Data center profile · Hood County, Texas

Big Digital Energy Hood County

Data center campus proposed by Big Digital Energy in Hood County, Texas, on grid power; about 249 MW of IT capacity planned.

Announced. No local approval or permit is on record yet. A utility or grid-operator filing is on record, with no final approval or signed service agreement yet. Newest record Aug. 2026.
The campus, Lower-resolution satellite image, Oct. 10, 2026
111 MW
utility load on file
facility power, not split into IT capacity
50
acres in the site
2029+
first building in service, our estimate
no dated power path yet; no company target on record
OperatorBig Digital Energy
CustomerNone named
Planned IT capacity249 MW at full build-out (our estimate from the company or utility power figure)
First building in serviceOur estimate: 2029 or later (no dated power path yet).
The site

The site from above

Satellite overview
Lower-resolution satellite image, Oct. 10, 2026.
Power

Power and the grid

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. July 20, 2026
    Utility MW on record
Queue positions on record
  1. Not set
    ERCOT queue position
    111 MW, subject to ERCOT validation Company · July 2026
Permits

Permits checklist

5 checked, nothing on file

Approvals a campus like this normally needs, and what we found.

Money

Money on record

$10M
Land acquisition
First closing: 30 acres; option to acquire the remainder News report · July 2026
$5M
JV partner loan
Loan funding part of 10NetZero's capital contribution; due News report · July 2026
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. July 15, 2026
    Money JV partner loan on record ($5M). News report · July 2026
  2. July 20, 2026
    Site Land acquisition on record ($10M). News report · July 2026
Construction activity

Since Oct. 2026: 1 satellite capture. Satellite · Oct. 2026

Who is involved

Owners, partners and builders

Power and utilities
  • Mawson Infrastructure Group
Investors and lenders
  • Big Digital Energy, partner
  • 10NetZero, partner
  • Texas Load House, partner
Still unknown

Open questions

Where this comes from

21 records from 6 documents

Drawn from news reports, company statements and satellite captures, each kept with its date and source. The bar shows documents by type.

News report 3Company 2Satellite 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (10)
  • Announced: July 6, 2026
    “signed a letter of intent to acquire a live powered industrial site in Hood County, Texas, and to develop it into a large-scale datacenter campus serving artificial intelligence (“AI”) tenants”
  • Campus name: Big Digital Energy Hood County (Texas Load House JV)
    “it has completed an acquisition of the previously announced power-ready industrial site in Hood County, Texas, through a 50/50 joint venture with energy-infrastructure company 10NetZero”
  • Utility service: 111 MW
    “is expected to support a phased expansion to as much as 111 MW of grid capacity, subject to validation by the Electric Reliability Council of Texas ("ERCOT")”
  • Utility service: 17 MW
    “the approximately 50-acre site currently has 17 MW of operational power”
  • On-site power technology: Existing natural-gas infrastructure offering the potential for behind-the-meter gas generation
    “The site's existing natural-gas infrastructure also provides the potential to add behind-the-meter generation, supporting a total buildout of up to 300 MW”
  • Site acreage: 50 acres
    “the approximately 50-acre site currently has 17 MW of operational power”
  • County code: 48221
    “power-ready industrial site in Hood County, Texas”
  • interconnection queue (ERCOT): subject to ERCOT validation
    “is expected to support a phased expansion to as much as 111 MW of grid capacity, subject to validation by the Electric Reliability Council of Texas ("ERCOT")”
  • Project status: Powered industrial site acquired July 2026. It carries 17 MW of operational power serving existing structures (30,000+ sq ft) that the JV intends to repurpose; no data hall serving IT capacity exists or is do
    “The 50-acre Hood County site contains more than 30,000 square feet (2,787 sqm) of existing structures the partnership intends to repurpose for data center use”
  • Stated campus size: 311 MW
    “The site has 17MW of operational power, reportedly upgradable to 111MW of grid power. The site also has the option to add behind-the-meter natural gas power, potentially taking the site to 311MW”
Money and contracts (3)
  • Nonbinding letter of intent with Tensor IQ for an initial deployment of 7,748 NVIDIA GPUs at Hood County, targeting availability in 2027
    “At Hood County, Big Digital signed a nonbinding letter of intent with Tensor IQ for an initial deployment of 7,748 NVIDIA D300 GPUs, targeting availability in 2027”
  • land acquisition: First closing: 30 acres; option to acquire the remainder (~20 acres) for $600,000 10000000 USD
    “The JV closed on 30 acres for about $10 million with an option to buy the remainder for $600,000”
  • JV partner loan: Loan funding part of 10NetZero's capital contribution; due Oct. 13, 2026, with ownership-transfer mechanics if unpaid 4900000 USD
    “To fund part of 10NetZero's capital contribution, Big Digital Energy provided a $4.9 million loan due October 13, 2026”

Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).