Power and the grid
- Evergy grid via an on-site substation Planned44.2-acre substation parcel; no MW or service agreement published News report · Oct. 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Nov. 14, 2025Large-load tariff approvedMissouri regulators approve Evergy's tariff for customers of 75 MW or more; Google signed the settlement. It is the framework, not a Kestrel contract. Utility regulator · Nov. 2025
- 2026Substation parcel set asideA 44.2-acre section of the site is to go to Evergy for an on-site substation (press). News report · Oct. 2026
- Not setService agreement: none foundNo Kestrel-specific state utility docket or service agreement was found as of Oct. 2026. Utility regulator · Oct. 2026
- Under the tariff, contracts run at least 12 years, with collateral of two years of minimum bills and a minimum bill on at least 80% of contract capacity. Utility regulator · Nov. 2025
- A 700 MW figure in Kansas City coverage belongs to Project Micah, a separate Google campus, not to Kestrel. News report · Jan. 2026
- Port KC says the campus will use at least 50% carbon-free energy. Local government · Aug. 2025
Permits checklist
2 pending · 1 granted · 1 checked, nothing on file
Approvals on record; note that a staff or commission recommendation is not a final decision.
- ◷Final plat, 430 acres (KCI 29 Logistics Park Third Plat) PendingKansas City Plan Commission · Aug. 20, 2025: staff recommended approval with conditions; final action not in the record Local government · Aug. 2025
- ◷KCI-29 park plan amendment (park-wide) PendingKansas City Plan Commission and City Council · Jan. 21, 2026: commission recommended approval with conditions; not a Kestrel site plan Local government · Jan. 2026
- ✓Bonds and 35-year tax exemption GrantedPort KC Board of Commissioners · Aug. 25, 2025: real and personal property tax, plus sales tax on construction materials News report · Aug. 2025
- –Checked, nothing on file: Air or construction permits
What could slow it down
- MediumTenant unconfirmedGoogle has not commented; the link rests on Shenandoah Computing, the filer behind two confirmed Google projects in the area (press). News report · Jan. 2026
- MediumNo construction startPort KC said the first phase would start in 2026, but no start had been confirmed by Oct. 2026. News report · Aug. 2025
- WatchTax-break criticismThe Platte County presiding commissioner opposes the 35-year exemption (press). News report · Nov. 2025
Money on record
What happened, and what is due
- July 8, 2024Paper trail Shenandoah Computing LLC registered in Missouri
- July 11, 2025Permits Final plat application filed for 430 acres in the KCI-29 park Local government · Aug. 2025
- Aug. 20, 2025Permits City staff recommend approving the plat with conditions Local government · Aug. 2025
- Aug. 25, 2025Money Port KC board approves 35-year bonds for the project News report · Aug. 2025
- Aug. 26, 2025Site Port KC announces Project Kestrel: six hyperscale data centers and a $100B headline Local government · Aug. 2025
- Nov. 14, 2025Power State regulators approve Evergy's large-load tariff; Google is a signatory Utility regulator · Nov. 2025
- Nov. 2025Site Platte County's presiding commissioner says he can't support Kestrel's tax breaks News report · Nov. 2025
- 2026Site Google-linked Shenandoah Computing buys the 430 acres from Hunt Midwest (press) News report · 2026
- Jan. 21, 2026Permits City Plan Commission recommends a park-wide plan amendment for KCI-29 Local government · Jan. 2026
Building activity by quarter
Since July 2026: 19 FAA filings (July 2026): tallest crane 200 ft (July 2026).
Specs
Owners, partners and builders
- Shenandoah Computing LLC: buyer of the site, linked to Google (press)
- Hunt Midwest: seller and KCI-29 park owner
- Port KC (Port Authority of Kansas City): bonds and tax exemption
- Kansas City Plan Commission and City Council: plat and park plan
- Missouri Public Service Commission: Evergy large-load tariff
- Evergy: serving utility, on-site substation
- Scott Fricker, Platte County Presiding Commissioner: opposes the tax breaks
Open questions
- Confirmed tenant and campus MW.
