Permits
Permits checklist
1 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- –Checked, nothing on file: Zoning and site approvals
Risks
Why it stopped, what could revive it
- HighProposal cancelledThe proposal was cancelled in October 2025 and no construction ever started.
- WatchNo power planNo megawatt figure or utility service request was ever published.
Power
Power and the grid
Not used, not on record, or dropped
- We Energies grid (utility territory) None on recordthe site lies in We Energies territory in MISO; no service request or megawatt figure was published
Timeline
What happened, and what is due
SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
- 2025Site The proposal surfaces publicly after an initially confidential process
- Oct. 2025Site Microsoft cancels the Caledonia proposal
Who is involved
Owners, partners and builders
Owners
- Microsoft: proposed owner-operator
Still unknown
Open questions
- The planned size in MW and the reasons Microsoft cancelled.
- Whether the land stays available for another project.
- 1 unconfirmed county land record near the site: the buyer or location could not be tied to this campus.
Where this comes from
1 records from 1 documents
Drawn from news reports, each kept with its date and source. The bar shows documents by type.
News report 1
Evidence
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Site and other (1)
- Announced: July 28, 2025“Rich Brittingham, a vice president at Dewberry, on Monday presented plans before the village of Caledonia Plan Commission.”News report · July 2025 · grade C