Data center profile · Southern Nodaway County, Missouri, near U.S. 71 and 340th St. (Jet Road), south of Maryville

White Cloud Acres, Nodaway County

Scale Microgrids' proposed 600 MW data center with a separate 600 MW gas plant near Barnard, Missouri, paused by a county construction moratorium and still without a customer

Proposed, county moratorium. Nodaway County commissioners voted unanimously on July 21, 2026 for a six-month moratorium to Jan. 21, 2027, extendable. Land options and a pending state air permit for the gas plant, but no customer, power contract, water commitment or construction.
600 MW
data center size the developer markets
developer says; whether this is IT or total load is not stated
600 MW
gas plant in the air permit application (separate project)
12 turbines, to sell up to 600 MW to the grid; not extra data-center load
$6B+
combined investment the developer cites
data center and gas plant; an early press report said $4B for the data center
Jan. 21, 2027
county moratorium ends unless extended
commissioners may add six months
OperatorScale Microgrids (developer); a hyperscaler is meant to own and run the data center
CustomerNone named; developer plans to hand the site to an unnamed hyperscaler
Planned IT capacity480 MW at full build-out (our estimate from the company's 0.6 GW campus power figure)
Next deadlineJan. 21, 2027: County data-center moratorium ends, unless the commissioners extend it six more months
Permits

Permits checklist

2 pending · 1 draft · 3 checked, nothing on file

Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.

Risks

Why it stopped, what could revive it

Power

Power and the grid

Sources on record, size not disclosed
Related generation and energy contracts (context, not added to campus supply)

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. June 18, 2026
    Gas plant air permit filed
    White Cloud Generating applies to the Missouri DNR for a 12-turbine plant at Barnard. Local government · Oct. 2026
  2. July 20, 2026
    Application deemed complete
    The state calls the application administratively complete; no draft permit has been issued. Local government · Oct. 2026
  3. Not set
    Utility commission: no filing
    No Missouri Public Service Commission case exists for the project, although one does for a separate Evergy plant nearby. see Permits
Money

Money on record

$6B+ combined data center and gas plant investment (developer says) (an earlier press report put the data center at $4B). Company · Oct. 2026

Not on record: price Scale paid for Reload, Feb. 2026: undisclosed, EQT is Scale's equity partner with a material commitment Company · Oct. 2026; tax abatements requested or granted: county statement, June 9, 2026 Local government · Oct. 2026

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Dec. 16, 2025
    Site ReLoad introduces a data center campus to the county commissioners Local government · Oct. 2026
  2. Feb. 23, 2026
    Money Scale Microgrids acquires ReLoad and takes over the project Company · Oct. 2026
  3. April 2, 2026
    Site Scale is introduced to the county commission as the new developer Local government · Oct. 2026
  4. June 9, 2026
    Money County states no tax abatements have been requested or granted Local government · Oct. 2026
  5. June 18, 2026
    Permits White Cloud Generating files its state air permit application for the gas plant Local government · Oct. 2026
  6. June 23, 2026
    Site Water district releases a draft study on supplying the data center Local government · Oct. 2026
  7. July 20, 2026
    Permits State deems the air permit application complete Local government · Oct. 2026
  8. July 21, 2026
    Permits County commissioners enact a six-month data-center moratorium, 3-0 Local government · Oct. 2026
  9. Oct. 2026
    Site County posts a public briefing on the project; water source and utility remain undecided Dataset · Oct. 2026
  10. Jan. 21, 2027
    Permits Moratorium period ends unless extended by six months Local government · Oct. 2026
The buildings

Specs

12 turbines
ProEnergy PE6000 simple-cycle gas units with emission controls
82,000 gal/day
minimum average water need in the draft supply study
50 dBA
sound limit the developer says it will model; seven-day background readings taken July 2026
Who is involved

Owners, partners and builders

Owners
  • Scale Microgrids: current developer; will keep the gas plant
  • ReLoad, Inc.: original developer, acquired Feb. 2026
  • EQT: Scale's equity partner
Decision-makers
  • Nodaway County Commission: moratorium and development agreement
  • Missouri Department of Natural Resources: air permit
  • Public Water Supply District No. 1: water service
  • Missouri Public Service Commission: utility certificates
Opponents
  • Nodaway Says No
Still unknown

Open questions

Where this comes from

110 records from 19 documents

Drawn from local government records, news reports, state agency records, company statements, public and commercial datasets and securities filings, each kept with its date and source. The bar shows documents by type.

