Data center profile · Astra Enterprise Park, De Soto, Johnson County, Kansas

Digital Realty De Soto (Astra North)

Digital Realty's 1,440-acre site in De Soto, Kansas: Evergy contract for 600 MW by early 2028 and up to 2 GW planned; no tenant.

Land bought, pre-construction. Digital Realty closed on the land in Apr. 2026 and says it has an Evergy energy service agreement. No construction is reported; press expects a 2027 start. No tenant is named. City tax-incentive hearing is Nov. 19, 2026.
2 GW
utility power at full delivery under the energy service agreement (company filing)
600 MW by early 2028; this is utility supply, not a stated IT capacity
1,440 acres
bought for about $475M
near Kansas City, per Digital Realty's June 22, 2026 filing
9 buildings
planned, about 3M sq ft
first phase (Astra North) covers about 280 acres
$300M+
transmission upgrades Digital Realty would fund
company statement to the city (press)
OperatorDigital Realty (developer and owner)
CustomerNone announced; Digital Realty says it is in talks with an unnamed major cloud operator
Planned IT capacity1.6 GW at full build-out (our estimate from the company or utility power figure)
First building in serviceOur estimate: 2028 (range 2027 to 2030).
Next deadlineNov. 19, 2026: City council public hearing on a tax increment financing district for Digital Realty
Power

Power and the grid

600 MW contracted

Evergy grid service (large-load tariff)Contracted (company says)
600 MW
Digital Realty says the energy service agreement delivers 600 MW by early 2028, rising to 2 GW at full delivery; the contract itself is not public SEC filing · June 2026
Full build-out ceilingStated, no date
2,000 MW
no date given for full delivery SEC filing · June 2026
ContractedProposed

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. Nov. 6, 2025
    Large-load tariff approved
    Kansas regulators approve Evergy's rate plan for customers of 75 MW or more: 12-year minimum term, 80% minimum bill, two years of collateral and an exit fee. State agency · Oct. 2026
  2. June 22, 2026
    Energy service agreement announced
    Digital Realty says it has signed with Evergy for 600 MW by early 2028, rising to 2 GW. SEC filing · June 2026
  3. Sept. 8, 2026
    Regional transmission plan
    The regional grid operator's draft plan includes a new Sailor substation and a 765 kV line driven by this campus and a neighboring one; not final until Nov. 2026. News report · Oct. 2026
  4. Dec. 8, 2026
    Prepayment ruling due
    Regulators target a decision on whether Evergy may take advance prepayments from large-load customers, which could change contract cash terms. News report · Oct. 2026

Grid upgrades

No grid upgrade for this campus's load is on record. Related grid records in the area:

What is next door

campus3.02 km · 345 kV+ substation3.26 km · 345 kV+ line8.33 km · gas pipelinecampus3.02 km · 345 kV+ substation3.26 km · 345 kV+ line8.33 km · gas pipeline

Distances from mapped lines and plants. OpenStreetMap · Oct. 2026

Permits

Permits checklist

1 pending · 2 granted · 2 checked, nothing on file

Approvals a campus like this normally needs, and what we found.

Risks

What could slow it down

Money

Money on record

$475M
land purchase
for about 1,440 acres, per Digital Realty's June 22, 2026 filing SEC filing · June 2026
$300M+
transmission and substation upgrades
Digital Realty says it will fund them (press estimate) News report · June 2026
$20M
community investment pledge
includes $1,000 a year in utility and property tax credits for 10 years to every De Soto household; announced Oct. 14, 2026, not yet executed News report · Oct. 2026
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Nov. 6, 2025
    Power Kansas regulators approve Evergy's large-load rate plan State agency · Oct. 2026
  2. April 2026
    Site Digital Realty closes on about 1,440 acres at Astra Enterprise Park for about $475M News report · June 2026
  3. June 4, 2026
    Permits Digital Realty introduces the campus to the De Soto City Council; no vote taken News report · Oct. 2026
  4. June 22, 2026
    Site Digital Realty's filing announces the land and an energy service agreement with the local utility for 600 MW by early 2028, rising to 2 GW SEC filing · June 2026
  5. Aug. 6, 2026
    Legal Residents demand an investigation of the city's economic development contract; mayor opens it for future review News report · Oct. 2026
  6. Sept. 8, 2026
    Power Regional grid operator's draft plan adds a Sailor substation and 765 kV line serving this and a neighboring campus News report · Oct. 2026
  7. Oct. 14, 2026
    Money Digital Realty pledges $20M in community investment; residents' petition calls it a bribe ahead of the incentive vote News report · Oct. 2026
  8. Nov. 19, 2026
    Permits City council hearing on a tax increment financing district expected News report · Oct. 2026
  9. 2027
    Construction Press expects construction to begin News report · Oct. 2026
  10. 2028
    Power First 600 MW of utility power due by early 2028 (company) SEC filing · June 2026
The buildings

