Power and the grid
None energized or contracted yet
- On-site natural gas fuel cells Exploratorysponsor says it is exploring them with Bloom Energy (Aug. 2026); no contract, application or permit News report · Aug. 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Dec. 10, 2025Site made eligible, not servedThe county plan change approves industrial use only; water and operating details were deferred to later steps. News report · Dec. 2025
- Jan. 14, 2026Utility queue contextAPS reports about 30,000 MW of data-center requests against an 8,200 MW peak; none names this campus (press). News report · Jan. 2026
- Not setPower agreement: noneNo electric service agreement, direct pricing contract or interconnection agreement naming the campus is public. Dataset · Oct. 2026
- A 500 kV Palo Verde to Rudd line (APS) runs about 0.8 km from the site anchor. OpenStreetMap · Oct. 2026
- Any future load would price under an APS large-load schedule that is being re-litigated in a rate case heard in 2026. Utility regulator · July 2026
Permits checklist
2 granted · 4 checked, nothing on file
Land-use entitlements are in hand; nothing needed to build or power the campus has been filed.
- ✓Comprehensive plan amendment CPA 25-0008 GrantedMaricopa County Board of Supervisors · Dec. 10, 2025: voice vote after an 8-0 planning commission recommendation on Nov. 6; designation only, no zoning or site approval News report · Dec. 2025
- ✓Rezoning to industrial (two-story data centers) GrantedMaricopa County Board of Supervisors · April 2026: unanimous per press; exact meeting date not retrieved News report · April 2026
- –Checked, nothing on file: Site plan and building permits, Air permit for on-site generation, Power plant or line siting certificate, State data-center tax exemption
What could slow it down
- HighNo buyer or tenantThe sponsor's model is to entitle and resell the land; as of Oct. 2026 a state tracker still lists it as land to be resold to a builder. Dataset · Oct. 2026
- HighNo power pathAPS has about 30,000 MW of requests against an 8,200 MW peak (press), and nothing ties this site to a supply agreement. News report · Oct. 2026
- MediumClaims keep growingThe stated size grew from 1 GW (May 2025) to about 3.5 GW (Oct. 2026) with no new approval beyond a two-story zoning change. News report · Oct. 2026
- MediumState political riskThe attorney general called for a pause on new data centers in Oct. 2026; the governor opposes a moratorium. News report · Oct. 2026
- WatchWaterA speaker at the Dec. 2025 hearing said a 1.5 GW campus could use 10 million gallons of water a day; the sponsor says closed-loop cooling, and water details were deferred. News report · Dec. 2025
Money on record
Not on record: construction or project financing: only the land-deal investor group is on record News report · May 2025; tax incentives or abatements: statewide exemption moratorium runs to June 2029 State agency · June 2026
What happened, and what is due
- 2008Site The ranch is entitled for more than 5,700 homes that are never built. News report · Dec. 2025
- May 28, 2025Site Arizona Land Consulting announces a $51M land deal and a site that can accommodate over 1 GW. Company · May 2025
- Nov. 6, 2025Permits County planning commission recommends the plan amendment 8-0, a recommendation only. News report · Nov. 2025
- Dec. 10, 2025Permits County supervisors approve the plan amendment for 2,077 acres, and adopt a data-center zoning ordinance. News report · Dec. 2025
- March 3, 2026Site Adjacent neighbors submit a support letter after the developer agrees to larger setbacks and other changes. News report · April 2026
- April 2026Permits Supervisors unanimously rezone the land, allowing two-story data centers. News report · April 2026
- May 20, 2026Site The sponsor buys a separate 956-acre Tonopah site, a different campus. News report · May 2026
- June 13, 2026Money Arizona bars new data-center sales-tax exemption applications for three years. State agency · June 2026
- Aug. 31, 2026Power Sponsor tells a magazine it is exploring on-site natural-gas power. News report · Oct. 2026
- Oct. 6, 2026Site Sponsor raises its stated size from 1.5 GW to about 3.5 GW across 50+ buildings and more than $50B (press). News report · Oct. 2026
- Oct. 13, 2026Site A reporter returning to the site finds neighbors still looking at open desert. News report · Oct. 2026
- June 2029Money State moratorium on new data-center tax exemptions ends. State agency · June 2026
Satellite captures by quarter
Since March 2022: 71 satellite captures. The chart starts in the first quarter of 2023; 4 earlier records are not drawn.
