Data center profile · 3333 Beverly Road, Hoffman Estates, Cook County, Illinois

Compass Hoffman Estates (former Sears headquarters)

Compass Datacenters' first Illinois campus: five hyperscale buildings on 197 acres of the former Sears headquarters in Hoffman Estates, approved in 2025 and under construction.

Under construction. Village approvals came in Feb. 2025; the mayor said in Apr. 2026 demolition finished and construction began. About 200 MW of IT capacity is a tracker's estimate; Compass and ComEd have published no MW figure, and no tenant is named.
5 buildings
hyperscale facilities planned
on a nearly 200-acre site (Compass and ComEd, June 2024)
197 acres
bought Sept. 12, 2023
former Sears headquarters; the Sears assets had been sold to Transformco
$10B+
investment the mayor cited
mayor's Apr. 2026 speech; not a company figure
OperatorCompass Datacenters (developer and owner)
CustomerNone named; Compass says its campuses are usually built for a single tenant
Planned IT capacity200 MW at full build-out (company IT figure)
First building in serviceOur estimate: 2029 or later (no dated power path yet).
Next stepNo date published; ComEd's on-site substation was slated for energization in mid-2026 and its status is not confirmed in our sources
Power

Power and the grid

Sources on record, size not disclosed

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. June 13, 2024
    Substation announced
    ComEd says it will deliver upgrades including a new on-site substation, to be energized in mid-2026. Company · June 2024
  2. June 16, 2025
    Village approves the substation site plan
    The village board approves site plan for the ComEd substation at Trillium Boulevard and Beverly Road. see Permits
  3. Oct. 20, 2025
    Underground line license granted
    The village board approves ComEd's license for underground lines in the Beverly Road right-of-way to serve the campus; two 138 kV routes were recommended on Nov. 24, 2025. News report · Oct. 2025
  4. March 19, 2026
    State large-load deposit rule
    The ICC approves ComEd's revised deposit tariff; a new project of 50 to 200 MW posts a deposit starting at $1 million (press). see Permits
Permits

Permits checklist

5 granted

Approvals a campus like this normally needs, and what we found.

Risks

What could slow it down

Money

Money on record

$10B+
investment the mayor described
Apr. 2026 address; not a company figure News report · April 2026
$1M+
ICC-approved deposit floor for 50 to 200 MW projects
utility tariff (press); rises $500,000 per extra 100 MW News report · March 2026
Land assembly

1 recorded land document for the campus company in county records (Sept. 2023); 1 lists a price. Parcel counts come from the deed; acreage is not recorded.

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Sept. 12, 2023
    Site Compass closes on the 197-acre former Sears headquarters News report · Sept. 2023
  2. Sept. 14, 2023
    Money Land purchase recorded at $194M: TF Hcffman Estates IL LLC to Compass Datacenters Ord I LLC (3 parcels) County deed records · Sept. 2023
  3. June 13, 2024
    Site Compass, ComEd and the village hold a kickoff as demolition of the Sears campus begins Company · June 2024
  4. Feb. 17, 2025
    Permits Village board approves the plat and site plan, and the tax classification News report · Feb. 2025
  5. June 16, 2025
    Power Village approves the site plan for ComEd's on-site substation News report · June 2025
  6. Oct. 20, 2025
    Power Village board approves ComEd's license for underground power lines on Beverly Road News report · Oct. 2025
  7. March 19, 2026
    Power ICC approves ComEd's revised large-load deposit tariff News report · March 2026
  8. April 30, 2026
    Construction Mayor says demolition is finished and Compass has begun construction News report · April 2026
The buildings

Specs

Who is involved

Owners, partners and builders

Owners
  • Compass Datacenters (Dallas, CEO Chris Crosby): developer and owner
  • Transformco: seller after the Sears bankruptcy
Decision-makers
  • Hoffman Estates Village Board: site plan, license and tax classification
  • Commonwealth Edison: utility
  • Illinois Commerce Commission: tariff regulator
Still unknown

Open questions

Where this comes from

59 records from 20 documents

Drawn from news reports, company statements, public and commercial datasets and utility regulator dockets, each kept with its date and source. The bar shows documents by type.

