The site from above
Minooka block
Views of the same ground from above on April 6, 2023 and Oct. 11, 2026. The later view comes from a lower-resolution satellite (10 m pixels), so it is much softer than the first. Drag to compare. What we count on the Oct. 11, 2026 image:
- 3 roofed data halls
- 2 halls under construction
Power and the grid
None energized or contracted yet
- Backup diesel generators (8 x 3.5 MW, press) Planned (press)28 MW; emergency use only; the noise study modeled 3.5 MW Cummins units News report · Oct. 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- March 19, 2025Power not yet lined upAn Equinix real-estate director says electricity and water are still being arranged; the need had risen from 600 to nearly 700 MW. News report · Oct. 2026
- Sept. 23, 2025Village plans an on-site substationThe approved plan includes a ComEd substation on the campus. State agency · Aug. 2025
- March 19, 2026State sets large-load rulesThe Illinois Commerce Commission approves ComEd's tariff: customers back 80% of calculated demand for ten years and post collateral. State agency · March 2026
- As of Oct. 2026No agreement foundNo executed Equinix-ComEd security agreement exists in state or federal records; a blog claim of one is unsupported. see Permits
- Not setUtility capacity: unconfirmedEquinix has said it did not know whether ComEd could connect it to the high-capacity lines on the site's edge. News report · Oct. 2026
- A 345 kV line is mapped 0.5 km from the site anchor, and a 345 kV generating station lies next door (Kendall Dynegy Energy). OpenStreetMap · Oct. 2026
- No filing states an IT-load figure; 420 MW is the campus-stated total whose basis is not given. State agency · Oct. 2026
- Press coverage of FERC's Mar. 10, 2026 acceptance of ComEd security agreements lists Equinix among the customers but does not name Minooka; no filing ties an Equinix agreement to this campus. News report · March 2026
Permits checklist
6 granted · 3 checked, nothing on file
Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.
- ✓Enterprise-zone amendment for the project GrantedUpper Illinois River Valley Development Authority · Aug. 12, 2025: approved 11-0 (Ordinance 25-025) State agency · Aug. 2025
- ✓Annexation into the village GrantedVillage of Minooka Village Board · Sept. 23, 2025: on the Sept. 23 agenda; the village later calls the project approved; vote not retrieved Local government · Sept. 2025
- ✓Rezoning to the data-center district GrantedVillage of Minooka Village Board · Sept. 23, 2025: from county agriculture and R-1 residential; same agenda Local government · Sept. 2025
- ✓Conditional use and preliminary plat (planned development) GrantedVillage of Minooka Village Board · Sept. 23, 2025: same agenda; adoption corroborated by the village's own FAQ Local government · Sept. 2025
- ✓Annexation and development agreement GrantedVillage of Minooka · Sept. 23, 2025: executed text not retrieved Local government · Sept. 2025
- ✓Road construction on Ridge Road and Wildy Road GrantedVillage of Minooka · Oct. 15, 2026: construction notice issued; begins Oct. 15, 2026 Local government · Oct. 2026
- –Checked, nothing on file: Air permit for generators, Electric service agreement, State water approval for the Lake Michigan allocation
What could slow it down
- HighPower not confirmedNo ComEd agreement or study result is public, and Equinix has said it was unsure of high-capacity access; the need has been reported at up to 700 MW. News report · Oct. 2026
- MediumWater supplyThe initial 3M gallons a day is about a third of Minooka's future Lake Michigan allocation, which depends on a pipeline due in 2030. see Permits
- MediumNoise near homesThe noise study meets the nighttime limit only with mitigation and exceeds it along part of the north line. Local government · Sept. 2025
- MediumLocal oppositionFarmers, a county governments group and a petition have raised water, power and land concerns. News report · March 2025
- WatchEarlier doubts from EquinixIn Mar. 2025 an Equinix director said he was not sure the project would ever be built; in Sept. 2026 executives said it is on track. News report · March 2025
Money on record
- Enterprise zone: special incentive status granted for the project (benefits not offered under other state data-center incentives; amounts not stated) State agency · Aug. 2025
What happened, and what is due
- Oct. 1, 2024Site Equinix announces a $15B-plus xScale venture with GIC and CPP Investments SEC filing · Oct. 2024
- Jan. 23, 2025Site Equinix holds its first public proposal meeting in Minooka News report · Jan. 2025
- March 19, 2025Site Equinix says it needs nearly 700 MW and is still lining up electricity and water News report · March 2025
- Aug. 12, 2025Permits Enterprise-zone amendment approved 11-0, citing seven 60 MW buildings and a $5.4B investment State agency · Aug. 2025
- Sept. 9, 2025Permits Planning commission hears the plan with a noise study Local government · Sept. 2025
- Sept. 23, 2025Permits Village board takes up annexation, rezoning, development agreement and conditional use Local government · Sept. 2025
- Dec. 16, 2025Site A petition against the campus is published News report · Dec. 2025
- March 19, 2026Power Illinois approves ComEd's large-load tariff State agency · March 2026
- July 30, 2026Site Village publishes an FAQ on the approved data center Local government · July 2026
- Sept. 19, 2026Site Equinix executives tell investors Minooka is on track News report · Sept. 2026
- Oct. 15, 2026Site Road construction is scheduled to begin on the campus's west and north edges Local government · Oct. 2026
- 2027Site Main vertical construction slated to begin (press) News report · Oct. 2026
Satellite captures by quarter
Since April 2023: 4 satellite captures.
