Power and the grid
- PSE&G grid service via a new 69/26 kV substation Substation approvedno MW or service agreement on public record; substation approved Apr. 24, 2025 News report · Oct. 2026
- Existing on-campus cogeneration plant (EF Kenilworth) Existing, role unconfirmed29 MW; separate owner and air permit; sells to the host and the utility; not confirmed as supply for the data center News report · Oct. 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- April 24, 2025Substation approvedThe Planning Board approves a 1.3-acre PSE&G substation that steps 69 kV feeds down to 26 kV. News report · Oct. 2026
- 2026Cogeneration plant emissions raisedResidents cite the existing plant's emissions and worry they would grow if it supplied the data center around the clock. News report · Oct. 2026
- April 6, 2026Cogeneration permit renewal proposedThe state proposes renewing the plant's air permit, which is separate from the data center. State agency · Oct. 2026
- No public electric service agreement with PSE&G was found. Analysis · Oct. 2026
Permits checklist
2 pending · 4 granted · 1 checked, nothing on file
Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.
- ◷Building permit PendingBorough of Kenilworth · Sept. 2025: $2.7M application reported; not confirmed against borough records News report · Oct. 2026
- ◷Redevelopment agreement and PILOT PendingKenilworth Mayor and Council · May 6, 2026: unsigned in May 2026; an aggregator reports a June 30 vote (unverified) Local government · Oct. 2026
- ✓Redevelopment plan GrantedKenilworth Borough Council · Oct. 2024: adopted Oct. 2024 Local government · Oct. 2026
- ✓Site plan for the data center GrantedKenilworth Planning Board · May 15, 2025: two minor variances; 45-day appeal period expired July 2025 Local government · Oct. 2026
- ✓Substation site plan GrantedKenilworth Planning Board · April 24, 2025: PSE&G substation News report · Oct. 2026
- ✓Subdivision into four lots GrantedKenilworth Planning Board · April 28, 2026: approved over 95 emails of opposition News report · Oct. 2026
- –Checked, nothing on file: Air permit for data center generators
What could slow it down
- HighLocal oppositionA petition passed 12,000 signatures, residents from nine towns have spoken against it, and protests continued at the site in Oct. 2026. News report · Oct. 2026
- HighBorough agreement unsignedThe mayor said the redevelopment and PILOT agreement, the borough's remaining lever, was still being negotiated; the borough's redeveloper designation lapsed twice. News report · Oct. 2026
- MediumState tax credit under reviewThe state paused the program in June 2026 after CoreWeave became its only awardee. News report · Oct. 2026
- MediumPower and air permits unclearNo service agreement or generator air permit is on record, and the existing cogeneration plant's role is unresolved. Analysis · Oct. 2026
Money on record
What happened, and what is due
- Oct. 2024Site CoreWeave announces a long-term lease of Building 11 and the borough adopts the redevelopment plan. News report · Oct. 2026
- April 24, 2025Power Planning Board approves the PSE&G substation. News report · Oct. 2026
- May 15, 2025Permits Planning Board approves the data center site plan; the approval was memorialized May 27. Local government · Oct. 2026
- June 2025Money CoreWeave forms a joint venture (85% developer, 15% CoreWeave) that buys the building. SEC filing · Oct. 2026
- Nov. 2025Money State economic development board awards CoreWeave a $250M tax credit. News report · Oct. 2026
- Dec. 4, 2025Money A $555M construction loan is reported (press). News report · Oct. 2026
- April 28, 2026Permits Planning Board approves a four-lot subdivision as about 40 residents speak against it. News report · Oct. 2026
- June 3, 2026Site More than 100 residents pack a council meeting to protest. News report · Oct. 2026
- Aug. 27, 2026Money New Jersey ends the remaining uncommitted data center tax credits; CoreWeave's award stays. News report · Oct. 2026
- Oct. 9, 2026Site Council hires a firm for an independent technical review, paid from CoreWeave's escrow. News report · Oct. 2026
Since Aug. 2025: 1 FAA filing (Aug. 2025): a 140 ft crane. FAA · Aug. 2025
Specs
- Closed loop: glycol cooling; no municipal water for cooling Local government · Oct. 2026
Owners, partners and builders
- CoreWeave: operator and 15% venture partner
- Kenilworth joint venture: unnamed third-party developer holds 85%
- Onyx Equities, Machine Investment Group and Pivot Real Estate Partners: sold Building 11
- Merck: former owner
- Kenilworth Planning Board and Mayor and Council
- New Jersey Economic Development Authority
- New Jersey DEP
- PSE&G: utility
- EF Kenilworth LLC (Atlantic Power): cogeneration plant owner
- GLAS USA: reported lender
- Union County Residents Alliance Coalition
Open questions
- Whether the borough signs a redevelopment and PILOT agreement.
