Power and the grid
- Evergy grid service Not on recordMW not disclosed; no state docket names the project; the developer says it would fund dedicated power infrastructure (press) News report · July 2026
- Diesel generators (Tier 2) Described in filingbackup equipment only, to idle almost all year; not a power supply Company · June 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Nov. 2025Evergy large-load tariff approvedThe state commission approves Evergy's tariff for loads over 75 MW. It is the framework, not a contract for this campus. News report · Nov. 2025
- As of Oct. 2026No state docket for the projectNo Kansas Corporation Commission docket names DAMAC or Heartland. News report · Oct. 2026
- Service would run under Evergy's approved large-load tariff if the undisclosed load reaches 75 MW, or under standard tariffs; neither produces a project docket. News report · Oct. 2026
Permits checklist
2 denied · 1 granted · 2 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- ✕Final site plan FSP2026-0002 DeniedEdgerton Planning Commission · June 2026: commission denied after a 2-2 tie in May; its role is advisory on appeal News report · May 2026
- ✕Data center moratorium DeniedEdgerton City Council · June 11, 2026: moratorium resolution denied 3-2; none in force Local government · June 2026
- ✓Appeal of the site plan denial GrantedEdgerton City Council · July 16, 2026: approved 4-0 with conditions that DAMAC meet all codes; final plat still pending Local government · July 2026
- –Checked, nothing on file: Air permit, Tax abatement or development agreement
What could slow it down
- HighBallot petition litigationResidents' petition for a public vote on data centers is in court and could constrain the project. see Lawsuits
- MediumPlat approvals outstandingA final plat still had to return to the planning commission and then the council after the July override. News report · July 2026
- MediumContested processThe override came at a special meeting where public comment was not permitted. News report · July 2026
- WatchGenerators and noiseThe commission denied the plan amid questions on noise and expansion; the developer says diesel units are state-permitted backup that idle most of the year. News report · July 2026
2 cases on record
- Struck Sept. 3, 2026 City of Edgerton v. Twente, Schmidt and Public Trust CollectiveJohnson County District Court News report · Sept. 2026city sought to void the data center petition; judge ruled it violated the Kansas Public Speech Protection Act (press)
- Pending Mandamus suit to place the petition on the ballotJohnson County District Court News report · Sept. 2026emergency motion denied; city ordered to show cause; hearing Sept. 24, 2026 (press)
Money on record
$860M reported project value (press; not in city minutes). News report · July 2026
What happened, and what is due
- Oct. 6, 2025Paper trail DAMAC Digital Solutions Kansas LLC registered in Delaware
- Nov. 2025Power Kansas regulators approve Evergy's large-load tariff News report · Nov. 2025
- May 12, 2026Permits Planning commission motion to approve the site plan fails 2-2 and is tabled News report · May 2026
- June 11, 2026Permits The council denies a proposed moratorium on data center applications, 3-2 Local government · June 2026
- July 16, 2026Permits The council overrides the planning commission's denial in a special meeting with no public comment Local government · July 2026
- Aug. 4, 2026Legal The city sues petition organizers to void a petition for a public vote (press) News report · Aug. 2026
- Sept. 3, 2026Legal A judge strikes the city's suit under the state speech-protection law News report · Sept. 2026
- Sept. 24, 2026Legal Hearing in a separate suit seeking to put the petition on the ballot; no ruling found by Oct. 19 News report · Sept. 2026
Specs
- Existing building: zoned Logistics Park, which allows data centers as a permitted use (developer filing) Local government · June 2026
- Advanced cooling: developer says water use will be minimized (press) News report · July 2026
Owners, partners and builders
- DAMAC Digital Solutions Kansas, LLC: applicant
- DAMAC Digital (formerly Edgenex): parent, founded 2021 by Hussain Sajwani
- Edgerton City Council: overrode the commission 4-0
- Edgerton Planning Commission: denied the plan in June 2026
- Johnson County District Court: petition cases
Open questions
- Campus MW.
- Final plat approval.
- Court ruling on the petition.
- Air permit and Evergy service terms.