Specs
5,700 homes, never built the site was entitled for housing in 2008. News report · Dec. 2025
- Up to two stories: the Apr. 2026 rezoning allows two-story data center buildings; 50+ buildings claimed (Oct. 2026) News report · Oct. 2026
- Closed-loop cooling: sponsor design intent; no building design has been filed News report · Aug. 2026
- Larger setbacks: offices nearest neighbors, road moved, desert buffer (reported neighbor concessions) News report · Oct. 2026
Owners, partners and builders
- Arizona Land Consulting: developer; CEO Anita Verma-Lallian
- Hassayampa Ranch, Light Year Capital and DYA Capital: named co-buyers in recorder documents (press)
- Social Capital (Chamath Palihapitiya): investor in the land deal, role undisclosed
- Arizona Public Service: incumbent utility, no agreement
- Bloom Energy: named by the sponsor for exploratory fuel cells
- Maricopa County Board of Supervisors: approved the plan change and rezoning
- City of Buckeye: withdrew its opposition after wildlife commitments
- Berry Riddell LLC: land-use counsel to the applicant
- Tonopah and Buckeye neighbors: petitions of about 100 to 200 signers; lead opponents later supported the revised plan
Open questions
- Any buyer, tenant or end user.
- A power agreement or study with APS.
- Water supply and the written zoning stipulations.
- Whether the 3.5 GW claim is supported by any plan filing.
- 2 unconfirmed county land records near the site: the buyer or location could not be tied to this campus.
271 records from 25 documents
Drawn from news reports, public and commercial datasets, state agency records, company statements, securities filings, utility regulator dockets and satellite captures, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (30)
- Utility service: not stated“Hassayampa Ranch | Arizona Land Consulting | Unincorporated Maricopa Co., near Tonopah | 2,000 acres; 1 GW; $25B”Dataset · Oct. 2026 · grade B
- Interconnection status: No executed APS agreement, substation commitment or queue position located. Any service would require APS interconnection studies, which had not been reported as started, let alone completed, in a“Hassayampa Ranch | Arizona Land Consulting | Unincorporated Maricopa Co., near Tonopah”Dataset · Oct. 2026 · grade B
- Electric service agreement signed: none found - no APS electric service agreement, Direct Pricing Contract or load contract naming ALC or Hassayampa Ranch is public“land to be resold to a builder”Dataset · Oct. 2026 · grade B
- Grid operator: none - APS balancing area (WECC); Arizona has no ISO/RTO market“changes to APS's Extra High Load Factor (which applies to large load users, such as manufacturing companies and data centers)”Utility regulator · July 2026 · grade B
- Tariff context: Any eventual APS load would price under APS's Extra High Load Factor schedule or a Direct Pricing Contract. The XHLF structure is being re-litigated in APS rate case E-01345A-25-0105 (filed Jun 2025; hear“The Hearing in the Arizona Public Service Company (APS) rate case began on May 18, 2026 and concluded on July 7, 2026”Utility regulator · July 2026 · grade B
- Stated campus size: 1,000 MW“This project can accommodate over 1GW”Company · May 2025 · grade B
- ALC announces closing of the $51M Hassayampa Ranch land deal with Palihapitiya/Social Capital in the investor group; 'over 1GW' capacity claim; no tenant, timeline or power arrangement disclosed“This project can accommodate over 1GW”Company · May 2025 · grade B
- Nearest substation: REFERENCE: 4.42 km - unnamed 69 kV substation at 33.47958,-112.70803Measured on OpenStreetMap map data.
