Power and the grid
The plan on record is the grid, with on-site gas as a bridge. An interconnection study is under way.
We checked utility filings, regulator dockets and air-permit records for this campus.
Permits checklist
2 pending · 4 checked, nothing on file
Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.
- ◷Zoning approval PendingMaricopa County Planning and Development · Sept. 2026: Rezoning under review by Maricopa County Planning and Development. News report · Sept. 2026
- ◷Utility and grid approval PendingArizona Corporation Commission · 2025: Public hearing held on the transmission line approval. Company · Oct. 2026
- –Checked, nothing on file: Site plan, Building permit, Air permit, Water and wetlands permits
Money on record
$1.7B Construction financing (Construction loan). News report · Sept. 2026
What happened, and what is due
- April 2026Permits In April, Copia received rezoning approvals to expand the initial Harquahala phase by 700 acres while allowing for data center uses. News report · Sept. 2026
- Sept. 2026Permits Rezoning under review by Maricopa County Planning and Development. News report · Sept. 2026
Since Oct. 2026: 1 satellite capture. Satellite · Oct. 2026
Owners, partners and builders
- Copia Power, developer
- EQT
- The Carlyle Group, partner
Open questions
- Signed electric service agreement and delivery date.
- Whether site work has started.
23 records from 5 documents
Drawn from news reports, public and commercial datasets, satellite captures and company statements, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (10)
- transmission upgrade (ACC CEC): applied - public hearings held Sept. 29, 2025/30“Copia Power has submitted an application for a Certificate of Environmental Compatibility for a transmission line in Maricopa County to interconnect new generation, load, and increase resiliency”Company · Oct. 2026 · grade B
- On-site generation: 1,250 MW“(P) Planned for installation, but regulatory approvals not initiated”Dataset · Aug. 2026 · grade B
- Role of the on-site plant: prime“Saddleback Generation Station; Copia Power; Maricopa County; Natural Gas Fired Combined Cycle”Dataset · Aug. 2026 · grade B
- On-site power technology: natural gas combined cycle“Natural Gas Fired Combined Cycle”Dataset · Aug. 2026 · grade B
- Campus name: Copia Power Belmont Energy Center / Harquahala campus“is working to rezone about 3,100 acres near Tonopah in the far West Valley for its latest project, the Belmont Energy Center”News report · Sept. 2026 · grade C
- Site acreage: 3100 acres“Most of the project site - about 2,860 acres - would be for utility-scale solar energy generation, while about 320 acres would be used for a gas generation facility, BESS and data centers”News report · Sept. 2026 · grade C
- Announced: Sept. 2, 2026“Copia Power, which develops, builds and operates grid-connected power and data center infrastructure, is working to rezone about 3,100 acres near Tonopah”News report · Sept. 2026 · grade C
- Inside the wider planned campus, Copia has completed its flagship Harquahala Sun project (450 MW solar + 1,200 MWh storage, $1.2B) and is building the Maricopa Energy Center (550 MW solar + 2,200 MWh). This generation co“Copia just completed its flagship project within the larger planned campus - a $1.2 billion, 450-megawatt solar farm with 1,200 megawatt hours of battery storage”News report · Sept. 2026 · grade C
- Project status: Entitlement stage: the Belmont Energy Center rezoning (about 3,100 acres) is early in the Maricopa County process with no planning-and-zoning hearing yet scheduled; the 917-acre Harquahala campus's plan a“The Maricopa County Board of Supervisors of Arizona will consider Dec. 10 two land use requests tied to Copia Power's proposed 917-acre data center campus”News report · Dec. 2025 · grade C
- Utility: Arizona Public Service (APS)“an expansion of the nearby and under-construction Maricopa Energy Center (MEC), a 550 MW solar and 2,200 MWh battery storage facility, supported by 20-year PPAs with Arizona Public Service”News report · Dec. 2025 · grade C
Money and contracts (2)
- construction financing (construction loan): construction loan 1700000000 USD“The project is backed by a $1.7 billion construction loan and has a power purchase agreement with APS”News report · Sept. 2026 · grade C
- power purchase agreements (20-year): PPA term 20 years“a 550 MW solar and 2,200 MWh battery storage facility, supported by 20-year PPAs with Arizona Public Service”News report · Dec. 2025 · grade C
Permits and government (4)
- County code: 04013“according to planning documents filed with Maricopa County”News report · Sept. 2026 · grade C
- rezoning: applied - early entitlement; planning and zoning commission hearing not yet scheduled“Its latest 3,100-acre Belmont Energy Center project is early in the entitlement process. A planning and zoning commission hearing hasn't been scheduled yet”News report · Sept. 2026 · grade C
- In April (2026, per the September 2026 report), Copia received rezoning approvals to expand the initial Harquahala phase by 700 acres while allowing for data center uses - the entitlement under which the data-center comp“In April it received rezoning approvals to expand that initial phase by 700 acres while allowing for data center uses”News report · Sept. 2026 · grade C
- rezoning: Planning Commission recommended approval Nov. 6, 2025; Board of Supervisors consideration scheduled Dec. 10, 2025 (outcome not in sources retrieved)“The Planning Commission recommended the land use requests for approval Nov. 6”News report · Dec. 2025 · grade C