimum service commitments, demand and energy billing requirements, performance assurance and collateral, and termination cost provisions for qualifying large new loads”
  • Proposed tariff, Large New Load Rule (Docket 2026.04.023): condition
    “For the largest customers, the tariff would require individual service agreements to be reviewed and approved by the PSC”
  • Current target date: not stated
    “We are working with each of these parties to execute electric service agreements”
  • Development Agreement: scope
    “we have signed development agreements with both Sabey Data Centers and Atlas Power Holdings LLC to provide electric supply services for data centers being developed in Montana”
  • Development Agreement: condition
    “We are working with each of these parties to execute electric service agreements”
  • Electric Service Agreement (not executed): missing-clause finding
    “for the largest commitments, 50 megawatts or greater, we would file the executed Electric Service Agreement with the MPSC for review and approval before service begins”
  • development agreement - electric supply services: signed development agreement to provide electric supply services; the parties are working to execute electric service agreements
    “we have signed development agreements with both Sabey Data Centers and Atlas Power Holdings LLC to provide electric supply services for data centers being developed in Montana”
  • Letter of Intent, electric supply service: missing-clause finding
    “On December 2, 2025, the Commission granted NorthWestern's request for a protective order. Dkt. No. 2022.09.087, Index #41, Protective Order 8040 (Dec. 2. 2025)”
  • letter of intent - electric supply service: new energy supply load of 75 MW beginning 2026, with forecasted growth of up to another 75 MW in the subsequent three to five years 75 MW (new supply load, 2026)
    “The new energy supply load is expected to be 75 megawatts beginning in 2026, with forecasted growth of up to another 75 megawatts in the subsequent three to five years.”
  • Letter of Intent, electric supply service: scope 75 MW
    “The new energy supply load is expected to be 75 megawatts beginning in 2026, with forecasted growth of up to another 75 megawatts in the subsequent three to five years”
  • Letter of Intent, electric supply service: growth / expansion 150 MW
    “with forecasted growth of up to another 75 megawatts in the subsequent three to five years”
  • Letter of Intent, electric supply service: condition
    “Atlas Power Group is a NorthWestern Energy transmission service customer today”
  • Power Purchase Agreement (predecessor, historical): scope 64 MW
    “Cryptowatt signed a 64 MW Power Purchase Agreement with Portland General Electric, which distributes power from the Colstrip Steam Plant near Colstrip, Montana”
  • Development Agreement: study-cost condition 500000 USD (upwards of, per developer pair)
    “They put upwards of $500,000 of investment, if you will, for all the studies that are necessary that we need to complete as a utility”
  • NorthWestern Q4 2025 earnings call: Atlas had moved from a letter of intent to a development agreement and was moving faster than Sabey; management expected at least one of the two ESAs by the end of Q2 2026, a mileston
    “We have moved from an LOI to a development agreement, and they have been moving much, much quicker”
  • Proposed purchase (never closed): scope 300 MW
    “Atlas Power's owners planned buy the Basin Creek Solar Project to power the data center”
  • Facility shuts down after majority owner Matthew Goettsche is arrested and indicted over the separate BitClub Network scheme (alleged $722 million fraud); the mine itself was not the charged conduct.
    “Authorities closed down CryptoWatt after jailing its owner, Matthew Goettsche, on a separate fraud account totaling $722 million”
Permits and government (11)
  • Large New Load Tariff Rule application: Application filed; docket received
    “2026.04.023 NorthWestern Energy Application for Large New Load Tariff Rule”
  • Montana Public Service Commission (Business Meeting): Agenda No. 2026.04.14, new regulatory dockets received, incl. 2026.04.023 NorthWestern Energy Application for Large New Load Tariff Rule
    “New Regulatory Dockets Received in the Past Week: 2026.04.023 NorthWestern Energy Application for Large New Load Tariff Rule”
  • Intervention in tariff proceeding: State intervention announced
    “DEQ's Energy Office is requesting to participate as a party in the PSC proceeding under the Commission's intervention rule”
  • Protective order: Granted
    “On December 2, 2025, the Commission granted NorthWestern's request for a protective order. Dkt. No. 2022.09.087, Index #41, Protective Order 8040 (Dec. 2. 2025)”
  • Electric supply service, complaint proceeding: Complaint filed
    “Complainants request that the Commission inform NorthWestern that it shall not provide electricity supply service to large load customers until the Commission determines that the provision of such service will not adversely impact the utility's other customers”
  • conditional use permit: Denied
    “The conditional use permit for the proposed solar project was denied by the Butte Zoning Board as a result of strong public opposition”
  • Nine nonprofit groups petitioned the Montana Public Service Commission (Nov 2025) to impose rules on NorthWestern Energy so existing customers do not bear data center infrastructure costs; the petition coverage restates
    “Nine groups working on energy, conservation, social justice and affordability issues on Tuesday asked the Public Service Commission to impose rules on NorthWestern”
  • NorthWestern told the PSC it does not intend to disclose information on impacts to existing customers before it begins providing service to data centers as early as January 2026, the posture the November 2025 complaint
    “In September, NorthWestern informed the PSC that it does not intend to disclose information on impacts to existing customers before it begins providing service to data centers as early as January 2026”
  • Montana PSC inquiry: NorthWestern responded to PSC questions about its data-center plans, stating the two Butte-area data centers' power would be supplied from the Colstrip plant starting in 2026, when NorthWestern acqui
    “All of the power to those two data centers will be supplied from the Colstrip coal-fired power plant in Montana starting in the year 2026”
  • Special use permit, solar array: Denied
    “A Montana zoning board voted down a special use permit to build a $250 million, 300 MW solar array in Butte”
  • Butte-Silver Bow Zoning Board: Basin Creek Solar Project special use permit (Madison River Equity LLC), 300 MW solar array proposed to power the Atlas Power campus
    “Madison River Equity LLC sought the special use permit for the 1,600-acre solar array known as the Basin Creek Solar Project”
Legal (1)
  • Atlas's own recruiting material describes the site-lead role at its operations (work locations include Butte, MT) as work in a cryptocurrency mining operation, even as the company markets itself as a data-center hosting
    “As a Site Lead in a cryptocurrency mining operation, your primary responsibilities will be to: Manage a team of shift leads and all aspects of operations throughout the site”
Site and other (6)
  • State: Montana
    “at its Butte, Montana data center”
  • City: Butte
    “at its Butte, Montana data center”
  • County code: 30093
    “Butte is a consolidated city-county in and the county seat of Silver Bow County, Montana, United States.”
  • Site address: 200 Technology Way, Butte, MT 59701
    “Location: 200 Technology Way, Butte, MT 59701”
  • Operator type: own-use operator - flexible-load data center hosting: cryptocurrency mining plus machine learning and other data processing
    “In addition to mining cryptocurrency, the facility also performs machine learning and other data processing services.”
  • Address: 200 Technology Way, Butte, MT 59701
    “Location: 200 Technology Way, Butte, MT 59701”