Local government 6News report 4State agency 4Company 3Dataset 2SEC filing 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (19)
  • Developer: Scale Microgrids
    “introduced the Commission to Dan Scheffler, VP Development, Data Centers with Scale Microgrids. Scale Microgrids recently acquired the project from RELOAD, Inc.”
  • Filing record: No SEC filing states any load figure for this campus; Scale Microgrids and White Cloud LLC have no campus-named EDGAR footprint and no Form D
    “No SEC filing states a campus MW figure for this campus”
  • Sponsor equity: EQT (equity partner of Scale Microgrids)
    “material capital commitment from EQT”
  • Site location: Southern Nodaway County; generation facility addressed 340th Street and Jet Road, Barnard, MO 64423
    “The proposed energy facility's Missouri DNR application identifies the location as 340th Street and Jet Road, Barnard, Missouri 64423.”
  • Stated campus size: 600 MW
    “The project includes a 600-megawatt data center alongside a natural gas-powered energy facility, representing a combined investment of more than $6 billion.”
  • On-site generation: 600 MW
    “Application states the facility would sell up to 600 MW to the local bulk electric system.”
  • IT capacity: not stated
    “The project includes a 600-megawatt data center alongside a natural gas-powered energy facility”
  • Utility service: not stated
    “Public reporting indicates Evergy would serve the proposed data center”
  • Power plan: onsite gas generation (behind-the-meter) plus grid sales; no utility ESA
    “Application states the facility would sell up to 600 MW to the local bulk electric system.”
  • Scale Microgrids acquired Reload (ReLoad, Inc.), taking over the White Cloud Acres project; transaction terms undisclosed; EQT is Scale's equity partner.
    “the acquisition of Reload, a platform that sites, designs, and permits gigawatt-scale data center campuses paired with rapidly deployable on-site power infrastructure”
  • Source record
    “On July 31, 2025, the Missouri Public Service Commission issued its Report and Order in Case No. EA-2025-0075”
  • Build-and-assign structure stated by the developer: Scale performs all horizontal development, then assigns the land and materials to an unnamed hyperscaler who will own and operate the data center; Scale separately reta
    “Scale is performing all horizontal development of the site. Upon completion, Scale will assign the land and materials to a hyperscaler”
  • Stated campus size: 600 MW
    “According to the project's own marketing site, it would consist of a 600 MW data center plus a co-located natural-gas power plant - combined investment "of more than $6 billion"”
  • Interconnection status: Behind-the-meter self-supply by design: Scale Microgrids (which acquired developer ReLoad in February 2026) plans co-located natural-gas generation for the campus; NO interconnection agreement wit
    “Scale Microgrids, which specializes in behind-the-meter natural-gas power generation — a structure that lets the project bypass the utility-regulatory process that would otherwise apply if power came from Evergy or Ameren.”
  • Stated campus size: 600 MW
    “According to the project's own marketing site, it would consist of a 600 MW data center plus a co-located natural-gas power plant”
  • Press reporting indicates Evergy would serve the proposed data center (relayed in the county presentation). UNVERIFIED: no Evergy agreement, PSC filing or tariff application for this campus exists in the record opened; t
    “Public reporting indicates Evergy would serve the proposed data center”
  • Site geography: Proposed campus near U.S. Highway 71 and 340th Street / Jet Road, south of Maryville near Barnard, southern Nodaway County (per Nodaway County's October 2026 public briefing); split structure: White Cloud
    “Nodaway County's October 2026 public briefing describes a proposed 600 MW data center near U.S. Highway 71 and 340th Street/Jet Road.”
  • Separate generation warning: DO NOT ADD: the White Cloud Generating project's own ~600 MW figure (marketing) is a generation figure for a separate grid-sale project, not additional data center load; Evergy's 440 MW Mulli
    “The proposed generation project's 600 MW figure must not be added as another data center load.”
  • Project structure: Split into two projects under the same developer: White Cloud Acres (the data center) and White Cloud Generating (the co-located natural-gas generation system, which has applied to Missouri DNR for a p
    “One is under White Cloud Acres, which would run the data center, and White Cloud Generating, which would run the generator system”