Specs

280 acres
first phase, Astra North
1M gal a day
water the city would allocate to the site (press)
250 jobs
permanent positions expected once operating
1,000+ workers
expected on site at peak for Astra North
Who is involved

Owners, partners and builders

Owners and developers
  • Digital Realty Trust: developer and site owner
  • Sunflower Redevelopment Group: land seller
  • Kessinger Hunter: operator of Astra Enterprise Park (not a party to this campus)
Power
  • Evergy Kansas Metro: serving utility and contract counterparty
  • Kansas Corporation Commission: approves the tariff
Decision-makers
  • De Soto City Council: tax district
  • De Soto Planning Commission: site plan
Still unknown

Open questions

Where this comes from

121 records from 22 documents

Drawn from news reports, state agency records, securities filings, company statements and public and commercial datasets, each kept with its date and source. The bar shows documents by type.

News report 14State agency 3SEC filing 2Company 2Dataset 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (33)
  • Large-load tariff (LLPS) approval: approved
    “25-1859 – Order on Settlement Agreement. Commissioner Keen moved to approve the Order. Commissioner Kuether seconded the motion. The order was approved.”
  • Utility service: 600 MW
    “Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Utility service: 2,000 MW
    “an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Utility service: 600 MW
    “Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Utility service: 2,000 MW
    “an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Utility service: 600 MW
    “Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Utility service: 2,000 MW
    “an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Interconnection status: ESA signed: Evergy to provide 600 MW of utility power by early 2028, rising to 2,000 MW at full delivery; service under Kansas' large-load tariff (KCC-approved Evergy large load power service rate
    “Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Utility service: 2000
    “rising to two gigawatts at full delivery”
  • large load interconnection request: Energy Service Agreement entered into (announced June 22, 2026): 600 MW by early 2028, rising to 2 GW at full delivery
    “Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Utility: Evergy Kansas Metro, Inc. (Evergy)
    “In the Matter of the Application of Evergy Kansas Metro, Inc., Evergy Kansas South, Inc., and Evergy Kansas Central, Inc. for Approval of Large Load Service Rate Plan and Associated Tariffs.”
  • Nearest power line of 345 kV or more: 3.26 km
    Measured on OpenStreetMap map data.
  • Nearest substation of 345 kV or more: 3.02 km
    Measured on OpenStreetMap map data.
  • Nearest gas pipeline: 8.33 km
    Measured on OpenStreetMap map data.
  • IT capacity: not stated
    “DOCUMENTED ABSENCE: no IT (critical) load figure is stated in any source opened — company release, company project page, KCC LLPS record, or the local/trade press opened. The 600 MW (initial utility delivery) and 2,000 MW (full-delivery ceiling) are utility-side”
  • On-site generation: not stated
    “DOCUMENTED ABSENCE: no onsite generation capacity is stated in any source opened; this is a grid-supplied campus under the Evergy LLPS tariff. Emergency backup generators are mentioned in local reporting without ratings and are not booked as generation.”
  • SPP Board approval and NTC issuance remain pending; no project ID, cost, or in-service date for Sailor has been published
    “SPP's MOPC has endorsed a $23.7 billion transmission plan that includes six more 765-kV projects to address increasing load growth”
  • Utility: Evergy - Energy Service Agreement executed; power billed on Kansas' higher large-load tariff
    “Digital has entered into an energy service agreement with local utility Evergy to provide 600MW of utility power by early 2028, rising to 2GW at full delivery”
  • Stage: Announced only / pre-construction
    “Digital has entered into an energy service agreement with local utility Evergy to provide 600MW of utility power by early 2028, rising to 2GW at full delivery”
  • Current target date: 2028
    “To support development of the site, Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery.”
  • Change.org petition (Demand Real Answers, Not Bribes, on De Soto Data Centers) demands independent water-use, power-demand and household rate-impact disclosure before the November 19, 2026 TIF hearing; residents quoted c
    “A cash credit is no substitute for transparency. The De Soto City Council is expected to hold a public hearing on Nov. 19 on a tax increment financing (TIF) district for Digital Realty.”
  • SPP draft 2026 Integrated Transmission Plan: a proposed Viola–Sailor 765 kV line and a new Sailor substation are driven by the COMBINED De Soto load (Beale Project Pilot + Digital Realty Astra North). The portfolio is no
    “SPP filings indicate Sailor is a planned new substation related to the new load from projects Pilot and Astra North, the data center developments by Beale Infrastructure and Digital Realty in De Soto.”
