Data center profile · 11th Street and the Creek Turnpike, Fair Oaks industrial park, east Tulsa (Wagoner County portion), Oklahoma

Meta Tulsa (Project Anthem)

Meta's first Oklahoma data center, $1 billion-plus, 2 million-plus sq ft, on 340 acres in Tulsa, broke ground April 2026, due 2028; second phase withdrawn.

Groundbreaking announced; site work not confirmed. Meta broke ground on Phase 1 on Apr. 21, 2026, with operation expected in 2028; the developer withdrew its Phase 2 rezoning on Apr. 1. Power comes from PSO, but no campus MW or state-reviewed service agreement is public.
2M+ sq ft
data center planned; groundbreaking announced Apr. 2026
Fair Oaks industrial park (city economic development agency)
$1B+
investment Meta cites
up from $800M in the 2024 city plan
340 acres
Phase 1 parcel
a 375-acre Phase 2 rezoning was withdrawn (press)
2028
expected operation
per April 2026 groundbreaking reporting
OperatorMeta Platforms; Atmoss LLC is the developer and owner of record
CustomerMeta (own use)
First building in serviceOur estimate: 2029 or later (no dated power path yet); company says 2028.
Next deadline2028: Phase 1 expected to be operational
Power

Power and the grid

Sources on record, size not disclosed

Getting on the grid

Permits

Permits checklist

1 withdrawn · 1 moratorium · 1 granted · 1 checked, nothing on file

City actions on record.

Risks

What could slow it down

Money

Money on record

$1B+
investment (Meta, 2026)
the 2024 plan said $800M Local government · April 2026
$800M
investment in the 2024 city project plan
before Meta was named Local government · May 2024
85%
property tax exemption on new investment
up to 25 fiscal years Local government · May 2024
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Jan. 22, 2024
    Money City project plan proposes an 85% tax exemption for 'Project Anthem' on about 340 acres Local government · Jan. 2024
  2. May 1, 2024
    Money City Council creates the incentive district for the $800M project Local government · May 2024
  3. March 25, 2026
    Permits Council unanimously pauses new data centers for nine months; this campus is exempt News report · March 2026
  4. April 1, 2026
    Permits Atmoss withdraws its Phase 2 rezoning for about 375 acres News report · April 2026
  5. April 21, 2026
    Construction Meta breaks ground on Phase 1; protesters gather outside the event News report · April 2026
  6. July 1, 2026
    Power State ratepayer-protection law takes effect for loads of 75 MW or more News report · July 2026
  7. 2028
    Construction Phase 1 expected to be operational Local government · April 2026
The buildings

Specs

100 jobs operational, with more than 1,000 at construction peak (company claim). Local government · April 2026

Who is involved

Owners, partners and builders

Owners
  • Meta Platforms: owner and operator
  • Atmoss LLC: developer and owner of record
Builders
  • Fortis Construction: general contractor
Decision-makers
  • Tulsa City Council
  • Tulsa Metropolitan Area Planning Commission
  • PartnerTulsa: city economic development agency
Power partners
  • Public Service Company of Oklahoma (PSO)
Still unknown

Open questions

Where this comes from

41 records from 14 documents

Drawn from news reports, local government records, state agency records and utility regulator dockets, each kept with its date and source. The bar shows documents by type.

