Power
Power and the grid
504 MW contracted
ComEd gridDeveloper says secured
utility power the developer says is secured; FERC filing does not state MW Company · Nov. 2025
Contracted
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Nov. 2025Power claimKaris materials say 504 MW of ComEd power is secured. Company · Nov. 2025
- May 22, 2026Transmission agreement filedComEd files a transmission service agreement with Karis Critical at FERC, asking that it take effect July 22, 2026. see Permits
- Q1 2029First energizationDeveloper's expected date. Company · Nov. 2025
- The FERC notice names Karis Critical but not the site, and the agreement itself was not retrieved, so its link to DeKalb rests on the developer's materials. State agency · Oct. 2026
Permits
Permits checklist
1 pending
Filings on record.
- ◷Transmission service agreement (ER26-2615-000) PendingFERC · May 22, 2026: filed by ComEd; requested effective July 22, 2026; acceptance not on record State agency · May 2026
Risks
What could slow it down
- MediumPower claim is the developer'sThe 504 MW figure comes from Karis's own materials; the FERC notice states no MW. Company · Nov. 2025
- MediumSite link unconfirmedThe transmission agreement document was not retrieved, so which site it covers is not confirmed. State agency · Oct. 2026
Timeline
What happened, and what is due
SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
- Nov. 2025Site Karis Critical markets a DeKalb hyperscale campus with 504 MW of ComEd power Company · Nov. 2025
- May 22, 2026Power ComEd files a transmission service agreement with Karis Critical at FERC State agency · May 2026
- July 22, 2026Power Requested effective date for the transmission agreement State agency · May 2026
- Q1 2029Power First energization expected (developer) Company · Nov. 2025
Who is involved
Owners, partners and builders
Owners
- Karis Critical, LLC: developer
Power partners
- Commonwealth Edison Company (ComEd): serving utility
Decision-makers
- FERC: transmission agreement
Still unknown
Open questions
- Local zoning and site plan.
- Tenant.
- Whether FERC accepted the transmission agreement.
Where this comes from
26 records from 6 documents
Drawn from company statements, state agency records, public and commercial datasets and news reports, each kept with its date and source. The bar shows documents by type.
Company 3State agency 1Dataset 1News report 1
Evidence
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (6)
- Utility service: 504 MW“504 MW of utility power secured via ComEd, with first energization expected in Q1 2029”Company · Nov. 2025 · grade B
- Construction stage: pre-construction - land/listing stage; no construction reported; first energization expected Q1 2029“504 MW of utility power secured via ComEd, with first energization expected in Q1 2029”Company · Nov. 2025 · grade B
- Utility: ComEd (new dedicated substation planned)“ComEd has confirmed up to 504 MW deliverable via a new dedicated substation”Company · Nov. 2025 · grade B
- Announced: Nov. 2025“504 MW of utility power secured via ComEd, with first energization expected in Q1 2029”Company · Nov. 2025 · grade B
- Karis targets 300-500 MW of on-site gas generation (targeted late 2027), scaling total site capacity beyond 800 MW - prospective only, no permit found“onsite gas "300-500 MW" targeted late 2027, "scaling total site capacity beyond 800 MW over time"”Company · Nov. 2025 · grade B
- The Illinois Attorney General's FERC protests independently described the Karis Critical project as one that could grow to roughly 500 MW (via Utility Dive) - consistent with the 504 MW DeKalb figure and with mapping the“the Illinois AG’s FERC protests described the Karis Critical project as one that could "grow to roughly 500 MW" (Utility Dive)”News report · Oct. 2026 · grade C
Money and contracts (3)
- Tenant status: none found - developer markets powered land/campus; no tenant named“Karis Critical describes itself as an investor in land, energy, and infrastructure for data centers”Company · Oct. 2026 · grade B
- Transmission Service Agreement (TSA): transmission service filing TSA filed under FPA section 205(d)“§ 205(d) Rate Filing: Filing of TSA betwen ComEd and Karis Critical to be effective 7/22/2026. Filed Date: 5/22/26. Accession Number: 20260522-5122. Docket Numbers: ER26-2615-000”State agency · May 2026 · grade B
- Transmission Service Agreement (TSA): effective date July 22, 2026“Filing of TSA betwen ComEd and Karis Critical to be effective 7/22/2026”State agency · May 2026 · grade B
Site and other (5)
- Campus name: Karis Critical DeKalb Hyperscale Campus“Karis's own marketing teaser (Nov 2025, 'DeKalb, IL Hyperscale Data Center Campus')”Company · Oct. 2026 · grade B
- Developer: Karis Critical, LLC“Karis Critical's hyperscale site is DeKalb, IL”Company · Oct. 2026 · grade B
- County code: 17037Measured on OpenStreetMap map data.
- ComEd's ICC-approved KARE 345 kV project (Keslinger Rd / Crego Rd, Afton Township) is the transmission build for the south-DeKalb cluster's load growth (Meta / Edged / Karis) - context only, not a campus instrument“ComEd's ICC-approved KARE 345 kV project (Keslinger Rd / Crego Rd, Afton Township) is the transmission build for this cluster's load growth”Company · Oct. 2026 · grade B
- Site acres: 250 acres“250-acre hyperscale data center campus in DeKalb, IL (expansion land possible) - adjacent to Meta’s existing data center”Company · Nov. 2025 · grade B