The site from above
Power and the grid
The plan on record is a grid connection. A serving utility is named, but no signed service agreement is on record.
We checked utility filings, regulator dockets and air-permit records for this campus.
Permits checklist
1 granted · 4 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- ✓Zoning approval GrantedCity of Wichita Falls · Nov. 5, 2024: Rezoning approved by City of Wichita Falls. News report · Sept. 2026
- –Checked, nothing on file: Site plan, Building permit, Water and wetlands permits, Utility and grid approval
What happened, and what is due
- Nov. 5, 2024Permits Rezoning approved by City of Wichita Falls. News report · Sept. 2026
Since Oct. 2026: 1 satellite capture. Satellite · Oct. 2026
Owners, partners and builders
- Calvano Development, tenant
- Oncor Electric Delivery, utility
- City of Wichita Falls, public agency
Open questions
- Signed electric service agreement and delivery date.
- Whether site work has started.
17 records from 5 documents
Drawn from news reports and satellite captures, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (3)
- Two other Wichita Falls projects are NOT this campus: Skybox's PowerCampus in the Wichita Falls Business Park (~225 acres, construction targeted late 2026) and DataNovaX's Airport Drive rezoning, which the City Council v“On May 5, the Wichita Falls City Council voted against a request to rezone land near the intersection of Airport Drive and Spur 325 for a nine-structure data center planned by Data Nova X”News report · June 2026 · grade C
- Stated campus size: 300 MW“The maximum amount of electricity available to the site is 300MW, unless it is supplemented with onsite solar”News report · Nov. 2024 · grade C
- Utility: Oncor Electric Delivery“The land in question is adjacent to an Oncor facility, a transmission and distribution electric utility in Texas”News report · Nov. 2024 · grade C
Money and contracts (1)
- The developer's stated project cost is $5 billion (Times Record News, September 2026). A trade outlet separately wrote the property 'could hold about $2.3 billion in development' - a different (assessed development value“to accommodate Calvano's plans to build a $5-billion hyperscale data center”News report · Sept. 2026 · grade C
Permits and government (2)
- rezoning: approved“On Nov. 5, 2024, the Wichita Falls City Council voted to rezone about 227 acres of vacant land near Northwest Freeway and City View Drive from residential to light industrial”News report · Sept. 2026 · grade C
- Announced: Nov. 5, 2024“Wichita Falls City Council has approved a rezoning request for a data center development in Texas.”News report · Nov. 2024 · grade C
Site and other (4)
- Project status: Pre-development. About 227 acres were rezoned from residential to light industrial on Nov. 5, 2024; as of September 2026 the developer states the company is 'still in pre-development' and has not submitted“The developer of a large data center planned for Wichita Falls said his company hasn't submitted any documents for state approval yet”News report · Sept. 2026 · grade C
- Campus name: Calvano Data Center (Wichita Falls)“Calvano Data Center is a planned 300-megawatt center near Northwest Freeway and City View Drive”News report · Sept. 2026 · grade C
- Site acreage: 227 acres“Located in the north of Wichita Falls, the 227 acres close to Kiel Lane, City View Drive, and the Northwest Freeway will be rezoned from residential to light industrial”News report · Nov. 2024 · grade C
- County code: 48485“Wichita Falls is a city, and the county seat of Wichita County, in Nothern Texas”News report · Nov. 2024 · grade C
Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).