  • Evergy reports five executed LLPS energy service agreements totaling roughly 2.5 GW of steady-state peak load (Kansas: Beale Infrastructure and Digital Realty; Missouri: Meta and two Google projects). Portfolio context o
    “Campbell touted five executed energy service agreements for data center projects under our LLPS tariffs. Only two of those five are in Kansas, with developers Beale Infrastructure and Digital Realty.”
  • Site: Astra Enterprise Park, W 103rd St & Lexington Ave, De Soto, KS; approx 1,440 acres acquired April 2026 from Sunflower Redevelopment Group (about $475M); first phase 'Astra North' about 280 acres, up to nine buildin
    “Digital has acquired approximately 1,440 acres of land at the Astra Enterprise Park in DeSoto, Kansas, at W 103rd St & Lexington Ave.”
  • Power agreement press: Evergy energy service agreement reported: 600 MW of utility power by early 2028, rising to 2 GW at full delivery (press/company reporting; not an A4 registry record)
    “Digital has entered into an energy service agreement with local utility Evergy to provide 600MW of utility power by early 2028, rising to 2GW at full delivery.”
  • Grid operator: SPP (Southwest Power Pool)
    “SPP filings indicate Sailor is a planned new substation related to the new load from projects Pilot and Astra North, the data center developments by Beale Infrastructure and Digital Realty in De Soto.”
  • Power plan: Grid, Evergy retail service under the KCC LLPS tariff; SPP regional transmission (planned Sailor substation)
    “SPP filings indicate Sailor is a planned new substation related to the new load from projects Pilot and Astra North, the data center developments by Beale Infrastructure and Digital Realty in De Soto.”
  • SPP's draft 2026 Integrated Transmission Plan, previewed to the Kansas Corporation Commission on September 8, 2026, considers three new 765 kV lines in Kansas; the planned Sailor substation is related to the new load fro
    “SPP filings indicate Sailor is a planned new substation related to the new load from projects Pilot and Astra North, the data center developments by Beale Infrastructure and Digital Realty in De Soto.”
  • ESA status: Executed, Energy Service Agreement with Evergy under the LLPS tariff
    “Campbell touted five executed energy service agreements for data center projects under our LLPS tariffs. Only two of those five are in Kansas, with developers Beale Infrastructure and Digital Realty.”
  • Utility service: 600 MW
    “To support development of the site, Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery.”
  • Stated campus size: 2,000 MW
    “Secures Two-Gigawatt Development Site in Kansas City Metro”
  • Original target date: 2028
    “To support development of the site, Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery.”
  • trust debt $185.0 million; 26.8 MW of critical IT capacity; appraiser's stabilized value $463.0 million; owned 25% Digital Realty / 75% GI Partners); The collateral property is in Elk Grove, Illinois and is NOT this campus (
    “DATA 2024-CTR2 is collateralized by the borrower's fee simple interest in one hyperscale data center property located in Elk Grove, Illinois.”
Money and contracts (26)
  • Offtake (Energy Service Agreement): execution
    “Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Offtake (Energy Service Agreement): capacity 600 (initial) MW utility
    “Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Offtake (Energy Service Agreement): capacity 2000 (at full delivery; same agreement - do NOT sum with the 600 MW initial tranche) MW utility
    “an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Offtake (Energy Service Agreement): delivery 600 MW utility
    “Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Energy Service Agreement: capacity 600 MW utility
    “entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • Land purchase: consideration 475000000 USD
    “acquired approximately 1,440 acres of land at Astra Enterprise Park, located near Kansas City to support hyperscale data center development for approximately $475 million”
  • Tenant status: none named
    “Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery”
  • LLPS tariff framework (governs the ESA): term
    “The contract term will be a minimum of 12 years, plus an optional load ramp period of up to 5 years, which most customers are expected to use, for a total contract length of 17 years.”
  • LLPS tariff framework (governs the ESA): minimum billing 80 % of contract demand
    “Customers on the plan will pay a minimum monthly bill based on 80% of their contract demand, regardless of actual usage.”
  • LLPS tariff framework (governs the ESA): collateral
    “They will also be required to provide collateral equal to two years of minimum monthly bills.”
  • LLPS tariff framework (governs the ESA): termination exit fee
    “If the contract is terminated early, an exit fee will apply that will require the customer to pay all minimum bills that would have been billed had the customer continued service.”