- IT versus utility MW and the PSE&G service terms.
- Whether the cogeneration plant supplies the campus.
132 records from 33 documents
Drawn from news reports, our own analysis, securities filings, state agency records, local government records and public and commercial datasets, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (11)
- Stated campus size: 250 MW“Developing, as part of a joint venture, a new data center campus in Kenilworth, NJ, with capacity of up to 250MW.”SEC filing · Aug. 2025 · grade A
- Power plan: grid + on-site cogeneration, PSE&G grid service via a new 69/26 kV substation, with the pre-existing on-campus cogeneration plant; borough describes the property as having its own power grid“The property has its own power grid”Local government · Oct. 2026 · grade B
- Utility: PSE&G“PSE&G will be providing power to the site and is upgrading the local infrastructure.”News report · Oct. 2026 · grade C
- Stated campus size: 250 MW“Fully built, CoreWeave says the Kenilworth campus could require up to 250 megawatts of power”News report · Oct. 2026 · grade C
- IT capacity: not stated“DOCUMENTED ABSENCE: the 10-Q's Kenilworth JV note states equity interests and dollars only; no MW figure is given for the campus in any CoreWeave filing reviewed”Analysis · Oct. 2026 · grade C
- Utility service: not stated“PSE&G will be providing power to the site and is upgrading the local infrastructure”Analysis · Oct. 2026 · grade C
- On-site generation: 29 MW“CoreWeave intends to use the roughly 29-megawatt plant as a base power source for its data center, Ikeda told the council”News report · Oct. 2026 · grade C
- On-site generation: not stated“DOCUMENTED ABSENCE: the NJDEP BOSS public-notices index at capture lists no Kenilworth data-center permit; the only Kenilworth air document is the EF Kenilworth Title V renewal”Analysis · Oct. 2026 · grade C
- Utility: PSE&G (Public Service Electric & Gas)“PSE&G will be providing power to the site and is upgrading the local infrastructure”News report · Oct. 2026 · grade C
- Substation: Pre-existing campus substation described as 50 MW; new PSE&G substation approved April 24, 2025 (approx. 1.3 acres; 69 kV feed stepped down to 26 kV; three transformers)“leveraging its trove of high-end laboratories, support facilities and a robust utility infrastructure such as a 50-megawatt substation, cogeneration and chiller plants and a central boiler facility”News report · Oct. 2026 · grade C
- EF Kenilworth cogeneration plant emissions raised at council: the plant is classified by regulators as a major source; expert testimony cited EPA estimates of approx. 5 tpy PM2.5, 76 tpy NOx and 2 tpy SO2 while running a“the plant currently emits about five tons of fine particulate matter, 76 tons of nitrogen oxides and two tons of sulfur oxides annually, while running at only an estimated 50 to 60 percent of its full capacity”News report · Oct. 2026 · grade C
Money and contracts (46)
- Tenant status: owner-operator, self-developed through the Kenilworth JV; no tenant lease for the campus“Currently, with our joint venture in Kenilworth, New Jersey, and in the future with new projects, we are beginning to develop our own data centers, rather than relying on third parties”SEC filing · Oct. 2026 · grade A
- Joint venture agreement: scope“In June 2025, the Company entered into a joint venture (the JV) with a third-party infrastructure developer to support the acquisition and development of a multi-phase data center campus in Kenilworth, New Jersey.”SEC filing · Oct. 2026 · grade A
- Joint venture agreement: equity split 85% developer / 15% CoreWeave“Upon formation, the third-party infrastructure developer obtained an 85% equity interest while the Company holds the remaining 15% equity interest in the JV.”SEC filing · Oct. 2026 · grade A
- Joint venture agreement: contribution 57000000 USD“The Company contributed net assets worth $57 million for its 15% equity interest.”SEC filing · Oct. 2026 · grade A