- Nearest power line of 345 kV or more: REFERENCE: 0.79 km - Palo Verde - Rudd 500 kV line (Arizona Public Service)Measured on OpenStreetMap map data.
- Nearest power line of 138 kV: REFERENCE: 4.46 km - 230 kV line (nearest line in the 100-345 kV band)Measured on OpenStreetMap map data.
- Nearest gas pipeline: REFERENCE: 4.54 km - gas pipeline (Arizona Public Service)Measured on OpenStreetMap map data.
- IT capacity: not stated“increased projected power demand from 1.5 GW to roughly 3.5 GW across more than 50 planned data center buildings”News report · Oct. 2026 · grade C
- On-site generation: not stated“Arizona Land Consulting is finding onsite generation techniques using natural gas to reduce its reliance on utility-owned generation, according to Verma-Lallian. Bloom Energy, one of its partners, uses fuel cells”News report · Oct. 2026 · grade C
- Utility: Arizona Public Service (APS) - incumbent utility for the Tonopah / far West Valley area; no APS agreement of any kind is public for this campus“Arizona Public Service (APS) - which currently peaks around 8,200 MW - has 30,000 MW of data center requests sitting in their queue”News report · Oct. 2026 · grade C
- Power plan: grid“ALC is pioneering sustainable solutions, including partnerships in waterless cooling technology for data centers and exploring next-gen power sources like fusion and renewables”Company · Oct. 2026 · grade C
- Stage: Entitled land bank, pre-construction (paper): land closed May 2025 and both county entitlements won - Major CPA2500008 (Dec 10, 2025) and industrial rezoning (Apr 2026) - but there is no buyer/tenant, no power con“Anita Verma-Lallian and Chamath Palihapitiya have zoning approval”News report · Oct. 2026 · grade C
- Paper or real: Real: ~2,077 acres closed and rezoned for industrial/data-center use over organized opposition - the entitlements are the asset, consistent with ALC's entitle-and-resell model. Paper: the campus itself - n“increased projected power demand from 1.5 GW to roughly 3.5 GW across more than 50 planned data center buildings”News report · Oct. 2026 · grade C
- certificate of environmental compatibility (transmission/power siting): none found“to view the ACC Decision granting the CEC, go to the Commission Online docket at edocket.azcc.gov and enter docket L-00000YY-15-0318-00171”State agency · Oct. 2026 · grade C
- Stated campus size: 3,500 MW“increased projected power demand from 1.5 GW to roughly 3.5 GW across more than 50 planned data center buildings”News report · Oct. 2026 · grade C
- Maricopa County approves rezoning for a THIRD ALC site: a 1,000+ acre film-studio campus with a planned 500 MW data center component (the 'Balterra' mixed-use project, approved early Sep 2026); NPM's“Maricopa County officials approved rezoning for another Arizona Land Consulting project, a more than 1,000-acre film studio campus that includes a planned 500 MW data center component”News report · Oct. 2026 · grade C
- Sponsor restates the campus at ~3.5 GW, >50 two-story buildings and >$50B capex in an NPM interview - roughly triple the announced 1.5 GW - on the strength of the April 2026 two-story zoning alone. Still no tenant, buyer“increased projected power demand from 1.5 GW to roughly 3.5 GW across more than 50 planned data center buildings”News report · Oct. 2026 · grade C
- ALC acquires a SEPARATE 956-acre Tonopah site for $25M, taking its Tonopah-area holdings to ~4,000 acres across three sites; secondary coverage repeatedly blends“on May 20 she acquired 956 acres in Tonopah, Arizona... bringing her to a total of 4,000 acres across three sites in the area all slated for data center use”News report · May 2026 · grade C
- APS reports ~30,000 MW of data-center requests against an ~8,200 MW system peak; APS abandoned its 100% clean-energy commitment in Aug 2025 and plans a new 2,000 MW gas plant. No APS statement names Hassayampa; portfolio“We've never sat in a position before where somebody's asking you to triple the size of your company”News report · Jan. 2026 · grade C