  • LLPS tariff framework (governs the ESA): cost assignment
    “any system upgrades that are necessary solely to serve the new/expanded customers will be directly assigned to the new/expanded customer”
  • LLPS tariff framework (governs the ESA): eligibility scope 75 MW threshold
    “The new LLPS rates will apply to any new facility beginning service with a peak load forecast at 75 megawatts (75 MW) or more”
  • Tenants: not stated
    “No tenant announced as of October 18, 2026. On June 4, 2026 the company told the De Soto City Council it was in discussions with an unnamed major cloud infrastructure operator — discussions only; no lease or tenant has been”
  • LLPS tariff framework (governs the ESA): termination notice
    “The settlement also requires a written notice of 36 months before a customer may terminate or change rate schedules”
  • Development agreement / incentives, FINDING: status
    “If the company later requests economic incentives, that would be a separate process requiring a public hearing and city council consideration.”
  • Community investment commitment (announced, not executed): scope 20000000 USD
    “Digital Realty is offering every household in De Soto, Kansas, $1,000 in utility and property tax credits for 10 years, part of a $20 million community investment the company is pledging.”
  • Tenant status: No tenant announced
    “For the site at Astra, we're in discussions with a major cloud infrastructure operator that's a global company with an investment-grade balance sheet”
  • Transmission funding commitment: scope 300000000 USD (estimate, exceeds)
    “All necessary improvements to transmission lines and power substations, operated by Evergy, would be funded entirely by Digital Realty.”
  • Site acres: 1440 acres
    “Digital Realty has acquired approximately 1,440 acres of land at Astra Enterprise Park, located near Kansas City to support hyperscale data center development for approximately $475 million in cash and common units in its operating partnership.”
  • Land price: 475000000 USD
    “Digital Realty has acquired approximately 1,440 acres of land at Astra Enterprise Park, located near Kansas City to support hyperscale data center development for approximately $475 million in cash and common units in its operating partnership.”
  • Land seller: Sunflower Redevelopment Group
    “The site, set to support hyperscale data center development, was acquired from the Sunflower Redevelopment Group in April for approximately $475 million.”
  • Land acquired date: April 2026
    “The site, set to support hyperscale data center development, was acquired from the Sunflower Redevelopment Group in April for approximately $475 million.”
  • Energy Service Agreement (Evergy LLPS): scope 600 MW
    “To support development of the site, Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery.”
  • Energy Service Agreement (Evergy LLPS): delivery schedule 2,000 MW
    “To support development of the site, Digital Realty has entered into an Energy Service Agreement with the local utility to provide 600 megawatts of utility power by early 2028, rising to two gigawatts at full delivery.”
  • Energy Service Agreement (Evergy LLPS): tariff basis
    “Digital will be paying for its energy on Kansas' higher large-load tariff.”
Permits and government (12)
  • Kansas Corporation Commission: Docket No. 25-EKME-315-TAR, Order on Settlement Agreement (25-1859) approving the Evergy Large Load Service Rate Plan and associated tariffs
    “In the Matter of the Application of Evergy Kansas Metro, Inc., Evergy Kansas South, Inc., and Evergy Kansas Central, Inc. for Approval of Large Load Service Rate Plan and Associated Tariffs.”
  • Construction stage: No construction reported, entitlement/planning stage
    “The company acquired two parcels of land at Astra Enterprise Park in May and, as of Thursday, has yet to start the formal process by submitting a site plan”
  • LLPS tariff application: filed
    “Brian Fadoten, a commission presenter, said the application was filed Feb. 11 and that a joint motion for a unanimous settlement was filed Aug. 18”
  • Phase 1 site/development plan: approval reported, UNVERIFIED
    “Digital Realty's hyper-scale data center project, known as Project Jayhawk, has received approval for its first phase from the De Soto Planning Commission in Kansas.”
  • TIF district public hearing: scheduled
    “The De Soto City Council is expected to hold a public hearing on Nov. 19 on a tax increment financing (TIF) district for Digital Realty.”
  • Zoning status: no action required
    “A public hearing won't be a part of the process, as the land is already zoned for this kind of development.”
  • The KCC adopted a briefing schedule in the continuing LLPS docket (25-EKNE-315-TAR) on Evergy's request to confirm it may accept voluntary advance prepayments from qualified large-load customers: responses due October 23
    “The Kansas Corporation Commission adopted an unopposed briefing schedule in Docket No. 25-EKNE-315-TAR on Evergy's request to confirm it may accept voluntary advanced prepayments from qualified large-load customers”