- Joint venture agreement: funding structure“The JV will construct and develop the campus using a combination of additional debt and equity capital.”SEC filing · Oct. 2026 · grade A
- Joint venture agreement: accounting / carrying amount 57000000 USD“The carrying amount of the Company's investment in the JV is $57 million as of September 30, 2025.”SEC filing · Oct. 2026 · grade A
- Borough redevelopment agreement / PILOT: status, NOT executed (under negotiation at May 6, 2026)“Our team and I are working day in and day out to negotiate a PILOT agreement with real accountability for CoreWeave and a strong community benefits framework”Local government · Oct. 2026 · grade A
- purchase: purchase price 322 USD million“In a transaction valued at $322 million, CoreWeave has purchased part of the 107-acre campus.”News report · Oct. 2026 · grade C
- lease: lease of building 11“the GPU cloud firm has signed a long-term lease with an Onyx Equities and Machine Investment Group partnership for the entirety of building 11”News report · Oct. 2026 · grade C
- Tenants: No third-party tenant, CoreWeave itself (owner-operator); cloud end-customers not named for this site“We are incredibly excited to open a next-generation data center in CoreWeave's home state of New Jersey”News report · Oct. 2026 · grade C
- Stage: building, approvals final, but locally contested; redevelopment agreement / PILOT unexecuted“The Redevelopment Plan makes a redeveloper's designation conditional on signing a Redevelopment Agreement with the borough. As of June 2026, that agreement has not been signed for this parcel”News report · Oct. 2026 · grade C
- Building sq ft: 280000 sq ft“CoreWeave plans to invest $1.2 billion in converting the 280,000 sq ft (26,010 sqm) former lab and manufacturing building into a data center”News report · Oct. 2026 · grade C
- Site acres: 107 acres“In a transaction valued at $322 million, CoreWeave has purchased part of the 107-acre campus”News report · Oct. 2026 · grade C
- Investment: 1760000000 USD“The roughly $1.76 billion project is more than 17 times the program's $100 million minimum threshold”News report · Oct. 2026 · grade C
- First announced: Oct. 2024“CoreWeave plans to invest $1.2 billion in converting the 280,000 sq ft (26,010 sqm) former lab and manufacturing building into a data center”News report · Oct. 2026 · grade C
- Building lease (superseded by JV acquisition): scope“has signed a long-term lease with an Onyx Equities and Machine Investment Group partnership for the entirety of building 11 at The Northeast Science & Technology Center (NEST) in Kenilworth”News report · Oct. 2026 · grade C
- Building lease (superseded by JV acquisition): investment commitment 1200000000 USD“CoreWeave plans to invest $1.2 billion in converting the 280,000 sq ft (26,010 sqm) former lab and manufacturing building into a data center”News report · Oct. 2026 · grade C
- Building lease (superseded by JV acquisition): landlord contribution 50000000 USD“The Onyx Equities-led venture also expects to spend over $50 million on the project”News report · Oct. 2026 · grade C
- Building lease (superseded by JV acquisition): term, FINDING (length not disclosed)“DOCUMENTED ABSENCE: the October 2024 lease is described only as long-term in every opened source; no term length, rent, or renewal terms are public”Analysis · Oct. 2026 · grade C
- Building lease (superseded by JV acquisition): termination, FINDING (clause not disclosed)“DOCUMENTED ABSENCE: no termination, cancellation, or exit clause for the October 2024 lease is stated in any opened source; the lease itself is not public”Analysis · Oct. 2026 · grade C
- Joint venture agreement: termination / exit, FINDING (terms not disclosed)“DOCUMENTED ABSENCE: no JV termination, exit, buy-sell, or deadlock terms are disclosed in any filing; the 10-K risk factors note only that CoreWeave operates such ventures without sole decision-making authority”Analysis · Oct. 2026 · grade C
- Asset purchase: scope / price 322000000 USD“In a transaction valued at $322 million, CoreWeave has purchased part of the 107-acre campus”News report · Oct. 2026 · grade C
