Data center profile · Williston area, Williams County, North Dakota (no parcel or address published)

Nakota AI Campus

Proposed 1 GW gas-powered campus on 620 optioned acres near Williston, North Dakota; 100 MW offtake announced for India's Yotta; no permits or closed financing.

Announced only. Nixxy ended its binding deal with developer Tachyon9 on July 30, 2026 and says it is negotiating directly with the project's developer; no definitive agreement filed. The Yotta offtake was announced as executed June 22, 2026; later status unknown.
1 GW
campus power, developer says
on-site gas generation; the sponsor uses the same 1 GW for compute and gives the first phase as 120 or 150 MW
620 acres
held under option
land is not owned
~$156M
annual revenue claimed on the 100 MW offtake
sponsor claim; announced June 22, 2026
$310,000
only financing closed
a Nixxy stock sale; the $5B GPU financing partner was never named
OperatorTachyon9 (developer); Nixxy (sponsor, Nasdaq: NIXX)
CustomerNidar Infrastructure / Yotta Data Services (100 MW offtake, announced)
Planned IT capacity800 MW at full build-out (our estimate from the company's 1 GW campus power figure)
First building in serviceOur estimate: 2029 or later (no dated power path yet); company says 2027.
Next stepA definitive deal between Nixxy and the developer; none announced as of Oct. 18, 2026
Power

Power and the grid

None energized or contracted yet

On-site natural gas turbines (hydrogen-capable)Proposed
1,000 MW
stated generation; no turbine order, gas supply or permit filing Company · July 2026
Proposed

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. June 22, 2026
    Behind-the-meter plan
    Sponsors describe self-generation with no grid interconnection. Company · June 2026
  2. As of Oct. 2026
    No grid or gas paperwork
    No utility agreement, no regional grid queue position and no gas supplier is named in any source. Company · Oct. 2026
Permits

Permits checklist

4 checked, nothing on file

Nothing has been filed with any state, county or city office, as far as our searches show.

Risks

What could slow it down

Money

Money on record

$1B
planned investment
sponsor figure Company · June 2026
$5B
GPU financing memo, claimed
counterparty never named Company · June 2026
$75M
planned private placement
tied to the merger deal that has ended SEC filing · June 2026
$330K
Nixxy cash, June 30, 2026
going-concern doubt; $115.6M accumulated deficit SEC filing · Aug. 2026
~$1B
planned infrastructure investment, sponsor figure
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Jan. 28, 2026
    Paper trail Tachyon9 signs a joint venture with Robo.ai for a 20 MW project in Asia and the Middle East; no Tachyon9 project is documented as completed Company · Jan. 2026
  2. June 9, 2026
    Site Nixxy and Tachyon9 announce a binding letter of intent and the 1 GW, $1B Nakota campus Company · June 2026
  3. June 15, 2026
    Money An amended binding letter of intent is filed with the SEC, with a 30-day exclusivity period SEC filing · June 2026
  4. June 22, 2026
    Money Offtake with Nidar/Yotta announced as executed for the first 100 MW Company · June 2026
  5. July 2, 2026
    Site Sponsors publish design claims; Nixxy's CEO steps down the same day Company · July 2026
  6. July 30, 2026
    Money Nixxy ends its binding deal with Tachyon9; the separate Yotta offtake is not mentioned SEC filing · July 2026
  7. Aug. 12, 2026
    Money Nixxy's quarterly report raises going-concern doubt and does not mention Nakota SEC filing · Aug. 2026
Construction activity

Since June 2025: 1 satellite capture.

The buildings

Specs

120 to 150 MW
first phase, targeted Q2 2027; the same release gives both numbers
15 years
term of the announced Yotta offtake
Who is involved

Owners, partners and builders

Developer and sponsor
  • Tachyon9 Corporation: developer, led by Shahal Khan
  • Nixxy, Inc.: Nasdaq sponsor, CEO David Kratochvil
Customer
  • Nidar Infrastructure and Yotta Data Services: announced offtaker, backed by India's Hiranandani Group
Decision-makers
  • North Dakota Public Service Commission: siting certificate
  • North Dakota DEQ: air permit
  • Williams County and City of Williston: land use
Other
  • Robo.ai: joint venture partner of Tachyon9 on a separate project
Still unknown

Open questions

Where this comes from

157 records from 29 documents

Drawn from company statements, securities filings, news reports, utility regulator dockets, public and commercial datasets, local government records and satellite captures, each kept with its date and source. The bar shows documents by type.