  • Residents allege the city-funded De Soto Chamber/EDC (about $190,000 per year) lobbied for state data-center legislation (Senate Bill 51) affecting the Astra/Sunflower site, and demanded disclosure of any nondisclosure a
    “Our taxpayer dollars are being funneled into a private entity that is actively lobbying the state legislature for Senate Bill 51 and data centers projects that face overwhelming opposition”
  • De Soto City Council: Digital Realty introductory presentation of the De Soto campus (Project Jayhawk), Rafal Rak and Enrique Bellido presenting initial plans for 1,400+ acres at Astra Enterprise Park
    “representatives from Texas-based company Digital Realty introduced initial plans earlier this month in De Soto to develop more than 1,400 acres”
  • De Soto City Council: Residents demand an independent investigation of the city's Chamber/EDC contract and any developer NDAs, citing lobbying for state data-center legislation; mayor opened the matter for future review
    “At the Aug. 6 council meeting, resident Jennifer Sharp urged an 'immediate and independent investigation' into the city's contract with the De Soto Chamber of Commerce and Economic Development Council”
  • Kansas Corporation Commission: SPP briefing on the draft 2026 Integrated Transmission Plan, including the proposed Viola–Sailor 765 kV line and Sailor substation serving the combined De Soto load (Project Pilot and Astra
    “SPP filings indicate Sailor is a planned new substation related to the new load from projects Pilot and Astra North, the data center developments by Beale Infrastructure and Digital Realty in De Soto.”
  • Jurisdiction: City of De Soto (land use) / Kansas Corporation Commission (utility) / SPP-FERC (transmission)
    “A public hearing won't be a part of the process, as the land is already zoned for this kind of development.”
Site and other (14)
  • Site acreage: 1440 acres
    “Digital Realty has acquired approximately 1,440 acres of land at Astra Enterprise Park, located near Kansas City to support hyperscale data center development”
  • Phase 1 name: Astra North
    “For the Astra North phase alone, more than 1,000 workers are expected to be on site during peak construction activity”
  • Buildings planned: 9 buildings
    “Because the site will support a multi-building campus, construction will progress sequentially across the nine buildings.”
  • Jobs permanent: 250 FTE
    “Once operational, the project is expected to support approximately 250 full-time positions in facility operations, maintenance, security, infrastructure management, and related vendor support.”
  • Site acres: 1440 acres
    “Digital Realty has acquired approximately 1,440 acres of land at Astra Enterprise Park, located near Kansas City to support hyperscale data center development”
  • Code name: Project Jayhawk (per City of De Soto documents)
    “Local press reported on Digital's acquisition of the site and development plans earlier this month. City documents suggest the campus is known as Project Jayhawk”
  • A separate citizen initiative petition is circulating in De Soto to require a public vote on high-impact data center developments; if ruled legislative rather than administrative it could reach a March 2027 ballot. It wo
    “a citizen-led petition is actively circulating among residents of De Soto. The petition aims to block future high-impact data center developments by requiring a public vote on such projects.”
  • Press and petition coverage expects Digital Realty construction to begin in 2027; no construction start had been reported as of October 18, 2026.
    “Digital Realty plans to build a hyperscale data center on 300 acres at Astra Enterprise Park, with construction expected to begin in 2027.”
  • Construction stage: none - land acquired (closed April 2026); no construction started; the campus is in the City of De Soto development review process
    “Digital Realty, headquartered in Dallas, Texas, proposed a multiphase data center campus at Astra Enterprise Park. The project is currently going through the city's development review process”
  • Water allocation: 1000000 gal/day
    “the city of De Soto would allocate one million gallons of water per day to the site”
  • Developer: Digital Realty Trust, Inc. (NYSE: DLR)
    “Digital Realty (NYSE: DLR), the world's largest cloud- and carrier-neutral data center platform, today announced a series of transactions”
  • Location: W 103rd St & Lexington Ave, De Soto, Johnson County, KS
    “Digital has acquired approximately 1,440 acres of land at the Astra Enterprise Park in DeSoto, Kansas, at W 103rd St & Lexington Ave”
  • Phase 1 acres: 280 acres
    “The first phase, known as Astra North, would cover approximately 280 acres.”
  • First announced: June 22, 2026
    “AUSTIN, Texas, June 22, 2026 (GLOBE NEWSWIRE) -- Digital Realty (NYSE: DLR), the world's largest cloud- and carrier-neutral data center platform, today announced a series of transactions”