27 records from 12 documents
Drawn from news reports, local government records, company statements and business registries, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (2)
- Across the planning commission record, the council override and the city's FAQ, DAMAC has never stated Heartland's MW - not in its own June 9, 2026 filing. The only numbers in circulation are the 378,000 sq ft warehouse“Heartland Data Center - Developed by DAMAC”Company · July 2026 · grade B
- Planning Commission sequence: on May 12, 2026 a motion to approve the final site plan failed 2-2 and the plan was tabled so DAMAC could supply diesel-generator and noise information; DAMAC submitted supplemental engineer“A motion to approve was made Tuesday, but failed by a 2-2 vote. Planning Commission Chair Tina Mathos and Commissioner Ray Soemer voted to approve”News report · May 2026 · grade C
Money and contracts (3)
- County code: 20091“The city council unanimously overrode the commission's June denial of DAMAC Digital's $860 million facility”News report · July 2026 · grade C
- Project value reported at USD 860 million (Johnson County Post, Jul 2026): conversion of an existing approximately 400,000 sq ft warehouse at Logistics Park Kansas City; Tracker sites additionally claim construction from“Plans for an $860 million data center project in Edgerton are moving forward despite the city's planning commission rejecting it in June.”News report · July 2026 · grade C
- Press describes the project as an $860 million facility; no investment figure appears in the council minutes retrieved, and no MW figure is stated in any source retrieved for this campus“The city council unanimously overrode the commission's June denial of DAMAC Digital's $860 million facility”News report · July 2026 · grade C
Permits and government (8)
- Edgerton City Council (special session):“Councilmember Lewis made motion to approve the appeal, citing the applicant's initial April 16, 2026, application and their commitment to comply with UDC, KDHE, IFC, IBC, and other codes without deviations.”Local government · July 2026 · grade A
- Council denied Resolution No. 06-11-26A, which would have imposed a moratorium on UDC submissions (rezoning, variances, plats, site plans) for data centers; the draft would not have halted applications filed before it. N“Councilmember Lewis motioned to deny item ten on the Business Requiring Action items, seconded by Councilmember Longanecker. The motion carried 3-2 by the following vote: Yes: Longanecker, Lewis, Malloy”Local government · June 2026 · grade A
- Project status: approved“On July 16, the Edgerton City Council unanimously overrode the planning commission's rejection of final plans from Dubai-based DAMAC Digital for a data center project at the Logistics Park Kansas City warehouse at 31800 W. 196th St.”News report · July 2026 · grade C
- DAMAC Digital Solutions Kansas LLC's Project Heartland: Final site plan denied by Planning Commission, denial overridden by City Council (July 16, 2026)“in a special meeting on July 16, local news reports that city councilors overrode the Edgerton Planning Commission's denial”News report · July 2026 · grade C
- Jul 16, 2026: in a special meeting with public comment not permitted, the City Council overrode the Planning Commission's denial and approved DAMAC's appeal (reported as unanimous; the appeal vote was 4-0). A final plat“However, in a special meeting on July 16, local news reports that city councilors overrode the Edgerton Planning Commission's denial. Public comment was not permitted at the meeting.”News report · July 2026 · grade C
- Jun 15, 2026: the Edgerton City Council voted 3-2 to deny a proposed six-month ban on data centers (this campus's jurisdiction, debated alongside this project). No moratorium is in force.“The city council's override comes about a month after the city council voted on June 15 to deny a six-month ban on data centers”News report · June 2026 · grade C
- Announced: May 12, 2026“On Tuesday night, the Edgerton Planning Commission voted 4-0 to approve a preliminary plat that combines three properties to convert an existing 400,000-square-foot warehouse at Logistics Park into a large-scale data center.”News report · May 2026 · grade C
- In November 2025 the KCC approved Evergy's Large Load Power Service tariff, desi: FRAMEWORK: Evergy Large Load Power Service (LLPS) tariff approved (Nov. 2025) - the tariff any 75 MW+ Kansas load signs under“State regulators at the Kansas Corporation Commission in November 2025 approved a large load power service tariff for Evergy”News report · Nov. 2025 · grade C
Legal (3)
- Separate mandamus suit seeking to compel placement of the petition measure on the ballot: emergency motion for immediate placement denied, city ordered to show cause, hearing held September 24, 2026 with briefs due Octob“Judge Goodenow denied an emergency motion for immediate placement but ordered the city to show cause why the measure shouldn't go on the ballot, with a hearing set for September 24, 2026.”News report · Sept. 2026 · grade C
- Johnson County District Court Judge Stephanie Goodenow granted a motion to strike the City's August 4, 2026 lawsuit against petition organizers Carrie Schmidt, Kimberly Twente and Public Trust Collective Inc., ruling it“On Sept. 3 in Johnson County District Court, Judge Stephanie Goodenow sided with defendants Kimberly Twente and Carrie Schmidt, both Edgerton residents, in the city's lawsuit against them”News report · Sept. 2026 · grade C
- Residents gathered signatures on a petition to force a public vote on a data center ordinance; the City of Edgerton sued the petitioners, asking the court for a declaratory judgment that the petition is void (alleged fal“The city is now asking the court for two things: a declaratory judgment stating the petition is void because it contains false statements of fact, and a permanent injunction stopping the ordinance from being passed”News report · Aug. 2026 · grade C