Money and contracts (16)
  • tax abatement: finding none No abatements requested or granted
    “Commission stated no abatements have been granted nor requested at this time”
  • county order - temporary moratorium: enactment Order and Ordinance Enacting a Temporary Moratorium on Data Centers within Nodaway County, Missouri for the Purposes of Due Diligence
    “Burns made a motion to enact an Order and Ordinance Enacting a Temporary Moratorium on Data Centers within Nodaway County, Missouri for the Purposes of Due Diligence.”
  • press reports it applies to construction and does not affect permitting or surveying; the DNR applicati
    “Burns made a motion to enact an Order and Ordinance Enacting a Temporary Moratorium on Data Centers within Nodaway County, Missouri for the Purposes of Due Diligence.”
  • Tenants: not stated
    “No hyperscale/end-use customer has been publicly identified”
  • Tenant status: none identified; build-and-assign model (unnamed hyperscaler to own/operate the data center; Scale retains the gas facility)
    “Scale is performing all horizontal development of the site. Upon completion, Scale will assign the land and materials to a hyperscaler”
  • Investment stated: more than $6 billion (combined data center + energy facility) USD
    “The project includes a 600-megawatt data center alongside a natural gas-powered energy facility, representing a combined investment of more than $6 billion.”
  • acquisition: transaction
    “the acquisition of Reload, a platform that sites, designs, and permits gigawatt-scale data center campuses paired with rapidly deployable on-site power infrastructure”
  • acquisition: financial terms not disclosed in the release
    “the acquisition of Reload, a platform that sites, designs, and permits gigawatt-scale data center campuses paired with rapidly deployable on-site power infrastructure”
  • development agreement (proposed): status NOT EXECUTED as of Oct 2026
    “What property has actually been purchased, optioned, or otherwise controlled?”
  • development agreement (proposed): water protection Development Agreement is intended to bar direct withdrawal from, or discharge into, the 102 River within the project boundaries
    “The Development Agreement is intended to ensure the project does not directly withdraw water from or discharge water into the 102 River within the project boundaries.”
  • development agreement (proposed): cost responsibility White Cloud Generating LLC pays capital improvements required to serve the project; costs not passed to existing District customers
    “White Cloud Generating LLC will be responsible for capital improvements required to serve the project. Costs will not be passed to existing District customers.”
  • county order - temporary moratorium: term and extension Six-month period concluding January 21, 2027; Commission may extend by an additional six months
    “It is not a permanent ban.”
  • electric service agreement: finding none No ESA or utility service contract exists
    “Public reporting indicates Evergy would serve the proposed data center”
  • all agreements: termination clauses finding FINDING: no executed agreement exists for this campus, so no termination, clawback or condition clause exists to extract. The only executed instrument is the county moratorium
    “What property has actually been purchased, optioned, or otherwise controlled?”
  • Construction stage: none - no construction; the developer holds land options (one landowner reports being told the option would not be exercised for about a year) and is running sound-baseline studies; the project was pu
    “On December 16, 2025, representatives from Chicago-based ReLoad Energy met privately with the Nodaway County Commission to discuss a $4 billion data center campus south of Maryville”
  • water service agreement: finding none No service agreement; district has made no determination and selected no preferred alternative
    “The District has not made any determination regarding whether water service will be provided, nor has it selected a preferred alternative.”
Permits and government (23)
  • Construction stage: not stated
    “Burns made a motion to enact an Order and Ordinance Enacting a Temporary Moratorium on Data Centers within Nodaway County, Missouri for the Purposes of Due Diligence.”
  • Stage: announced only
    “Burns made a motion to enact an Order and Ordinance Enacting a Temporary Moratorium on Data Centers within Nodaway County, Missouri for the Purposes of Due Diligence.”
  • Original target date: not stated