- Evergy service agreement.
- Construction start date.
72 records from 10 documents
Drawn from news reports, local government records, state agency records, business registries, public and commercial datasets, company statements and utility regulator dockets, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (4)
- Evergy Large Load Power Service tariff applies at 75 MW or above demand, approved by Missouri PSC in November 2025; Evergy states no customer is currently served on LLPS and no Kestrel-specific service agreement is state“This rate, named the Large Load Power Service Tariff (LLPS), applies to any Evergy customer who is expected to have a 75 megawatt or above demand.”Company · Feb. 2026 · grade B
- Utility: Evergy“A 44.2-acre section will be delivered to Evergy for the development of an on-site substation.”News report · Oct. 2026 · grade C
- Substation acres: 44.2 acres“A 44.2-acre section will be delivered to Evergy for the development of an on-site substation.”News report · Oct. 2026 · grade C
- No MW figure for Kestrel exists in any retrieved source. The 700 MW figure in Kansas City coverage belongs to Project Micah ('The site will total 700MW, according to Port KC'), a separate Shenandoah/Google campus in Clay“The site will total 700MW, according to Port KC.”News report · Jan. 2026 · grade C
Money and contracts (12)
- Tenant operator: unnamed by Port KC; described only as one of the world's leading tech companies“the campus represents one of the largest technology investments in the region's history by one of the world's leading tech companies.”Local government · Aug. 2025 · grade B
- Building sq ft: 1800000 sq ft“the project will consist of six hyperscale data centers totaling up to 1.8 million square feet upon full build-out.”Local government · Aug. 2025 · grade B
- community / workforce payment: workforce development charge per square foot built 0.25 USD per sq ft“With each square foot built, a $0.25 per square foot charge will be collected and distributed to the area's workforce development.”Local government · Aug. 2025 · grade B
- tax abatement: 35-year exemption of real and personal property taxes and sales tax on construction material“The project has already been awarded a 35-year exemption of real and personal property taxes, as well as sales taxes for construction material.”News report · Oct. 2026 · grade C
- Google has NOT publicly confirmed Project Kestrel as its own project ('Google has yet to publicly comment on the project'). The link rests on Shenandoah Computing LLC, the same filer behind the confirmed Google projects“Shenandoah Computing is the company behind filings for Project Shale and Project Micah, both of which are in the Kansas City area and confirmed to be Google developments.”News report · Jan. 2026 · grade C
- Shenandoah Computing acquired 430 acres near KCI from Hunt Midwest (Kansas City Business Journal via DCD); current plans described as five 500,000 sq ft buildings in phases; a 44.2-acre section goes to Evergy for an on-s“A Google-affiliated company has purchased 430 acres of land near the Kansas City International Airport in Kansas City, Missouri, for a data center campus.”News report · 2026 · grade C
- bond financing and tax abatement: 35-year bonds / tax exemption 100000000000 USD authorized ceiling“Bonds for the project, which were approved during Port KC's Board meeting on Monday, will be in effect for the next 35 years.”News report · Aug. 2025 · grade C
- Industrial revenue bond: contract value 100000000000 USD“Port KC announced that a $100 billion data center campus is planned to be built in the Northland.”News report · Aug. 2025 · grade C
- Industrial revenue bond: term 35 years“Bonds for the project, which were approved during Port KC's Board meeting on Monday, will be in effect for the next 35 years.”News report · Aug. 2025 · grade C
- Tax abatement agreement: tax compliance payments (projected, all phases) 110000000 USD“The project is expected to generate over $110 million in new tax revenue across all phases over the bond term.”News report · Aug. 2025 · grade C
- Tax abatement agreement: first payment 2620000 USD“The first payment of $2.62 million will be paid during the first five years to the Northland school districts' new Northland Career Center.”News report · Aug. 2025 · grade C