- State incentive award, Next New Jersey Program - AI: award amount 250000000 USD“CoreWeave qualifies for the maximum allowable tax credit of $50 million per year, to be issued annually over the first five years of a 10-year commitment period”News report · Oct. 2026 · grade C
- State incentive award, Next New Jersey Program - AI: disbursement schedule 50000000 USD/year“CoreWeave qualifies for the maximum allowable tax credit of $50 million per year, to be issued annually over the first five years of a 10-year commitment period”News report · Oct. 2026 · grade C
- State incentive award, Next New Jersey Program - AI: commitment period 10 years“CoreWeave qualifies for the maximum allowable tax credit of $50 million per year, to be issued annually over the first five years of a 10-year commitment period”News report · Oct. 2026 · grade C
- State incentive award, Next New Jersey Program - AI: jobs commitment 143 jobs“CoreWeave will create 143 high-quality, innovation-driven positions that exceed the required 120 percent of the county's median salary”News report · Oct. 2026 · grade C
- State incentive award, Next New Jersey Program - AI: investment commitment 1760000000 USD“The roughly $1.76 billion project is more than 17 times the program's $100 million minimum threshold”News report · Oct. 2026 · grade C
- State incentive award, Next New Jersey Program - AI: clawback / revocation (performance-based)“The incentive is performance-based, meaning the state can reduce or revoke the tax credits if CoreWeave fails to meet commitments”News report · Oct. 2026 · grade C
- State incentive award, Next New Jersey Program - AI: environmental condition“CoreWeave's main obligation was to meet minimum environmental and sustainability standards”News report · Oct. 2026 · grade C
- State incentive award, Next New Jersey Program - AI: community benefit, FINDING (not required)“the older Aspire and Emerge programs required community benefit agreements for projects over $10 million. This one did not”News report · Oct. 2026 · grade C
- State incentive award, Next New Jersey Program - AI: termination, FINDING (executed agreement not public)“DOCUMENTED ABSENCE: the executed NJEDA incentive agreement is not public; beyond the reported performance-based reduction/revocation language, no termination or recapture schedule is stated in any opened source”Analysis · Oct. 2026 · grade C
- Borough redevelopment agreement / PILOT: condition, redeveloper designation lapsed twice“Resolutions 25-129 and 25-231 each set a deadline to sign that agreement, and each provided that the designation would automatically expire if the deadline passed”News report · Oct. 2026 · grade C
- Borough redevelopment agreement / PILOT: status, aggregator reports consent-agenda passage June 30, 2026 (UNVERIFIED)“approving a consent agenda that included Resolution 26-172, a redevelopment agreement related to the Onyx/Nest campus”News report · Oct. 2026 · grade C
- Construction financing: loan amount 555000000 USD“CoreWeave has obtained a $555 million loan from GLAS USA for its ongoing data center conversion project at 2000 Galloping Hill Road in Kenilworth, N.J., according to Yardi Matrix data”News report · Oct. 2026 · grade C
- Electric service (PSE&G): service, FINDING (no public ESA)“DOCUMENTED ABSENCE: no electric service agreement, interconnection agreement, tariff filing, or contracted MW for this campus is public; PSE&G stated only that it is upgrading the local infrastructure for the site”Analysis · Oct. 2026 · grade C
- Borough officials and CoreWeave operated under a non-disclosure agreement during the approval period, per an internal borough email obtained via OPRA and reported by The Central Jerseyan (no records request was filed by“An internal email from June 2025 shows Ash telling colleagues, with the Mayor copied, we all signed the NDA”News report · Oct. 2026 · grade C
- Protests continued at the active construction site in October 2026; the project remains under construction and not operating“Residents in the small borough of Kenilworth, NJ are taking to the streets to rally against the ongoing construction of a massive $1.8 billion AI data center”News report · Oct. 2026 · grade C