News report 13Company 4Dataset 2Utility regulator 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (4)
  • County code: 17031
    “Located in Cook County, the campus will feature five buildings. Site: 3333 Beverly Road, Hoffman Estates (Cook County -> 17031; halls, substation on the one parcel).”
  • Utility: ComEd (Commonwealth Edison)
    “ComEd is delivering infrastructure upgrades for this project, including a new onsite substation that will be energized in mid-2026 to power the site.”
  • Project status: clearing - demolition complete; substation in progress; data center buildings not started in sources checked
    “ComEd is delivering infrastructure upgrades for this project, including a new onsite substation that will be energized in mid-2026 to power the site.”
  • Compass's Hoffman Estates data centers will use water-free cooling and hydrogenated vegetable oil-based fuels for backup power (Daily Herald, Jun 2024)
    “Compass' data centers will use water-free cooling and hydrogenated vegetable oil-based fuels for backup power, as well as taking additional sustainable measures.”
Money and contracts (15)
  • Projected $10 billion of investment into the area in the coming years per ComEd/Compass release
    “transforming the space with a new data center campus projected to bring $10 billion of investment into the area in the coming years.”
  • Land purchase (recorded deed): contract value 194000000 USD
    “Recorded: Sept. 14, 2023 · Price: $194,000,000 · Mortgage1amount: 367000000 · Grantor: TF HCFFMAN ESTATES IL LLC · Grantee: COMPASS DATACENTERS ORD I LLC · Parcel number: 01-31-201-003 · Address: 685 W HIGGINS RD · City: HOFFMAN ESTATES”
  • Mayor's 2026 State of the Village address (Apr 30, 2026): demolition of the former Sears headquarters finished (2025) and Compass Data Centers began construction on the campus; mayor put the investment at more than $10 b
    “demolition of the former Sears headquarters finished and Compass Data Centers began construction on a new data-center campus, a project the mayor described as an investment of more than $10,000,000,000”
  • Microsoft's Hoffman Estates data center campus (Barrington Road / Lakewood Boulevard, $500M phase 1+2) is a separate project in the same village - do not conflate with Compass at 3333 Beverly Road
    “Microsoft has entered phase 2 of a $500,000,000 data center expansion along Lakewood Boulevard”
  • Demolition of the former Sears headquarters finished during 2025 and Compass began construction of the data center campus (Mayor McLeod, State of the Village address, Apr 30, 2026)
    “demolition of the former Sears headquarters finished and Compass Data Centers began construction on a new data-center campus, a project the mayor described as an investment of more than $10,000,000,000”
  • License Agreement (ComEd right-of-way, 138 kV routes): license ComEd right-of-way license agreement (138 kV routes): Planning, Building & Zoning Committee recommended a license for two underground 138 kV distribution rou
    “The license agreement largely mirrors prior agreements with only minor jurisdictional inclusions.”
  • License Agreement (ComEd right-of-way, Beverly Road): license ComEd right-of-way license agreement (Beverly Road): Village Board approved a license agreement allowing ComEd to install underground electric distribution li
    “a Commonwealth Edison license agreement for underground electric lines to serve the Compass data center”
  • Tax classification (Village of Hoffman Estates): tax incentive Compass Data Center tax classification: Village Board approved a Compass Data Center tax classification item on Feb 17, 2025; the classification type, percen
    “the village agenda and subsequent staff materials should be consulted for the official parcel ID and incentive agreement language”
  • No tenant identified; Compass VP of Development Brett Collard said the company's campuses are primarily developed for a single tenant each and the Hoffman Estates site is likely to do the same
    “Compass Vice President of Development Brett Collard said the company has primarily developed its campuses for a single tenant each and the Hoffman Estates site is likely to do the same.”
  • No tenant identified; Compass VP Development Brett Collard said the company has primarily developed campuses for a single tenant each and Hoffman Estates is likely to do the same (Daily Herald, Jun 2024)
    “Though no specific tenant was identified in advance, a number of tech companies could be in the market for a site of this size, Collard said.”
  • land purchase: purchase price 194 USD million
    “Sears finalized the sale of its 197-acre Chicago-area headquarters for $194M to Compass Datacenters”
  • Compass interest in buying the former Sears HQ first revealed July 2023; purchase closed September 12, 2023: 197 acres at 3333 Beverly Road
    “The site in question covers 197 acres at 3333 Beverly Road, with the purchase closed on September 12.”