Specs
Owners, partners and builders
- Equinix, Inc.: developer; Equinix LLC owns the land
- AMER 3 Joint Venture: Equinix 25%, GIC 37.5%, CPP Investments 37.5% (Minooka not documented as an asset)
- Village of Minooka Village Board and Planning and Zoning Commission
- Upper Illinois River Valley Development Authority: enterprise zone
- Illinois Commerce Commission: ComEd tariff
- Commonwealth Edison (ComEd): serving utility
- Kendall Dynegy Energy: neighboring generating station
- Shen Milsom & Wilke: noise study for the village
Open questions
- Any ComEd study result or service agreement.
- Whether the second water allocation is approved.
- The tenant and the true IT capacity.
- Start date for vertical construction.
- 2 unconfirmed county land records near the site: the buyer or location could not be tied to this campus.
184 records from 29 documents
Drawn from news reports, state agency records, local government records, public and commercial datasets, securities filings, satellite captures and court filings, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (17)
- Large-load tariff order: final order issued“Rider DE will now include standard facilities installed on premises along with additional construction or investment in [ComEd's] existing distribution system”State agency · March 2026 · grade A
- Cooling design: Air-cooled chillers (336 York YVAM1500 units modeled) with modeled noise mitigation“Two primary scenarios were evaluated; (1) all 336 chillers operating and (2) all chillers operating and three emergency generators operating”Local government · Sept. 2025 · grade A
- Stated campus size: 420 MW“Each of the seven buildings will have a power capacity of 60MW, totaling 420MW once the site is fully built out”State agency · Aug. 2025 · grade A
- Utility: Commonwealth Edison (ComEd)“the site will also house a Com-Ed substation, stormwater detention infrastructure, a regional bike trail extension”State agency · Aug. 2025 · grade A
- Power plan: Grid supply via new on-site ComEd substation; no on-site generation“the site will also house a Com-Ed substation, stormwater detention infrastructure, a regional bike trail extension”State agency · Aug. 2025 · grade A
- Nearest power line of 345 kV or more: 0.54 kmMeasured on OpenStreetMap map data.
- Nearest substation of 345 kV or more: 0.45 kmMeasured on OpenStreetMap map data.
- Nearest gas pipeline: 0.82 kmMeasured on OpenStreetMap map data.