- Source record“CoreWeave has obtained a $555 million loan from GLAS USA for its ongoing data center conversion project”News report · Oct. 2026 · grade C
- CoreWeave obtained a $555 million loan from GLAS USA for the Kenilworth conversion project“CoreWeave has obtained a $555 million loan from GLAS USA for its ongoing data center conversion project at 2000 Galloping Hill Road in Kenilworth, N.J.”News report · Nov. 2025 · grade C
- tax credit: award amount 250 USD million“CoreWeave has started construction on a nearly $1.8 billion data center in Kenilworth with the help of what will be a five-year, $250 million tax credit award”News report · Nov. 2025 · grade C
- tax credit: commitment period 10 years“CoreWeave qualifies for the maximum allowable tax credit of $50 million per year, to be issued annually over the first five years of a 10-year commitment period”News report · Nov. 2025 · grade C
- Construction began mid-September 2025: 108,100 sq ft of new construction plus retrofit of the existing 284,500 sq ft 11 NEST building“That includes 108,100 square feet of new construction and a retrofit of an existing 284,500-square-foot building known as 11 NEST”News report · Nov. 2025 · grade C
- Tenant status: owner-occupied (owner-operator since Aug 2025 purchase)“In a shakeup for the sprawling 102-acre campus in Kenilworth, CoreWeave has purchased a data center site at NEST for $322 million.”News report · Aug. 2025 · grade C
- Tenants: CoreWeave (owner-operator; no end customer named for this site)“We are pleased to announce that CoreWeave has purchased the 280,000-square-foot building it had already secured by lease and the land immediately around it at Northeast Science and Technology Center in Kenilworth, NJ.”News report · Aug. 2025 · grade C
- Lease superseded by ownership: CoreWeave purchased the 11 NEST building and adjacent 27 acres from the Onyx Equities / Machine Investment Group JV for USD 322M (announced Aug 1, 2025) and became owner-operator; the Oct 2“We are pleased to announce that CoreWeave has purchased the 280,000-square-foot building it had already secured by lease and the land immediately around it at Northeast Science and Technology Center in Kenilworth, NJ.”News report · Aug. 2025 · grade C
- Tenant lease: execution“CoreWeave signed on with a long-term lease last October for the entirety of 11 NEST.”News report · Oct. 2024 · grade C
Permits and government (22)
- Redevelopment plan (zoning): adopted“the redevelopment of this site was approved by council in October of 2024 and the data center was approved by the planning board in May of 2025”Local government · Oct. 2026 · grade A
- Site plan, data center: approved“at the last Planning Board meeting on May 15, 2025, the Board heard and approved an application regarding the CoreWeave Data Center, 2000 Galloping Hill Road, Kenilworth, NJ”Local government · Oct. 2026 · grade A
- Air operating permit (Title V), initial: approved“Initial Operating Permit Approval Date: January 4, 2001”State agency · Oct. 2026 · grade A
- Air operating permit (Title V), renewal: proposed (public comment)“Cogeneration: Production of electrical and thermal energy for sale to host facility and power utility”State agency · Oct. 2026 · grade A
- Kenilworth Planning Board (special meeting): Application #25-003, CoreWeave Inc. data center site plan, 2000 Galloping Hill Road (Building K-11)“at the last Planning Board meeting on May 15, 2025, the Board heard and approved an application regarding the CoreWeave Data Center, 2000 Galloping Hill Road, Kenilworth, NJ”Local government · Oct. 2026 · grade A
- Kenilworth Planning Board: Adoption of the memorializing resolution for Application #25-003 (CoreWeave data center)“Picerno voted yes, Mr. Scorese voted yes, Mr. Clementi voted yes, Mr. Laudati voted yes, Mr. Scuderi voted yes, Mr. Grimaldi voted yes and Mr. Pugliese voted yes”Local government · Oct. 2026 · grade A