  • Hoffman Estates levies an electricity tax on high-volume power users (such as data centers) that will help fund two new fire stations
    “Hoffman Estates has a new electricity tax for high-volume power users (such as data centers) which will help the village to fund two new fire stations.”
  • Hoffman Estates has a new electricity tax for high-volume power users such as data centers, which will help the village fund two new fire stations (per DCD)
    “Hoffman Estates has a new electricity tax for high-volume power users (such as data centers) which will help the village to fund two new fire stations.”
  • Announced: July 20, 2023
    “Dallas-based Compass Datacenters has signed a contract to buy the property, Crain’s Chicago Business reported, citing sources familiar with the transaction.”
Permits and government (9)
  • Demolition of former Sears HQ campus (seven buildings): Kickoff / demolition launch announced
    “We're taking a careful and methodical approach to demolition, setting the stage for doing what we do best - building sustainably and building to last”
  • On-site substation and infrastructure upgrades: Under construction - energization targeted mid-2026
    “ComEd is delivering infrastructure upgrades for this project, including a new onsite substation that will be energized in mid-2026 to power the site.”
  • A different Hoffman Estates data-center rezoning proposal was withdrawn on July 2 after local opposition - it is not the Compass/Sears site, which was approved Feb 17, 2025 and is under construction
    “The July 2 withdrawal removes the current rezoning application from active consideration”
  • As reported by Capitol News Illinois (Mar. 20, 2026), the ICC approved ComEd's r: ICC approves ComEd Rider DE large-load deposit/security tariff revisions (Dockets 25-0677/25-0679), as reported by Capitol News Illinois
    “Under the revised tariff, security deposits for new projects requesting 50-200 megawatts will start at $1 million and increase by $500,000 for each additional 100 megawatts beyond that point.”
  • Village of Hoffman Estates Planning, Building & Zoning Committee:
    “The Planning, Building & Zoning Committee on Nov. 24 voted to recommend approval of a license agreement with Commonwealth Edison (ComEd) authorizing two underground electric distribution routes”
  • Village of Hoffman Estates Village Board:
    “a license agreement with Commonwealth Edison for underground electric distribution in Beverly Road”
  • Village of Hoffman Estates Village Board:
    “The board also approved an ordinance granting preliminary and final site plan approval for a ComEd substation located at a record line described in the agenda as "700000000005000 Boulevard."”
  • Village of Hoffman Estates Village Board:
    “Compass Data Center preliminary/final plat and site plan (3333 Beverly Road): recorded roll call responses: Trustee Nolte/Noel - Aye; Trustee Palafis - Aye; Trustee Staunton - Aye; Trustee Keneen - Aye; Trustee Mills - Aye; Mayor McLeod - Aye. Outcome: approved.”
  • Village of Hoffman Estates Village Board:
    “Hoffman Estates approves consent agenda including Compass Data Center tax classification and site plan”
Site and other (7)
  • Building count: 5 buildings
    “The new Compass site represents the Dallas-based company's first data center campus in Illinois, bringing five hyperscale, or high-capacity and scalable facilities, onto the nearly 200-acre site.”
  • Developer: Compass Datacenters
    “The new Compass site represents the Dallas-based company's first data center campus in Illinois, bringing five hyperscale, or high-capacity and scalable facilities, onto the nearly 200-acre site.”
  • ComEd / Compass / Village kickoff event June 13, 2024: demolition of the seven-building Sears campus under way (American Demolition), concrete and asphalt to be reused as fill
    “We are taking a careful and methodical approach to demolition, setting the stage for doing what we do best - building sustainably and building to last, said Compass CEO Chris Crosby.”
  • Project status: under construction
    “demolition of the former Sears headquarters finished and Compass Data Centers began construction on a new data-center campus”
  • Village 2026 State of the Village address (Apr 30 2026, as reported): 2025 was a transformational year as demolition of the former Sears headquarters finished and Compass began construction on the campus; the began-const
    “demolition of the former Sears headquarters finished and Compass Data Centers began construction on a new data-center campus”
  • Site location: 3333 Beverly Road, Hoffman Estates, IL (former Sears headquarters campus)
    “The site in question covers 197 acres at 3333 Beverly Road, with the purchase closed on September 12.”
  • Site acres: 197 acres
    “The site in question covers 197 acres at 3333 Beverly Road, with the purchase closed on September 12.”

Imagery and records: County deeds: ATTOM.