    “Burns made a motion to enact an Order and Ordinance Enacting a Temporary Moratorium on Data Centers within Nodaway County, Missouri for the Purposes of Due Diligence.”
  • Nodaway County enacted a temporary data-center moratorium for due diligence (unanimous vote); the six-month period concludes Jan 21, 2027 and may be extended six months.
    “Burns made a motion to enact an Order and Ordinance Enacting a Temporary Moratorium on Data Centers within Nodaway County, Missouri for the Purposes of Due Diligence.”
  • City of Maryville separately proposed (Council Bill 2026-58) a six-month moratorium on large-scale development over 60 contiguous acres within city limits. The campus is on unincorporated county land, so the county morat
    “The ordinance is being considered in response to increased interest in large-scale development activity within Nodaway County”
  • Nodaway County Commission: ReLoad, Inc. introduction to the Commission (Dan Scheffler, Zach Siegel, Michael Bendok)
    “Dan Scheffler, Zach Siegel and Michael Bendok from ReLoad, Inc. stopped in to introduce themselves to the Commissioners.”
  • Nodaway County Commission: Commission attended TEAMS meeting with Missouri Partnership (Subash Alias, Evan Glantz, Janelle Higgins) and Josh McKim (NCED) regarding a potential data center
    “regarding potential data center”
  • Nodaway County Commission: Scale Microgrids project update: Josh McKim (NCED) introduced Dan Scheffler, VP Development, Data Centers, Scale Microgrids; Scale recently acquired the project from RELOAD, Inc.
    “introduced the Commission to Dan Scheffler, VP Development, Data Centers with Scale Microgrids. Scale Microgrids recently acquired the project from RELOAD, Inc.”
  • Nodaway County Commission: Abatement status stated on the record
    “Commission stated no abatements have been granted nor requested at this time”
  • Nodaway County Commission: County attorney Travis Elliott reported his team is still researching and drafting the ordinance that would allow the county to explore a moratorium; closed session scheduled Jun 23, 2026 under
    “still researching and drafting the ordinance that would allow Nodaway County to explore a moratorium”
  • Nodaway County Commission: Tentative presentation of the draft Order and Ordinance Enacting a Temporary Moratorium on Data Centers; draft shared with the public; press release sent to media
    “tentative presentation of An Order and Ordinance Enacting a Temporary Moratorium on Data Centers within Nodaway County, Missouri”
  • Nodaway County Commission: Moratorium enacted: Order and Ordinance Enacting a Temporary Moratorium on Data Centers within Nodaway County, Missouri for the Purposes of Due Diligence
    “Burns made a motion to enact an Order and Ordinance Enacting a Temporary Moratorium on Data Centers within Nodaway County, Missouri for the Purposes of Due Diligence.”
  • Maryville City Council: Council Bill No. 2026-58 (agenda item): proposed Large-Scale Development Moratorium Ordinance - six-month pause on projects exceeding 60 contiguous acres within the City of Maryville
    “The proposed Large-Scale Development Moratorium Ordinance establishes a temporary six-month pause on the acceptance, processing, approval, and permitting of certain commercial, industrial, and mixed-use development projects exceeding sixty (60) contiguous acres within the City of Maryville.”
  • Air construction permit application: Application filed - pending
    “A separate proposed natural-gas generation facility has Missouri DNR air application 2026-06-032 (site 147-0052).”
  • air construction permit: application filed
    “Missouri DNR - White Cloud Generating LLC construction permit application (2026-06-032).”
  • air construction permit: administratively complete
    “Application states the facility would sell up to 600 MW to the local bulk electric system.”
  • air construction permit: pending - listed on DNR Pending Air Permits
    “air-related permit applications the department has received and currently is reviewing”
  • Clean Water Act Section 404 / jurisdictional action: action listed in USACE public regulatory database
    “U.S. Army Corps of Engineers - NWK-2026-00145, White Cloud Acres, LLC - White Cloud Acres.”
  • construction land disturbance stormwater permit: not yet obtained - developer states it will be obtained before land disturbance
    “Prior to land disturbance, the project will obtain the applicable Missouri Department of Natural Resources (MDNR) Construction Land Disturbance Stormwater Permit.”
  • certificate of convenience and necessity (CCN): no filing - negative finding