News report 9Local government 4State agency 1Utility regulator 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (6)
  • Utility: Public Service Company of Oklahoma (PSO); Meta planned its energy needs with PSO years ahead of the campus coming online and will pay, through its utility bills, hundreds of millions of dollars toward grid infra
    “Meta worked closely with the Public Service Company of Oklahoma to plan for and meet its energy needs years in advance of the data center coming online.”
  • No campus MW is disclosed in any source found
    “Meta currently has projects under contract that are adding over 1,500 megawatts of clean energy to the grid in Oklahoma.”
  • Oklahoma HB 2992 (Data Center Consumer Ratepayer Protection Act of 2026), signed May 11, 2026 and effective Jul 1, 2026, is the statutory framework governing this campus's eventual PSO agreement: large-load customers at
    “requires large-load customers that add 75 MW or more of demand to sign long-term agreements covering infrastructure costs tied to their projects, rather than spreading those costs across the general rate base”
  • Utility: Public Service Company of Oklahoma (PSO) - inferred from Meta's PSO programme references and a PSO easement/right-of-way on the final plat; no PSO service agreement document was located
    “it said it is adding more than 1,500 megawatts of clean energy to Oklahoma's grid and will contribute to PSO's Light a Life Program to assist customers struggling to pay energy bills.”
  • Meta's 'more than 1,500 megawatts of clean energy' / '1.5 GW of clean energy to the grid in Oklahoma' is a statewide generation-addition commitment, NOT this campus's load; no campus MW on any named basis was found, so n
    “In total, Meta will add 1.5GW of clean energy to the grid in Oklahoma.”
  • The 'more than 1,500 MW of clean energy' figure attached to the Tulsa announcement is Meta's Oklahoma-wide portfolio under contract to match its electricity use - a statewide matching commitment, NOT this campus's load o
    “All electricity used by the facility will be matched with clean energy sources, adding more than 1,500 megawatts of clean power to Oklahoma's grid”
Money and contracts (3)
  • Project status: under construction - Phase 1 ground broken Apr 21, 2026; Phase 2 rezoning application withdrawn in 2026; operational target 2028
    “Today, local and state leaders joined Meta to break ground on the company's newest data center in Tulsa, representing an investment of more than $1 billion”
  • tax incentive district: ad valorem exemption 85 percent
    “The proposed Ordinance would make the City of Tulsa an Incentive District with a tax exemption of 85%.”
  • Gross floor area: 2000000 sq ft
    “Gross Floor Area: more than 2 million square feet”
Permits and government (6)
  • Tulsa City Council:
    “The proposed Ordinance would make the City of Tulsa an Incentive District with a tax exemption of 85%.”
  • Framework record, not a campus case. HB 2992 (Data Center Consumer Ratepayer Pro: PSO large-load tariff filed with the OCC under HB 2992 - joint stipulation proposing three service options for customers with contract dem
    “three service options within a new largeload tariff applicable to eligible customers with contract demand exceeding 75 MW”
  • Project status: Phase 1 UNDER CONSTRUCTION (groundbreaking Apr 21, 2026; operational 2028 expected); Phase 2 rezoning WITHDRAWN by the developer on Apr 1, 2026
    “Meta has broken ground on its first data center in Oklahoma, starting work on a campus in Tulsa.”
  • Atmoss withdrew its Phase 2 rezoning for approximately 375 acres between East 11: Phase 2 rezoning application (~375 acres) WITHDRAWN by applicant
    “Developer Atmoss LLC yesterday withdrew its plans to build the second phase of a more than 500-acre data center called 'Project Anthem' in Tulsa, Oklahoma.”
  • Tulsa City Council:
    “Tulsa City Council voted unanimously Wednesday to pause building new data centers for nine months.”
  • Tulsa City Council approved a temporary nine-month data center moratorium that exempted Project Anthem phases 1 and 2; Atmoss nevertheless withdrew its Phase 2 rezoning application for about 375 acres east of South 193rd
    “Although the Tulsa City Council approved a temporary nine-month data center moratorium last week, the moratorium exempted the first and second phases of Project Anthem”
Legal (1)
  • Resident opposition on environment, energy and water use and property values, and moratorium pressure; no lawsuit naming Atmoss or Project Anthem was located
    “Residents expressing opposition to new data center projects in Tulsa frequently cite concerns about their impact on the local environment, energy and water usage, and their effect on local property values.”
Site and other (6)
  • Developer: Atmoss LLC (developer of record, owner of record on the final plat); Meta Platforms (owner-operator, confirmed 2026)
    “ATMOSS, LLC, A DELAWARE OWNER OF RECORD:”
  • County code: 40145
    “IN THE CITY OF TULSA, WAGONER COUNTY, STATE OF OKLAHOMA PART OF SECTION 8, T-19-N, R-15-E”
  • Meta / PartnerTulsa claim more than 1,000 construction jobs at peak and approximately 100 operational jobs once completed - company/economic-development claims, up from the 50 permanent employees projected in the 2024 pl
    “The Tulsa Data Center is expected to support more than 1,000 construction jobs at peak and create approximately 100 operational jobs once completed.”
  • Residents protested the Meta announcement in east Tulsa on Apr 21, 2026, citing water, energy and community impacts; the Tulsa Chamber account notes protesters outside the announcement event
    “Addressing the data center protesters outside the building, Demasi noted that Meta would be good stewards for the environment.”
  • Project identity: Meta Tulsa Campus - 'Project Anthem', 340-acre parcel at 11th Street and the west side of the Creek Turnpike, City of Tulsa (east Tulsa); final plat places the site in Wagoner County
    “It is set for a 340-acre parcel at the intersection of 11th Street and the west side of the Creek Turnpike.”
  • Closed-loop liquid cooling; Meta aims to use zero water for the majority of the year
    “The facility will use a closed-loop liquid cooling system, and aims to use zero water for the majority of the year.”