Power and the grid
2,670 MW contracted
- Texas grid (ERCOT) Not usednone: the plant runs behind the meter and does not join the grid queue News report · 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Oct. 2025Air permit application filedEnergy Forge One applies to the state air regulator for the Kilby Power Plant, listed at about 2,595 MW (press). News report · Oct. 2025
- April 2026Exclusivity agreement with MicrosoftChevron and Engine No. 1 sign an exclusivity agreement setting terms for a future power deal (press). News report · April 2026
- June 10, 2026Preliminary decision on air permitsThe state air regulator issues its notice of application and preliminary decision and schedules a public meeting. see Permits
- June 22, 202620-year power purchase agreementEnergy Forge One signs to supply dedicated power to the Microsoft data center. News report · June 2026
- Not setFinal investment decision: pendingChevron targets the end of 2026; an executive told Semafor it could slip to 2027 (press). News report · Oct. 2026
- The plant is designed to run behind the meter and does not join the Texas grid's interconnection queue. News report · 2026
- No state utility commission docket exists: supply is a private power purchase agreement, not regulated utility service. News report · Oct. 2026
- Coverage has not settled whether the governor's Sept. 2026 pause on data-center permits covers a behind-the-meter plant. News report · Sept. 2026
On-site generation on file
- Generating units on the permit: 2 units Dataset · Oct. 2026
- Generating units on the permit: 3 units Dataset · Oct. 2026
- Generating units on the permit: 12 units Dataset · Oct. 2026
+2 more
- Generating units on the permit: 29 units Dataset · Oct. 2026
- Generator maker and model: GE Vernova 7HA.02 (CC1-CC2, GT1-3); Solar Turbines T350 (GT4-15); Solar Turbines T130 (GT16-44) Dataset · Oct. 2026
Permits checklist
1 pending · 1 checked, nothing on file
Approvals the power plant and campus need, and what we found.
- ◷Air permits for the Kilby Power Plant (state, PSD and greenhouse gas) PendingTexas Commission on Environmental Quality · June 10, 2026: preliminary decision issued; final issuance subject to the Sept. 2026 state pause State agency · June 2026
- –Checked, nothing on file: Grid interconnection
What could slow it down
- HighNo investment decision yetChevron has not committed to build; an executive said the decision could slip from 2026 to 2027 (press). News report · Oct. 2026
- HighState permit pauseThe governor's Sept. 21, 2026 directive suspends data-center permits, and the plant's air permits are only at a preliminary decision. News report · Sept. 2026
- MediumCampus load never statedNo source gives an IT or utility load; the only figures are the plant's 2.67 GW and Microsoft's roughly 2 GW claim. Company · June 2026
Money on record
- Pending: Chevron final investment decision (expected by end of 2026; could slip to 2027 (press)) News report · Oct. 2026
What happened, and what is due
- Jan. 28, 2025Power Chevron, Engine No. 1 and GE Vernova announce a gas 'power foundries' program built on seven reserved 7HA turbines; Kilby later grows out of it Company · Jan. 2025
- March 4, 2025Paper trail Energy Forge One LLC registered in Delaware and Texas
- Oct. 2025Permits Air permit application filed for the Kilby Power Plant at about 2,595 MW (press) News report · Oct. 2025
- April 2026Power Partners sign an exclusivity agreement with Microsoft (press) News report · April 2026
- June 10, 2026Permits State air regulator issues a preliminary decision on the plant's permits State agency · June 2026
- June 22, 2026Power 20-year power purchase agreement with Microsoft announced; the project is named Kilby News report · June 2026
- June 23, 2026Site Microsoft says the campus will add roughly 2 GW of data-center capacity over five to seven years (press) News report · June 2026
- Sept. 21, 2026Permits Governor directs the state air regulator to suspend data-center permits News report · Sept. 2026
- Oct. 13, 2026Money A Chevron executive says the investment decision could slip to 2027 (press) News report · Oct. 2026
- Dec. 2026Money Target for Chevron's final investment decision Company · June 2026
- 2028Power Target for first power to the campus Company · June 2026
Specs
- Brackish groundwater: planned for power-plant operations instead of fresh water (company) Company · June 2026
Owners, partners and builders
- Energy Forge One LLC: Chevron subsidiary developing the plant and selling the power
- Chevron Corporation: parent company
- Engine No. 1 and its energy venture Joulent: development partner with an option on a 50% stake
- Microsoft: builds and operates the campus and buys the power
- GE Vernova: large turbines for most of the generation
- Solar Turbines (Caterpillar): additional generation
- Texas Commission on Environmental Quality: air permits
Open questions
- IT or utility load in MW (only plant generation and Microsoft's 2 GW claim are published).
- Whether Chevron's investment decision lands on schedule.
- Whether the state permit pause applies to a behind-the-meter plant.