- Development stage: Entitlements only - CPA25008 comprehensive plan amendment approved by the Board of Supervisors Dec 12, 2025 (P&Z recommended 8-0 on Nov 6, 2025); Apr 2026 zoning allows two-story data center buildings;“The Maricopa County Board of Supervisors on Dec. 12 approved a comprehensive plan amendment for Hassayampa Ranch (CPA 25-0008) that redesignates roughly 2,077 acres near the Tonopah-Arlington area.”News report · Dec. 2025 · grade C
- Governing jurisdiction: Maricopa County (unincorporated): the Board of Supervisors / Planning & Zoning Commission hold land-use authority. The site is OUTSIDE Buckeye city limits, so no city approval was required or obta“The site, known as Hassayampa Ranch, is situated in a sparsely populated, unincorporated area of far western Maricopa County, just outside the city limits of Buckeye”News report · Dec. 2025 · grade C
- Land acquisition: Arizona Land Consulting (Anita Verma-Lallian) bought Hassayampa Ranch in May 2025 in a $51M deal backed by investors including Chamath Palihapitiya (Social Capital).“In May 2025, she had bought a vast tract of desert called Hassayampa Ranch, in a $51 million deal backed by heavyweight tech investors including billionaire venture capitalist Chamath Palihapitiya.”News report · May 2025 · grade C
- Stated campus size: 1,000 MW“In terms of capacity, Palihapitiya said that the facility would be able to "accommodate over 1GW." Anita Verma-Lallian, CEO of ALC, told DCD that this number could potentially reach up to 1.5GW.”News report · May 2025 · grade C
- Stated campus size: 1,000 MW“In terms of capacity, Palihapitiya said that the facility would be able to "accommodate over 1GW." Anita Verma-Lallian, CEO of ALC, told DCD that this number could potentially reach up to 1.5GW.”News report · May 2025 · grade C
- Interconnection status: Announcement stage only - the queue's interconnection study tag is unverified: no APS interconnection study, service agreement or ACC filing naming Hassayampa Ranch was located (see searched rows)“Development timelines are not currently available, but Palihapitiya said that they would “continue the process of entitlements and regulatory permitting so we can start construction.””News report · May 2025 · grade C
- Stated campus size: 1,500 MW“Anita Verma-Lallian, CEO of ALC, told DCD that this number could potentially reach up to 1.5GW, but noted that it was challenging to provide estimates until the project entered the planning and design phases”News report · May 2025 · grade C
Money and contracts (21)
- Sponsor model: Entitle-and-resell: ALC buys unzoned land, wins entitlements, and resells to a builder/end user; it does not operate data centers“Hassayampa Ranch | Arizona Land Consulting | Unincorporated Maricopa Co., near Tonopah | 2,000 acres; 1 GW; $25B | County zoning approved 5 to 0 | Dec 2025, land to be resold to a builder”Dataset · Oct. 2026 · grade B
- power supply (APS): finding - no agreement exists in the public record FINDING: no ESA, Direct Pricing Contract, interconnection agreement or other APS instrument naming ALC or Hassayampa Ranch was found in any source ch“land to be resold to a builder”Dataset · Oct. 2026 · grade B
- AZ tracker still carries Hassayampa Ranch as 'land to be resold to a builder' (1 GW / $25B / 2,000 acres) - i.e., as of the Oct 2026 pass the entitlement flip has not produced a named buyer in tracker or press coverage“Hassayampa Ranch | Arizona Land Consulting | Unincorporated Maricopa Co., near Tonopah | 2,000 acres; 1 GW; $25B”Dataset · Oct. 2026 · grade B
- Incentives: No Arizona Commerce Authority Computer Data Center exemption approval, GPLET or county abatement for this campus found in any source checked. Statewide, HB 4168 (signed Jun 13, 2026) bars the ACA from accepti“a three year data center tax credit moratorium”State agency · June 2026 · grade B