- IT capacity: not stated“DOCUMENTED ABSENCE: no source opened — enterprise-zone application, Equinix SEC filings, ICC dockets, village records — states an IT (critical) load figure for this campus. The only primary-document capacity figure is the 420 MW campus-stated total, whose basis is unspecified.”State agency · Oct. 2026 · grade B
- Utility service: not stated“DOCUMENTED ABSENCE: no utility-contracted capacity or ComEd study result for this campus appears in any primary document opened. Press reported a ~700 MW electricity need (Chicago Tribune, Mar 2025) — a press estimate of need, not a utility figure, so”State agency · Oct. 2026 · grade B
- On-site generation: not stated“Cummins Generator C3500 D6E, 3500 kW: Sound pressure Level of 87 dBA at 23 feet with a Level 1 sound-attenuated walk-in enclosure”Local government · Sept. 2025 · grade B
- On-site generation: 28 MW“Formula: 8 generators x 3.5 MW = 28 MW”News report · Oct. 2026 · grade C
- Utility service: 700 MW“the Minooka facility would need nearly 700 megawatts of electricity, up from the original forecast of 600 megawatts”News report · Oct. 2026 · grade C
- A tariff blog asserts the Minooka project is backed by an executed Transmission Security Agreement“a 700 MW Equinix project in Minooka backed by a Transmission Security Agreement”News report · Oct. 2026 · grade C
- Interconnection status: ComEd TSA approved at FERC on Mar 10, 2026 (Equinix counterparty; EEI ties the TSA to the 700 MW Minooka project) - superseding Mar 2025 reporting that Equinix still awaited ComEd's answer on hook“The agreements are with Equinix, Grundy County Power, Karis Critical, PowerHouse Hillwood Holding and QTS Investment Properties Chicago.”News report · March 2026 · grade C
- large load interconnection request: Transmission Security Agreement approved by FERC“The agreements are with Equinix, Grundy County Power, Karis Critical, PowerHouse Hillwood Holding and QTS Investment Properties Chicago.”News report · March 2026 · grade C
- Data Center Watch briefing: local farmers and the Will County Governmental League raise water-allocation and power concerns over the proposal“a 340-acre data center that would use approximately 700 megawatts of electricity and 3 million gallons of water per day”News report · March 2025 · grade C
Money and contracts (24)
- Transmission Security Agreement (tariff framework): minimum commitment 80 % of calculated demand“the Large Load Project Applicant or Customer would need to provide 80% of the calculated demand for a period of ten (10) years”State agency · March 2026 · grade A
- Transmission Security Agreement (tariff framework): collateral Collateral amount scaled by the applicant's credit rating“with the amount of collateral it is required to post based on its credit rating”State agency · March 2026 · grade A
- Transmission Security Agreement (tariff framework): condition precedent TSA to be filed with FERC shortly after ComEd completes an initial study of the proposed project“to be filed with the Federal Energy Regulatory Commission (FERC) shortly after ComEd completes an initial study of a proposed project”State agency · March 2026 · grade A
- Rider DE (distribution extension terms): deposit / collateral 2000000 USD threshold“The Commission finds that it is just and reasonable for ComEd to accept an LOC when the costs of an extension exceed $2,000,000”State agency · March 2026 · grade A
- AMER 3 Joint Venture: condition JV agreement subject to closing conditions at signing; venture formed Oct 30, 2024“On October 30, 2024, we formed a joint venture to develop and operate xScale data center campuses in the Americas region”SEC filing · Feb. 2026 · grade A
- AMER 3 Joint Venture: scope limitation No campus sites are named in the JV documents and Minooka is not documented as a JV asset; the only JV asset transaction disclosed is Hampton (sold to the JV Jan 13, 2026 for an est“On January 13, 2026, we sold the assets and liabilities of the Hampton data center campus (Hampton) located in the greater Atlanta metro area to the AMER 3 Joint Venture”SEC filing · Feb. 2026 · grade A
- Land purchase: scope 16929 N Ridge Rd farmstead parcel acquired in 2025 for incorporation into the data center project“Equinix LLC (2025) Acquisition for incorporation into data center project”State agency · Feb. 2026 · grade A
- Annexation and Development Agreement: authorization“An Ordinance Authorizing the Execution of Annexation and Development Agreement (Equinix)”Local government · Sept. 2025 · grade A