- Tax abatement agreement: job commitments 50 jobs per phase“The data center campus is anticipated to create approximately 50 high-paying jobs per phase, with average annual salaries exceeding $100,000.”News report · Aug. 2025 · grade C
Permits and government (26)
- Expands KCI-29 MPD boundary by about 167-168 acres to about 2,500 acres for 20 m: Major amendment to KCI-29 MPD - City Plan Commission recommended approval with conditions Jan 21, 2026; ordinance 260213 followed“The City Plan Commission heard this application on January 21, 2026 and recommended approval with conditions.”Local government · Jan. 2026 · grade A
- Kansas City Plan Commission:“The City Plan Commission heard this application on January 21, 2026 and recommended approval with conditions. There was no public testimony at the City Plan Commission.”Local government · Jan. 2026 · grade A
- MoPSC approved the LLPS settlement for Evergy Metro and Evergy Missouri West: cu: Evergy Large Load Power Service (LLPS) Tariff APPROVED - framework governing this campus“The Commission accepted an agreement signed by Evergy Metro, Inc., Evergy Missouri West, Inc. the Union Electric Company d/b/a Ameren Missouri, Google LLC”Utility regulator · Nov. 2025 · grade A
- 430 acres at SW corner North Winan Road and Highway 92, 2 lots for industrial de: Final Plat (KCI 29 Logistics Park Third Plat) - staff recommendation approval subject to conditions“Professional Staff Recommendation Docket #C10 Approval Subject to Conditions”Local government · Aug. 2025 · grade A
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-ACE-3316-OE: Project Kestrel - Building 01 NE Crane, Crane, 200 ft AGL, 1184 ft AMSL, 39.35278,-94.70111, Determined - No Hazard, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3315-OE: Project Kestrel - Building 01 SE Crane, Crane, 200 ft AGL, 1185 ft AMSL, 39.35056,-94.70111, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3311-OE: Project Kestrel - Building 01 NW Crane, Crane, 200 ft AGL, 1182 ft AMSL, 39.35278,-94.70750, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3320-OE: Project Kestrel - Building 02 NE Crane, Crane, 200 ft AGL, 1160 ft AMSL, 39.35000,-94.70417, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3313-OE: Project Kestrel - Building 01 SW Crane, Crane, 200 ft AGL, 1183 ft AMSL, 39.35056,-94.70750, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3317-OE: Project Kestrel - Building 02 NW Crane, Crane, 200 ft AGL, 1159 ft AMSL, 39.35000,-94.70750, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3319-OE: Project Kestrel - Building 02 SE Crane, Crane, 200 ft AGL, 1160 ft AMSL, 39.34639,-94.70417, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3324-OE: Project Kestrel - Building 03 NE Crane, Crane, 200 ft AGL, 1160 ft AMSL, 39.34639,-94.70417, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3318-OE: Project Kestrel - Building 02 SW Crane, Crane, 200 ft AGL, 1161 ft AMSL, 39.34639,-94.70750, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3321-OE: Project Kestrel - Building 03 NW Crane, Crane, 200 ft AGL, 1161 ft AMSL, 39.34639,-94.70750, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3323-OE: Project Kestrel - Building 03 SE Crane, Crane, 200 ft AGL, 1160 ft AMSL, 39.34389,-94.70417, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3332-OE: Project Kestrel - Building 05 NE Crane, Crane, 200 ft AGL, 1170 ft AMSL, 39.34278,-94.70111, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3322-OE: Project Kestrel - Building 03 SW Crane, Crane, 200 ft AGL, 1161 ft AMSL, 39.34389,-94.70750, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3328-OE: Project Kestrel - Building 04 NE Crane, Crane, 200 ft AGL, 1168 ft AMSL, 39.34278,-94.70389, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3329-OE: Project Kestrel - Building 05 NW Crane, Crane, 200 ft AGL, 1168 ft AMSL, 39.34278,-94.70389, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3325-OE: Project Kestrel - Building 04 NW Crane, Crane, 200 ft AGL, 1167 ft AMSL, 39.34278,-94.70833, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3331-OE: Project Kestrel - Building 05 SE Crane, Crane, 200 ft AGL, 1170 ft AMSL, 39.34056,-94.70111, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3327-OE: Project Kestrel - Building 04 SE Crane, Crane, 200 ft AGL, 1171 ft AMSL, 39.34056,-94.70389, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA obstruction evaluation (7460-1): Reevaluating“ASN 2026-ACE-3330-OE: Project Kestrel - Building 05 SW Crane, Crane, 200 ft AGL, 1171 ft AMSL, 39.34056,-94.70389, Reevaluating, submitted 2026-07-14”FAA · July 2026 · grade B