- tax incentives: finding - no incentive agreement found FINDING: no ACA Computer Data Center exemption approval, GPLET or abatement for this campus appears in any source checked. Independently, HB 4168 (signed Jun 13, 202“a three year data center tax credit moratorium”State agency · June 2026 · grade B
- Name: Hassayampa Ranch Data Center“Chamath Palihapitiya Joins $51M Arizona AI Datacenter Land Deal With Arizona Land Consulting's Anita Verma-Lallian”Company · May 2025 · grade B
- Developer: Arizona Land Consulting (ALC)“Arizona Land Consulting (ALC), Arizona's AI data center investment fund led by Anita Verma-Lallian, has closed on a landmark $51 million land deal”Company · May 2025 · grade B
- Announced: May 28, 2025“PHOENIX, AZ, UNITED STATES, May 28, 2025 /EINPresswire.com/ -- Arizona Land Consulting (ALC)... has closed on a landmark $51 million land deal”Company · May 2025 · grade B
- Land control date: May 2025“has closed on a landmark $51 million land deal”Company · May 2025 · grade B
- Land price: 51000000 USD“has closed on a landmark $51 million land deal”Company · May 2025 · grade B
- land acquisition: scope Approximately 2,077 acres (APNs 504-03-010A/B) north of I-10 near 339th Ave, Tonopah - the Hassayampa Ranch master-planned land“has closed on a landmark $51 million land deal”Company · May 2025 · grade B
- Tenants: none - no tenant, buyer or end user named in any source checked through Oct 2026“Anita Verma-Lallian and Chamath Palihapitiya have zoning approval. But the neighbors I met last December are still looking out at open desert”News report · Oct. 2026 · grade C
- development agreement (Maricopa County): finding - no agreement located; stipulation text not retrieved FINDING: no development agreement between ALC and Maricopa County was located. The Apr 2026 rezoning presumably carr“any specific setbacks, design stipulations and mitigation measures will be addressed if and when the applicant files for a zone change and plan of development”News report · Oct. 2026 · grade C
- Stated capital cost: 50000000000 USD“lifted the project's expected capital outlay from USD 25bn to more than USD 50bn”News report · Oct. 2026 · grade C
- neighbor commitments (zoning phase): scope / conditions as reported Concessions that converted the lead opponents: larger setbacks; office buildings (not data halls) nearest the adjacent homes; access road relocated away“By March 3, more than five weeks before the final hearing, the Fletchers submitted a formal letter of support to the Maricopa County Board of Supervisors”News report · March 2026 · grade C
- wildlife coordination commitment: condition (reported) Applicant agreed to work with the city, AZGFD and the Conservancy to mitigate impacts on wildlife movement; on that basis Buckeye withdrew its earlier opposition to“Buckeye officials withdrew their opposition after Arizona Land Consulting agreed to work with the city, the Arizona Game and Fish Department and the White Tank Mountains Conservancy to mitigate the impact on wildlife movement”News report · Dec. 2025 · grade C
- Tenant status: none found - six to eight hyperscalers reported interested (sponsor statement to Fortune, Dec 2025); none named, no LOI disclosed“We have probably six to eight large hyperscalers that are interested in looking at it”News report · Dec. 2025 · grade C
- Stated capital cost: 25000000000 USD“Verma-Lallian said that this would cost $25 billion at full build out”News report · May 2025 · grade C
- Financing: No construction or project financing found. The only capital in the record is the May 2025 land-deal investor group (Social Capital / Chamath Palihapitiya; DYA Capital; Light Year Capital per recorder reportin“The deal was backed by Chamath Palihapitiya, CEO of tech venture capital firm Social Capital. Palihapitiya's exact role or level of investment was not disclosed”News report · May 2025 · grade C
- land acquisition: price 51000000 USD“documents show that Hassayampa Ranch first sold the land to ALC for $37.5m, before ALC then sold the land back to Hassayampa Ranch, Light Year Capital, and DYA Capital for $51m”News report · May 2025 · grade C