    “On July 31, 2025, the Missouri Public Service Commission issued its Report and Order in Case No. EA-2025-0075”
  • White Cloud Generating, LLC filed MO DNR construction-permit application 2026-06-032 for a 12-turbine natural-gas generation facility at Barnard (Site ID 147-0052); administratively complete Jul 20, 2026.
    “Missouri DNR - White Cloud Generating LLC construction permit application (2026-06-032).”
  • Nodaway County enacted a six-month data-center moratorium on July 21, 2026, while the White Cloud Acres proposal was under county review; the county's October 2026 public briefing describes proposals and pending decision
    “The county enacted a six-month data-center moratorium July 21, 2026.”
  • Regulatory status: Six-month county measure VERIFIED as a moratorium: the Nodaway County Commission adopted a data-center moratorium unanimously in July 2026, running six months (terminable early or extendable by six mor
    “The period will be for six months and can be terminated early by the Commission or extended for another six months. The measure applies to construction and does not affect permitting or surveying”
Site and other (16)
  • Developer original: ReLoad, Inc. (Reload)
    “Dan Scheffler, Zach Siegel and Michael Bendok from ReLoad, Inc. stopped in to introduce themselves to the Commissioners.”
  • County: Nodaway County, Missouri
    “within Nodaway County, Missouri for the Purposes of Due Diligence”
  • First announced: Dec. 16, 2025
    “Dan Scheffler, Zach Siegel and Michael Bendok from ReLoad, Inc. stopped in to introduce themselves to the Commissioners.”
  • First documented developer contact: ReLoad, Inc. (Dan Scheffler, Zach Siegel, Michael Bendok) introduced itself to the Nodaway County Commission.
    “Dan Scheffler, Zach Siegel and Michael Bendok from ReLoad, Inc. stopped in to introduce themselves to the Commissioners.”
  • County code: 29147
    “Site is in Nodaway County, MO (FIPS 29147)”
  • Name: White Cloud Acres
    “White Cloud Acres, LLC - White Cloud Acres”
  • Current target date: not stated
    “No hyperscale/end-use customer has been publicly identified”
  • Regulatory status: County temporary data-center moratorium in effect; six-month period concludes Jan. 21, 2027, extendable by six months
    “It is not a permanent ban.”
  • Sound-baseline work performed: background sound levels measured for seven days in July 2026 at several locations along the proposed project boundary; compliance to be modeled against a 50 dBA limit (CadnaA / ISO 9613-2).
    “Background sound levels were measured for seven days at several locations along the proposed project boundary representing nearby non-participating residences.”
  • Water alternatives still open: reclaimed water from the Maryville wastewater treatment facility or potable water from Savannah; final source not determined. Maryville and PWSD No. 1 began discussions in September 2026 re
    “Two alternatives are currently identified: reclaimed water from the Maryville wastewater treatment facility or potable water from Savannah.”
  • Water demand avg: 82000 gpd
    “The proposed industrial user will need a minimum of 82,000 gallons per day (gpd), on average, to run the site.”
  • Water service status: No determination made by Public Water Supply District No. 1; no preferred alternative selected
    “The District has not made any determination regarding whether water service will be provided, nor has it selected a preferred alternative.”
  • Organized local opposition (Nodaway Says No; May 1, 2026 rally; May 26, 2026 community meeting) and a petition demanding the commissioners extend the data-center moratorium, with an independent impact review and farmland
    “Demand for Nodaway County Commissioners to Extend the Data Center Moratorium”
  • County meeting reporting in September 2026 described Grand River Mutual marking utility lines at the White Cloud Generating work site (press-level item relayed in the county presentation).
    “marking utility lines at the White Cloud Generating work site”
  • Aggregator reporting expected a final go/no-go decision by the end of June 2026. No decision occurred; the county instead spent June-July 2026 drafting and enacting the moratorium. The milestone is stale and should carry
    “final go/no-go decision expected by end of June 2026”
  • Moratorium: Nodaway County enacted a six-month data center moratorium on July 21, 2026; the moratorium names data centers and, per county discussion, may not reach the separate White Cloud Generating entity
    “The county enacted a six-month data-center moratorium July 21, 2026.”