- Annexation ordinance: scope Annexes the remaining roughly two-thirds of the 373-acre site from unincorporated Kendall County into the Village“An Ordinance Annexing Certain Territory to the Village of Minooka, Will County, Grundy County, and Kendall County, State of Illinois (Equinix)”Local government · Sept. 2025 · grade A
- Rezoning ordinance: scope Kendall County Agriculture and Minooka R-1 to Minooka DC Data Center District“An Ordinance Rezoning Certain Property within the Village of Minooka (Kendall County Agriculture and Minooka R-1 to Minooka DC Data Center District)”Local government · Sept. 2025 · grade A
- Conditional use / PUD approval: scope Conditional permitted use permit for a planned unit development and preliminary PUD plat“An Ordinance Granting a Conditional Permitted Use Permit for a Planned Unit Development and Approving a Preliminary PUD Plat (Equinix)”Local government · Sept. 2025 · grade A
- Buildings: 7“Equinix will build seven data center facilities, totaling approximately 2 million square feet of floor area”State agency · Aug. 2025 · grade A
- Floor area: 2000000 sq ft“Equinix will build seven data center facilities, totaling approximately 2 million square feet of floor area”State agency · Aug. 2025 · grade A
- Investment: 5396173438 USD“The investment in the project is $5,396,173,438, including land acquisition, new construction, and new equipment”State agency · Aug. 2025 · grade A
- Enterprise Zone amendment: scope 373-acre campus; $5,396,173,438 investment; 150 jobs; 7 buildings / ~2M sq ft“The investment in the project is $5,396,173,438, including land acquisition, new construction, and new equipment”State agency · Aug. 2025 · grade A
- Enterprise Zone amendment: benefit Enterprise-zone benefits not offered under other state incentives for data center development“benefits afforded by the enterprise zone that are not offered under other state incentives for data center development”State agency · Aug. 2025 · grade A
- Enterprise Zone amendment: schedule Public improvements from Sep 2025; data-center facilities from late 2025 over an estimated seven-year build“Equinix will begin constructing certain public improvements in September 2025, including access roads and stormwater detention infrastructure”State agency · Aug. 2025 · grade A
- AMER 3 Joint Venture: scope Capital pool over $15B; GIC 37.5%, CPP Investments 37.5%, Equinix 25%“CPP Investments and GIC will each control a 37.5% equity interest in the joint venture, and Equinix will own a 25% equity interest”SEC filing · Oct. 2024 · grade A
- Annexation and Development Agreement: termination FINDING: executed agreement text not retrieved, the village document library is JS-gated; termination, condition and scope clauses are unverified. Flagged for coordinato“Public Hearing to consider the terms of a proposed Annexation and Development Agreement for the Equinix Project”Local government · Sept. 2025 · grade B
- Tenants: None named (Equinix colocation / xScale model)“the joint venture is intended to accelerate the Equinix xScale data center portfolio, which enables hyperscale companies to add core deployments”SEC filing · Oct. 2024 · grade B
- Special Service Area: scope Special service area created for the Equinix Data Center campus north of Minooka; ordinance number and date not retrieved“The Minooka Village Board recently approved two items on the agenda that would create a special service area for the Equinix Data Center campus north of Minooka”News report · Oct. 2026 · grade C
- Transmission Security Agreement (campus status): scope No executed Equinix-ComEd TSA found in the ICC or FERC records searched; a blog claim that this project is backed by a TSA is unsupported“a 700 MW Equinix project in Minooka backed by a Transmission Security Agreement”News report · Oct. 2026 · grade C
- Tenant status: No tenant announced“Shaw said the Hampton and Minooka projects are currently on track, without providing further expansion details”News report · Sept. 2026 · grade C
- Minooka and five other towns are building a $1.54B pipeline to draw Lake Michigan water through Chicago, due to open 2030; the campus's initial 3M gal/day equals about a third of Minooka's 9M gal/day allocation, and the“That's a third of all the drinkable water Minooka will be allowed to draw from a $1.54 billion pipeline”News report · March 2025 · grade C
Permits and government (16)
- Public improvement construction notice: construction start notice issued“UPDATE: Due to additional contractor coordination, construction is now scheduled to begin Thursday, October 15, 2026”Local government · Oct. 2026 · grade A
- Annexation and development agreement: on Sep 23, 2025 board agenda for authorization (items 11A-11B); adoption corroborated by the Village FAQ description of the approved Equinix data center“An Ordinance Authorizing the Execution of Annexation and Development Agreement (Equinix)”Local government · Sept. 2025 · grade A