- land acquisition: finding - terms not public FINDING: no purchase agreement text is public; conditions, contingencies, termination or resale terms are not disclosed in any source checked. Sources close to the deal told D“Sources close to the deal said that these figures are not accurate, and that the minutiae of the closing could not be disclosed”News report · May 2025 · grade C
Permits and government (17)
- Governor Hobbs signs the FY2027 budget including HB 4168: three-year moratorium - the Arizona Commerce Authority may not accept new data-center sales-tax exemption applications Jul 1, 2026-Jun 30, 2029. Hassayampa holds“a three year data center tax credit moratorium”State agency · June 2026 · grade B
- site plan / building permits: none found“the neighbors I met last December are still looking out at open desert”News report · Oct. 2026 · grade C
- Conditions of approval: Neighbor concessions negotiated during the zoning phase (reported; the county stipulation text itself was not retrieved): larger setbacks; office buildings rather than data halls nearest the adjac“updated plans that included larger setbacks, putting offices rather than data center buildings closest to their homes, relocating a road to keep traffic away, and preserving desert landscaping as a buffer”News report · Oct. 2026 · grade C
- Arizona AG Kris Mayes publicly calls for a pause on new data center development pending regulation; Governor Hobbs states she opposes a moratorium. State-level political risk context for all unbuilt AZ campuses“Earlier this month, Arizona Attorney General Kris Mayes called for a pause on all new development until regulations and policies around their build-out are put in place. But Gov. Katie Hobbs said she opposes such a moratorium”News report · Oct. 2026 · grade C
- Rezoning date: April 2026“It turns out the Maricopa County Board of Supervisors unanimously approved the zoning for Hassayampa Ranch in April”News report · April 2026 · grade C
- zone change (rezoning to industrial): approved“The county's Board of Supervisors approved a zoning change in April allowing two-story, rather than one-story, data centers on the site”News report · April 2026 · grade C
- Maricopa County Board of Supervisors: Hassayampa Ranch rezoning (zone change to industrial; two-story data center buildings allowed)“Days later, the Maricopa County Board of Supervisors granted final zoning approval to the Hassayampa Ranch data center project outside Tonopah”News report · April 2026 · grade C
- Water use stated: Sponsor claims near-zero water use via closed-loop cooling ('except during construction'). No water supply, well filing or ADWR document for the campus appears in any source checked; at the Dec 2025 CPA“those details, including water use and operational specifics, will be considered during a subsequent rezoning and site-plan process”News report · Dec. 2025 · grade C
- Opposition: Organized Tonopah/Buckeye neighbor opposition through the CPA phase: Change.org petition against CPA2500008 (~200 signatures per Fortune; organizer Cherisse Campbell, heritage-turkey hatchery); two petitions“two petitions submitted to county officials collectively contained the signatures of 100 Tonopah and Buckeye residents opposed to the plan”News report · Dec. 2025 · grade C
- comprehensive plan amendment (Major CPA): approved“The Board approved CPA 25-0008 to change about 2,077 acres near Tonopah from a long-standing master-planned community designation to industrial”News report · Dec. 2025 · grade C
- zoning ordinance text amendment (county policy context): adopted“The county's new ordinance, passed Dec. 10, states that data centers will be allowed in two districts: IND-2 for general industrial uses and IND-3 for heavy industrial uses”News report · Dec. 2025 · grade C
- Same BOS meeting adopted TA25001, the county zoning ordinance modernization: data centers allowed in IND-2 (general industrial) and IND-3 (heavy industrial) districts; other land must rezone. This is the framework the Ap“data centers will be allowed in two districts: IND-2 for general industrial uses and IND-3 for heavy industrial uses”News report · Dec. 2025 · grade C