- Kenilworth Mayor & Council: CoreWeave project status, Mayor's statement; Borough Attorney on the finality of the 2025 approvals; PILOT / redevelopment agreement negotiation“the planning board granted site plan approval on May 15, 2025, and there is a 45-day period to appeal the decision from the planning board and that time expired in July of 2025”Local government · Oct. 2026 · grade A
- FAA OE/AAA: Determined - No Hazard“Temporary crane for steel erection.”FAA · Aug. 2025 · grade A
- Air preconstruction permit, data-center generator fleet: not located (negative search)“PN-DC1 4405 Rt 1 South Brunswick Twp, NJ 08540”State agency · Oct. 2026 · grade B
- Site plan, electrical substation: approved“the facility will receive 69 kV feeder lines and step that voltage down to 26 kV for the data center”News report · Oct. 2026 · grade C
- Building permit application: filed“Councilman Morrow said a building permit valued at $2.7 million was filed by CoreWeave”News report · Oct. 2026 · grade C
- Major subdivision (four lots): approved“On April 28, 2026, the 36-acre parcel was subdivided into four new lots”News report · Oct. 2026 · grade C
- Application 26-002 subdivision hearing: 95 emails of opposition on file and approx. 40 residents from Kenilworth and nine surrounding towns spoke against the project“The board's meeting minutes record 95 emails of opposition on file”News report · Oct. 2026 · grade C
- More than 100 residents packed the Kenilworth council meeting to protest the data center (Patch reporting, via NJBallot)“Patch reported that more than 100 people packed the June 3 Kenilworth council meeting”News report · Oct. 2026 · grade C
- NJEDA paused the Next New Jersey Program - AI in June 2026 for an internal review; CoreWeave was the program's only awardee“The tax credit went to one company, CoreWeave, before the state Economic Development Authority paused the program in June for an internal review”News report · Oct. 2026 · grade C
- End Data Center Tax Credits Act (A5165/S4390) signed by Gov. Sherrill: eliminates the remaining $250M of uncommitted Next NJ - AI credits; CoreWeave's awarded $250M remains intact. Part of the Governor's four-pillar data“New Jersey Gov. Mikie Sherrill signed legislation Thursday ending a tax credit program that encouraged the development of new data centers”News report · Oct. 2026 · grade C
- Companion law signed the same day requiring New Jersey data centers to report energy and water usage to the state (semi-annual reports to the BPU per bill reporting), will apply to this campus once operating“She also signed legislation Thursday requiring the facilities to report their energy and water usage to the state”News report · Oct. 2026 · grade C
- Kenilworth Planning Board: Site plan, PSE&G substation (approx. 1.3 acres) to serve the future data center at 2000 Galloping Hill Road“the facility will receive 69 kV feeder lines and step that voltage down to 26 kV for the data center”News report · Oct. 2026 · grade C
- Kenilworth Planning Board: Application 26-002, preliminary/final major subdivision of the CoreWeave parcel into four lots“On April 28, 2026, the 36-acre parcel was subdivided into four new lots”News report · Oct. 2026 · grade C
- Kenilworth Mayor & Council: Public comment, resident opposition to the CoreWeave data center“Patch reported that more than 100 people packed the June 3 Kenilworth council meeting”News report · Oct. 2026 · grade C
- Kenilworth Mayor & Council: Resolution 26-2-26, professional-services agreement with Arlington Analytics to coordinate an independent technical review of the CoreWeave project“The Kenilworth Borough Council unanimously approved Resolution 26-2-26 authorizing a professional-services agreement with Arlington Analytics to coordinate technical reviews of the proposed CoreWeave data-center project”News report · Oct. 2026 · grade C
- tax credit approval: approved“The planned 250-megawatt project is now advancing after the New Jersey Economic Development Authority approved the tax credit earlier this month”News report · Nov. 2025 · grade C