- FAA OE/AAA filings evidence vertical construction at Project Kestrel (KCI-29 Hyperscale Campus, Kansas City Northland): nineteen 200-ft cranes filed under the campus's own project name for Buildings 01 through 05, all su“ASN 2026-ACE-3316-OE: Project Kestrel - Building 01 NE Crane, Crane, 200 ft AGL, 1184 ft AMSL, 39.35278,-94.70111, Determined - No Hazard, submitted 2026-07-14”FAA · July 2026 · grade B
- IRB/abatement ordinance, Port KC Board of Commissioners approved the Project Ke: approved“Bonds for the project, which were approved during Port KC's Board meeting on Monday, will be in effect for the next 35 years.”News report · Aug. 2025 · grade C
- Port KC Board of Commissioners:“Bonds for the project, which were approved during Port KC's Board meeting on Monday, will be in effect for the next 35 years.”News report · Aug. 2025 · grade C
Legal (1)
- Platte County Presiding Commissioner Scott Fricker spoke out in Nov 2025 against the 35-year tax exemption, saying he 'can't support Project Kestrel'; no lawsuit, moratorium or denial found for this campus“Platte County Presiding Commissioner Scott Fricker has said he "can't support Project Kestrel" because it will give "massive property and sales tax subsidies"”News report · Nov. 2025 · grade C
Site and other (10)
- County code: 29165“"County":{"FIPS":"29165","name":"Platte County"}”Dataset · Oct. 2026 · grade A
- Site acres: 430 acres“The applicant seeks to gain approval of a Final Plat in District MPD on about 430 acres generally located at the southwest corner of North Winan Road and Highway 92”Local government · Aug. 2025 · grade A
- Project identity: Project Kestrel / KCI-29 Hyperscale Campus, Kansas City Northland, Platte County, MO“Planned on 379 acres of land within an existing industrial mega site, KCI-29, the project will consist of six hyperscale data centers”Local government · Aug. 2025 · grade B
- Project area acres: 379 acres“Planned on 379 acres of land within an existing industrial mega site, KCI-29”Local government · Aug. 2025 · grade B
- Port KC states Kestrel will use a minimum 50% carbon-free energy and replace above the amount of water it consumes; DCD restates at least 50% carbon-neutral sources“is committed to utilizing a minimum of 50% of all energy from carbon-free resources.”Local government · Aug. 2025 · grade B
- Project status: announced; site acquired by Shenandoah Computing LLC from Hunt Midwest; no construction timeline provided in latest report“No timeline for construction has been provided as yet, but local officials have suggested it could start sometime this year.”News report · Oct. 2026 · grade C
- Developer: Shenandoah Computing LLC“the site has been officially acquired by Shenandoah Computing LLC, a Delaware company known to be associated with Google.”News report · Oct. 2026 · grade C
- Campus expected to bring 50 full-time jobs per phase of construction; at least 50 percent of energy from carbon-neutral sources (DCD, from project reporting)“The campus is expected to bring 50 full-time jobs per phase of construction, and will use at least 50 percent of its energy from carbon-neutral sources.”News report · 2026 · grade C
- Platte County Presiding Commissioner Scott Fricker spoke out in November 2025 against the Kestrel tax breaks, saying they benefit a large rich corporation at residents' expense“Platte County Presiding Commissioner Scott Fricker has said he “can’t support Project Kestrel””News report · Nov. 2025 · grade C
- Project status: land acquired by Shenandoah Computing LLC; Port KC announced Aug 2025 with 35-year tax abatement; first-phase construction was set to begin in 2026, no confirmed construction start found“The operator behind Project Kestrel hasn't been named, but has been described by Port KC as a leading global technology company.”News report · Aug. 2025 · grade C