53 records from 15 documents
Drawn from news reports, state agency records, company statements, business registries and public and commercial datasets, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (15)
- Generating units on the permit: 2 units“CC1 | Pre-construction | fossil gas: natural gas | 555.7145 | combined cycle | 2028 (planned) | GE Vernova: 7HA.02 | no”Dataset · Oct. 2026 · grade B
- Generating units on the permit: 3 units“GT1-3 | Pre-construction | fossil gas: natural gas | gas turbine | 2029 (planned) | GE Vernova: 7HA.02 | no”Dataset · Oct. 2026 · grade B
- Generating units on the permit: 12 units“GT4-15 | Pre-construction | fossil gas: natural gas | 373.25 | gas turbine | 2028 (planned) | Solar Turbines: T350 | no”Dataset · Oct. 2026 · grade B
- Generating units on the permit: 29 units“GT16-44 | Pre-construction | fossil gas: natural gas | 392.955 | gas turbine | 2028 (planned) | Solar Turbines: T130 | no”Dataset · Oct. 2026 · grade B
- Generator maker and model: GE Vernova 7HA.02 (CC1-CC2, GT1-3); Solar Turbines T350 (GT4-15); Solar Turbines T130 (GT16-44)“GT4-15 | Pre-construction | fossil gas: natural gas | 373.25 | gas turbine | 2028 (planned) | Solar Turbines: T350 | no”Dataset · Oct. 2026 · grade B
- On-site generation: 2,670 MW“Kilby is expected to deliver approximately 2.67 gigawatts of capacity, built through a phased, modular approach that enables incremental expansion over time.”Company · June 2026 · grade B
- First power delivery anticipated in 2028, after a final investment decision expected by the end of 2026“First power delivery is anticipated in 2028.”Company · June 2026 · grade B
- Kilby is designed to deliver dispatchable electricity directly to Microsoft while mitigating impacts on the regional grid (behind-the-meter, not an ERCOT-interconnected load)“By co-locating new, large-scale power generation with the data center, Kilby is designed to deliver reliable, dispatchable electricity directly to Microsoft”Company · June 2026 · grade B
- Plant operations plan to use non-potable brackish groundwater instead of freshwater, with work on reusing produced water from oil and gas operations“In lieu of freshwater, Kilby plans to use non-potable, brackish groundwater sources for power plant operations.”Company · June 2026 · grade B
- County: Reeves County, TX (48389)“The proposed Power Plant (Kilby site) is located near Pecos, Reeves County, Texas”State agency · June 2026 · grade B
- Chevron targets FID by end of 2026 and first power in 2028; a Chevron executive told Semafor the FID could slip to 2027 amid the Texas permit calendar.“A Chevron executive told Semafor the FID could slip to 2027”News report · Oct. 2026 · grade C
- Generation equipment: GE Vernova 7HA turbines for most capacity, supplemented by Solar Turbines (Caterpillar) units; seven 7HA units reported in project coverage. Equipment counts are not converted to MW in this lane.“Project Kilby: Chevron's 20-year power agreement with Microsoft for about 2.67 GW of behind-the-meter gas generation in West Texas, with GE Vernova and Solar Turbines equipment”News report · Oct. 2026 · grade C
- Project identity: Project Kilby - Microsoft data center campus co-located with a Chevron (Energy Forge One LLC) behind-the-meter natural gas power plant near Pecos, Reeves County, TX; more than 2,000 acres; 20-year power“The development, called Project Kilby, will combine a Microsoft-operated data center with a co-located natural gas power plant developed by Chevron subsidiary Energy Forge One and investment firm Engine No. 1.”News report · June 2026 · grade C
- Stated campus size: 2,000 MW“Microsoft said the campus will add roughly 2 GW of data center capacity over the next five to seven years to support AI and cloud workloads.”News report · June 2026 · grade C
- The plant is engineered to run 100% behind the meter with no ERCOT interconnection, bypassing the grid queue“The plant runs independently of the Texas grid. It does not join the ERCOT interconnection queue”News report · 2026 · grade C
Money and contracts (5)
- Source record“This agreement represents an important milestone toward Chevron's Final Investment Decision (FID), which is expected by the end of 2026, subject to the completion of other necessary conditions.”Company · June 2026 · grade B
- Chevron expects Kilby to generate more than $10 billion in state and local tax revenue and support almost 2,000 jobs“Kilby is expected to generate significant economic benefits for the region, including more than $10 billion in state and local tax revenue, support almost 2,000 jobs”Company · June 2026 · grade B
- Microsoft expects more than 6,000 construction jobs at full buildout; a reported project value of around $7 billion circulates in coverage but is an estimate, not a Chevron-confirmed figure“The development is expected to create more than 6,000 construction jobs and hundreds of permanent operational positions.”News report · June 2026 · grade C
- power purchase agreement: term and capacity 2,670 MW“On 22 June 2026 Chevron announced that its subsidiary Energy Forge One LLC had signed a 20 year power purchase agreement with Microsoft for a co located power facility in West Texas”News report · June 2026 · grade C
- exclusivity agreement: exclusivity“in April, the partners signed an 'exclusivity agreement' with Microsoft, setting the parameters for a future energy supply deal.”News report · April 2026 · grade C
Permits and government (3)
- TCEQ issued a Notice of Application and Preliminary Decision for proposed State : notice of application and preliminary decision (NAPD); public meeting notice“has applied to the Texas Commission on Environmental Quality (TCEQ) for issuance of proposed State Air Quality Permit 181895, issuance of Prevention of Significant Deterioration (PSD) Air Quality Permit PSDTX1684”State agency · June 2026 · grade B
- The Governor's Sep 21, 2026 directive suspends TCEQ issuance of data center project permits pending the ERCOT audit; Kilby's permits are at preliminary-decision stage, so final issuance is gated by the pause. Whether a b“on September 21, 2026, Governor Abbott issued a letter instructing the TCEQ to suspend the issuance of all permits sought by data centers (or related to data center projects)”News report · Sept. 2026 · grade C
- Energy Forge One LLC filed a TCEQ air permit application for the Kilby Power Pla: air permit application filed“Chevron's subsidiary Energy Forge One had filed an air-permit application with Texas regulators (the TCEQ) for the plant — listed there at about 2,595 MW”News report · Oct. 2025 · grade C
Site and other (1)
- County code: 48389“The project, named Project Kilby, sits on more than 2,000 acres in Reeves County near the city of Pecos, deep in the Permian Basin.”News report · Oct. 2026 · grade C