Site and other (17)
- Name: CoreWeave Kenilworth (NEST)“In June 2025, the Company entered into a joint venture (the JV) with a third-party infrastructure developer to support the acquisition and development of a multi-phase data center campus in Kenilworth, New Jersey.”SEC filing · Oct. 2026 · grade A
- Address: 2000 Galloping Hill Road, Kenilworth, NJ 07033“CoreWeave Data Center, 2000 Galloping Hill Road, Kenilworth, NJ”Local government · Oct. 2026 · grade A
- Developer: Kenilworth joint venture, unnamed third-party infrastructure developer (85%) with CoreWeave, Inc. (15%), formed June 2025“In June 2025, the Company entered into a joint venture (the JV) with a third-party infrastructure developer to support the acquisition and development of a multi-phase data center campus in Kenilworth, New Jersey.”SEC filing · Oct. 2026 · grade A
- Operator: CoreWeave, Inc.“Currently, with our joint venture in Kenilworth, New Jersey, and in the future with new projects, we are beginning to develop our own data centers, rather than relying on third parties”SEC filing · Oct. 2026 · grade A
- County code: Union County, NJ (34039)“CoreWeave Data Center, 2000 Galloping Hill Road, Kenilworth, NJ”Local government · Oct. 2026 · grade B
- Cooling: closed-loop glycol, no municipal water used for cooling“This facility is engineered using a closed-loop system using Glycol so that there is no use of our water”Local government · Oct. 2026 · grade B
- Site address: 2000 Galloping Hill Road, Kenilworth, NJ“CoreWeave signed a lease for building 11 at the campus, located at 2000 Galloping Hill Road, in October 2024.”News report · Oct. 2026 · grade C
- Aliases: NEST Kenilworth; Northeast Science & Technology Center; 11 NEST; Building K-11“has signed a long-term lease with an Onyx Equities and Machine Investment Group partnership for the entirety of building 11 at The Northeast Science & Technology Center (NEST) in Kenilworth”News report · Oct. 2026 · grade C
- Construction stage: building“According to the EDA, CoreWeave began construction in mid-September and expects the 392,600-square-foot AI data center to be operational in early 2027”News report · Oct. 2026 · grade C
- Original target date: 2027“According to the EDA, CoreWeave began construction in mid-September and expects the 392,600-square-foot AI data center to be operational in early 2027”News report · Oct. 2026 · grade C
- Current target date: 2027“According to the EDA, CoreWeave began construction in mid-September and expects the 392,600-square-foot AI data center to be operational in early 2027”News report · Oct. 2026 · grade C
- Building sq ft: 392600 sq ft“According to the EDA, CoreWeave began construction in mid-September and expects the 392,600-square-foot AI data center to be operational in early 2027”News report · Oct. 2026 · grade C
- Jobs committed: 143 jobs“CoreWeave will create 143 high-quality, innovation-driven positions that exceed the required 120 percent of the county's median salary”News report · Oct. 2026 · grade C
- A Change.org petition urging Kenilworth to block the planned data centers passed 12,000 signatures; the Union County Residents Alliance Coalition (UCRAC) formed to oppose Union County data centers“a Change.org petition urging Kenilworth to block the planned data centers has more than 12,000 signatures”News report · Oct. 2026 · grade C
- No NJDEP enforcement action against the Kenilworth campus was located in opened sources“If it fails to do so in time, the company must stop operating its generators at the Vineland location, according to the DEP”News report · Oct. 2026 · grade C
- Neighbors circulated a petition opposing construction that gathered over 1,500 signatures by mid-April 2026“Neighbors circulated a petition opposing construction that gathered over 1,500 signatures by mid-April.”News report · April 2026 · grade C
- Project status: under construction“According to the EDA, CoreWeave began construction in mid-September and expects the 392,600-square-foot AI data center to be operational in early 2027.”News report · Nov. 2025 · grade C