- Maricopa County Board of Supervisors (formal meeting): CPA2500008 - Hassayampa Ranch comprehensive plan amendment approval“The motion was seconded and approved by voice vote; Chairman Galvin had recused himself for planning and zoning items”News report · Dec. 2025 · grade C
- Site acres: 2077 acres“The Planning and Zoning Commission voted 8-0 to recommend approval of CPA25008, a major comprehensive plan amendment to redesignate about 2,077 acres near Tonopah.”News report · Nov. 2025 · grade C
- Acres: 2077 acres“The Planning and Zoning Commission on Nov. 6 voted 8-0 to recommend approval of CPA 25008 to redesignate about 2,077 acres near Tonopah for industrial uses”News report · Nov. 2025 · grade C
- Change.org petition filed against Major CPA CPA2500008 (organizer Cherisse Campbell); ~200 signatures per Fortune; parallel petitions to the county totaling 100 signatures (azcentral); 104-signature petition presented at“RE: Opposition to Major Comprehensive Plan Amendment Application Case No. CPA2500008”News report · Nov. 2025 · grade C
- Maricopa County Planning & Zoning Commission: CPA2500008 - Major Comprehensive Plan Amendment, Hassayampa Ranch (2,077 acres, master-planned community to industrial)“The Planning and Zoning Commission on Nov. 6 voted 8-0 to recommend approval of CPA25008”News report · Nov. 2025 · grade C
Legal (1)
- Lawsuits: none found - opposition proceeded by petition and hearing testimony only; no litigation over the CPA or rezoning appears in any source checked“the Maricopa County Board of Supervisors unanimously approved the zoning for Hassayampa Ranch in April”News report · Oct. 2026 · grade C
Site and other (11)
- County code: 04013“FCC census block API: campus anchor -> Maricopa County AZ 04013; on-site facilities (same tract) -> Maricopa County”Dataset · Oct. 2026 · grade B
- County code: 04013“We, the undersigned property owners and residents of Maricopa County, Arizona”News report · Oct. 2026 · grade C
- Construction stage: not stated“the neighbors I met last December are still looking out at open desert”News report · Oct. 2026 · grade C
- Current target date: not disclosed“The expanded scale of Hassayampa Ranch could allow it to serve either multiple end users or a single one”News report · Oct. 2026 · grade C
- Aliases: Arizona Land Consulting Buckeye campus; Hassayampa Ranch hyperscale campus“Arizona Land Consulting's nearly 1,700-acre Maricopa County, Arizona Hassayampa Ranch hyperscale data center campus”News report · Oct. 2026 · grade C
- Buildings: 50+“roughly 3.5 GW across more than 50 planned data center buildings”News report · Oct. 2026 · grade C
- Cooling: closed-loop / direct-to-chip liquid cooling (sponsor design intent; no building design has been filed)“she says 100 percent of her data centers are using the same technology and will continue to in the future”News report · Aug. 2026 · grade C
- Prior entitlement: Hassayampa Ranch development master plan: approved 2005 and intensively entitled in 2008 for more than 5,700 residential units; never built. The Dec 2025 CPA replaced the master-plan designation with i“the site was intensively entitled in 2008 for more than 5,700 residential units but never developed”News report · Dec. 2025 · grade C
- Address: North of I-10 near 339th Avenue, Tonopah/Arlington area, unincorporated Maricopa County, AZ (about 50 miles west of downtown Phoenix)“the site, north of I-10 near 339th Avenue, is surrounded by existing and proposed industrial operations”News report · Nov. 2025 · grade C
- Parcel IDs: 504-03-010A; 504-03-010B“approximately 2,077 acres that are identified as Parcel # 504-03-010A and 504-03-010B”News report · Nov. 2025 · grade C
- Original target date: not disclosed - no construction or delivery timeline has ever been published for this campus“Development timelines are not currently available”News report · May 2025 · grade C