- Annexation: ordinance on Sep 23, 2025 board agenda (item 11C)“An Ordinance Annexing Certain Territory to the Village of Minooka, Will County, Grundy County, and Kendall County, State of Illinois (Equinix)”Local government · Sept. 2025 · grade A
- Rezoning: ordinance on Sep 23, 2025 board agenda (item 11D)“An Ordinance Rezoning Certain Property within the Village of Minooka (Kendall County Agriculture and Minooka R-1 to Minooka DC Data Center District)”Local government · Sept. 2025 · grade A
- Conditional use / PUD: ordinance on Sep 23, 2025 board agenda (item 11E)“An Ordinance Granting a Conditional Permitted Use Permit for a Planned Unit Development and Approving a Preliminary PUD Plat (Equinix)”Local government · Sept. 2025 · grade A
- Village of Minooka Village Board: Equinix package, new business items 11A-11G (agreement hearing, annexation agreement, annexation, rezoning, conditional PUD, district guideline corrections)“An Ordinance Granting a Conditional Permitted Use Permit for a Planned Unit Development and Approving a Preliminary PUD Plat (Equinix)”Local government · Sept. 2025 · grade A
- Village of Minooka Planning & Zoning Commission: Equinix PUD hearing packet including the SM&W acoustic evaluation“The Equinix site is bounded by the following properties: North: Wildy Road; East: Kendall Dynegy Energy; South: Holt Road; West: Ridge Road”Local government · Sept. 2025 · grade A
- Acoustic study filing: study filed in the P&Z packet for the Sep 9, 2025 hearing“Two primary scenarios were evaluated; (1) all 336 chillers operating and (2) all chillers operating and three emergency generators operating”Local government · Sept. 2025 · grade A
- Enterprise zone amendment: approved (roll call AYE 11 / NAY 0)“Ordinance No. 25-025 – An Ordinance to amend the UIRVDA Enterprise Zone on behalf of the Equinix data center project (Kendall County)”State agency · Aug. 2025 · grade A
- Upper Illinois River Valley Development Authority Board: Ordinance No. 25-025, enterprise zone amendment for the Equinix project“Ordinance No. 25-025 – An Ordinance to amend the UIRVDA Enterprise Zone on behalf of the Equinix data center project (Kendall County)”State agency · Aug. 2025 · grade A
- Data center district creation: adopted“(Ord. 2003-34, 8-26-2003; amd. Ord. 2024-50, 11-26-2024)”Local government · Nov. 2024 · grade B
- Special service area: approved per press report; ordinance number and date not retrieved“The Minooka Village Board recently approved two items on the agenda that would create a special service area for the Equinix Data Center campus north of Minooka”News report · Oct. 2026 · grade C
- ILEPI/PMCR Illinois data-center report (Sep 2026) tabulates Equinix Minooka at 700 MW, 340 acres, $2.0B cost and 150 jobs, the MW, acreage and cost figures conflict with the enterprise-zone application; see conflicts.cs“Equinix Minooka data center — Yes — 700 — 340 — $2,000,000,000 — 150”News report · Sept. 2026 · grade C
- Site location: Approx 300-340 acres of farmland along Ridge Road between Holt Road and Wildy Roads, Minooka, IL (village planning record; Equinix LLC acquired the parcels in 2025, including the Harvey Farmstead, Kendall“The acquired properties are located along Ridge Road between Holt Road and Wildy Roads in Minooka.”News report · Sept. 2025 · grade C
- Village of Minooka Board (committee meeting): Water and power review, Equinix presentations by Mickler and Baumann“Equinix cut its projected water use so dramatically by deciding to cool half of the servers in Minooka with air only instead of a combination of air and water”News report · March 2025 · grade C
- Village of Minooka Board: First Equinix proposal meeting for the Minooka campus“On January 23, 2025, Equinix held its very first proposal meeting to discuss a potential state-of-the-art data center campus in Minooka”News report · Jan. 2025 · grade C
Legal (1)
- Federal cases: not stated“Top results are Village of Minooka and Minooka school-district cases (N.D; Ill.)”Court filing · Oct. 2026 · grade B
Site and other (23)
- Stage: Entitled and annexed (Sep 2025); early site and road works under way Oct 2026; vertical construction not yet evidenced“construction is now scheduled to begin Thursday, October 15, 2026. During construction hours, Ridge Road south of Wildy Road will be reduced to one lane”Local government · Oct. 2026 · grade A
