The site from above
Power and the grid
The plan on record is a grid connection. An interconnection study is under way.
We checked utility filings, regulator dockets and air-permit records for this campus.
Permits checklist
1 pending · 4 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- ◷Utility and grid approval PendingERCOT · Sept. 15, 2026: Interconnection queue application filed with ERCOT. News report · Sept. 2026
- –Checked, nothing on file: Zoning approval, Site plan, Building permit, Water and wetlands permits
What happened, and what is due
- Feb. 14, 2025Site Project first appears in the public record
- Sept. 15, 2026Power Interconnection queue application filed with ERCOT. News report · Sept. 2026
Since Oct. 2026: 1 satellite capture. Satellite · Oct. 2026
Owners, partners and builders
- Cipher Mining, developer
Open questions
- Signed electric service agreement and delivery date.
- Whether site work has started.
11 records from 4 documents
Drawn from news reports and satellite captures, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (5)
- Campus name: Cipher Mikeska“Cipher's most recent presentation also notes the Mikeska (500MW, outside Brady), Milsing (500MW, outside Houston), and McLennan (500MW, outside Waco) sites”News report · Oct. 2026 · grade C
- Stated campus size: 500 MW“Cipher's most recent presentation also notes the Mikeska (500MW, outside Brady), Milsing (500MW, outside Houston), and McLennan (500MW, outside Waco) sites, which are expected to energize in 2027”News report · Oct. 2026 · grade C
- County code: 48307“the Mikeska (500MW, outside Brady)”News report · Oct. 2026 · grade C
- interconnection queue (ERCOT): filed into Batch Zero; site-level class not specified by Cipher in retrieved sources“Mikeska (500 MW, likely base load)”News report · Sept. 2026 · grade C
- Announced: Feb. 2025“The company’s presentation also notes options on the Mikeska (500MW, outside Brady), Milsing (500MW, outside Houston), and McLennan (500MW, outside Waco) sites that are expected to energize in 2027”News report · Feb. 2025 · grade C
Site and other (1)
- Project status: development site; energization expected 2027 per Cipher presentation reporting; no construction evidence“which are expected to energize in 2027”News report · Oct. 2026 · grade C
Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).