- Construction stage: Early site works (Ridge Rd / Wildy Rd road construction from Oct 15, 2026); data-center building construction not evidenced“construction is now scheduled to begin Thursday, October 15, 2026. During construction hours, Ridge Road south of Wildy Road will be reduced to one lane”Local government · Oct. 2026 · grade A
- Village notice: construction on Ridge Road and Wildy Road, the campus's west and north frontage roads, begins Oct 15, 2026, with Ridge Road south of Wildy Road reduced to one lane“construction is now scheduled to begin Thursday, October 15, 2026”Local government · Oct. 2026 · grade A
- Ch8 entity: Equinix Hyperscale 3 (CH8) LLC“Equinix Hyperscale 3 (CH8) LLC — listed in the subsidiary table with jurisdiction Delaware”SEC filing · Feb. 2026 · grade A
- Owner entity: Equinix LLC“Owner / Occupant: Equinix LLC”State agency · Feb. 2026 · grade A
- Address: 16929 North Ridge Road, Minooka, IL 60447 (Harvey Farmstead parcel inside the campus)“Location: 16929 North Ridge Road, Minooka, Seward Township, Kendall County, Illinois, 60447”State agency · Feb. 2026 · grade A
- City: Minooka“An Ordinance Annexing Certain Territory to the Village of Minooka, Will County, Grundy County, and Kendall County, State of Illinois (Equinix)”Local government · Sept. 2025 · grade A
- Site bounds: Bounded by Wildy Road (north), Ridge Road (west), Holt Road (south), Kendall Dynegy Energy (east)“The Equinix site is bounded by the following properties: North: Wildy Road; East: Kendall Dynegy Energy; South: Holt Road; West: Ridge Road”Local government · Sept. 2025 · grade A
- Developer: Equinix, Inc.“An Ordinance to amend the UIRVDA Enterprise Zone on behalf of the Equinix data center project (Kendall County)”State agency · Aug. 2025 · grade A
- County: Kendall County“They are looking to develop multiple data centers projects near Minooka in unincorporated Kendall County, near Ridge Road and Wildy Road”State agency · Aug. 2025 · grade A
- Site acres: 373 acres“The data center campus will occupy +/- 373 acres of property, of which, approximately one-third is currently in the Village of Minooka”State agency · Aug. 2025 · grade A
- Jobs: 150 jobs“The project is expected to create 150 jobs according to their application”State agency · Aug. 2025 · grade A
- Current target date: 2032“Equinix will begin constructing the data center facilities in late 2025, with the seven facilities being built over an estimated seven-year period”State agency · Aug. 2025 · grade A
- Enterprise zone: UIRVDA Enterprise Zone (amended for this project by Ordinance 25-025)“They are seeking to take potential advantage of benefits afforded by the enterprise zone that are not offered under other state incentives for data center development”State agency · Aug. 2025 · grade A
- Name: Equinix Minooka Campus“In an effort to keep residents informed regarding the approved Equinix data center the Village of Minooka has compiled the following document and map”Local government · July 2026 · grade B
- Aliases: CH8“Equinix: Minooka CH8”News report · Oct. 2026 · grade C
- Equinix job posting for a Senior Manager, Construction Project Management based in Minooka, Illinois (via a job aggregator), consistent with a move toward construction staffing“Senior Manager Construction Project Management Illinois Minooka”News report · Oct. 2026 · grade C
- Equinix executives told investors the Hampton and Minooka projects are currently on track, without further expansion detail“Shaw said the Hampton and Minooka projects are currently on track, without providing further expansion details”News report · Sept. 2026 · grade C
- Change.org petition NO DATA CENTERS in Minooka, IL published, opposing the campus on water, energy and land-use grounds“A proposal to construct a large-scale data center in Minooka, Il. has recently surfaced”News report · Dec. 2025 · grade C
- Original target date: not stated“he is still scrambling to line up electricity and water to break ground next year and complete the project by 2034”News report · March 2025 · grade C
- Water demand: 3000000 gal/day“It would need 3 million gallons of water a day. That's a third of all the drinkable water Minooka will be allowed to draw”News report · March 2025 · grade C
- Pre-entitlement, Equinix's real-estate director said he was not sure the project would ever get built; electricity and water were not yet lined up and ComEd said the project was still in study and design“Baumann said he's not sure it will ever get built. He's still scrambling to line up electricity and water”News report · March 2025 · grade C
- First announced: Jan. 23, 2025“On January 23, 2025, Equinix held its very first proposal meeting to discuss a potential state-of-the-art data center campus in Minooka”News report · Jan. 2025 · grade C