Company 11SEC filing 9News report 5Utility regulator 2Dataset 2Local government 1Satellite 0
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (22)
  • Interconnection status: none - behind-the-meter by design, no grid position: the campus is designed around on-site BTM generation (Baker Hughes hydrogen-capable turbines on natural gas) with no grid interconnection filin
    “On July 30, 2026, Nixxy, Inc. (the Company) terminated the binding Letter of Intent (the Binding Letter of Intent) with Tachyon 9 Corporation, a Delaware corporation, dated as of June 15, 2026”
  • Stated campus size: 1,000 MW
    “designed to deliver up to 1 gigawatt (GW) of capacity over an anticipated 36-month buildout period, with the first 150 megawatts (MW) expected to be operational by the second quarter of 2027”
  • Phase plan inconsistency: First phase stated as both 120 MW and 150 MW (Q2 2027) within the same June 9, 2026 release; build in 120 MW increments over 24 months per the release body vs a 36-month buildout in its bullet
    “Total compute power will be built in 120mw increments over a period of 24 months”
  • Grid context: Williams County sits in the SPP footprint; Mountrail-Williams Electric Cooperative is the local distribution co-op (Basin Electric member)
    “Class C Member Mountrail-Williams Electric Cooperative, which serve members in northwestern North Dakota within the Williston Basin”
  • IT capacity: not stated
    “Documented absence: no IT-load (critical load) figure is stated in any sponsor release or filing”
  • Utility: None - no utility service agreement; no Mountrail-Williams Electric Cooperative agreement found or claimed
    “up to 1 GW of independent, behind-the-meter power”
  • Grid operator: None - no ISO/RTO interconnection, ESA, or queue position found
    “up to 1 GW of independent, behind-the-meter power”
  • Gas supply: No gas supplier, pipeline lateral, or supply agreement named in any source
    “abundant natural gas supply in North Dakota and other states connected to the Northern Midwest Gas supply pipelines”
  • As of this pass, nixxy.com still presents the Tachyon9 agreement and the Nakota 1 GW campus (initial 120 MW phase) as current - about 11 weeks after the LOI expired.
    “NIXXY has entered into an agreement with Tachyon9 to create a Nasdaq-listed AI hyperscale infrastructure and energy platform”
  • Generation technology: Hydrogen-capable Baker Hughes turbines burning hydrogen-rich blends from natural gas, incl. gas that would otherwise be flared; pre-combustion decarbonization / CCS optionality claimed
    “integrating behind-the-meter generation, hydrogen-capable Baker Hughes turbine technology, pre-combustion decarbonization optionality and advanced closed-loop liquid cooling”
  • Nixxy CEO Mike Schmidt stepped down; Chairman David Kratochvil became Chairman and CEO; Simon Kearney joined the board - mid-way through the LOI's life.
    “Mr. Kratochvil will succeed Mr. Mike Schmidt, who stepped down to pursue other opportunities”
  • Nakota design release: Baker Hughes hydrogen-capable turbines, hydrogen-rich blends from otherwise-flared gas, closed-loop liquid cooling, claimed qualification under the Fourth State Initiative / Section 45V - all spons
    “the campus under the U.S. Government's Fourth State Initiative (FSI) under Section 45V, the Clean Hydrogen”
  • Site acres: 620 acres
    “Located on approximately 620 acres in North Dakota’s energy corridor, the campus is expected to benefit from abundant natural gas resources”
  • Phase 1 target: first 120-150 MW of compute capacity targeted for Q2 2027, subject to financing, regulatory approvals, and completion of the Nixxy-Tachyon 9 transaction
    “The first 120–150 megawatts of computing capacity are targeted to become operational in the second quarter of 2027, subject to financing, regulatory approvals”
  • On-site generation: 1,000 MW
    “the Nakota Data Campus is designed to deliver up to 1 GW of independent, behind-the-meter power”
  • Power plan: Behind-the-meter self-generation (natural gas); no grid interconnection
    “designed to deliver up to 1 GW of independent, behind-the-meter power”
  • Site acreage: 620 acres
    “certain rights and opportunities relating to a proposed 620-acre hyperscale development campus in North Dakota targeting up to approximately 1 gigawatt of power capacity”
  • Stated campus size: 1,000 MW
    “designed to deliver up to 1 gigawatt (GW) of capacity over an anticipated 36-month buildout period”
  • Stated campus size: 120 MW
    “the first 120mw of compute power are planned to be operational by 2nd quarter of 2027”
  • IT capacity: 120 MW
    “First 120 megawatts (MW) of compute capacity targeted to be operational during the second quarter of 2027”
  • Tachyon9 signed a definitive JV with Robo.ai's subsidiary (first project: 20 MW in APAC/MENA) - its only other documented data-center agreement. No completed Tachyon9 project is documented in any source.
    “has entered into a definitive Joint Venture agreement with Tachyon9 Corporation (Tachyon9), a U.S.-based advanced data center infrastructure provider”
  • Burkhan Capital LLC-led consortium committed $300M to Robo.ai - Shahal Khan's Burkhan platform links the Tachyon9 chairman to Robo.ai months before their data-center JV.
    “Shahal Khan, Founder and CEO of Burkhan Capital LLC”
Money and contracts (43)
  • Sponsor structure status: Nixxy-Tachyon9 binding LOI terminated July 30, 2026; Nixxy negotiating directly with the Nakota developer (unnamed in the filings) to acquire the entire project - no definitive agreement filed
    “The Company terminated the Binding Letter of Intent to pursue other potential business opportunities. The Company did not incur any early termination penalties in connection with the termination of the Binding Letter of Intent”
  • Project status: announced only - the Nixxy / Tachyon 9 binding LOI was TERMINATED Jul 30, 2026 (Nixxy 8-K Item 1.02, filed Jul 31, 2026); Nixxy is negotiating directly with the unnamed Nakota project developer to procure
    “On July 30, 2026, Nixxy, Inc. (the Company) terminated the binding Letter of Intent (the Binding Letter of Intent) with Tachyon 9 Corporation, a Delaware corporation, dated as of June 15, 2026”
  • Transaction status: LOI terminated Jul 30, 2026 - no closing pending. Successor path: direct Nixxy-developer negotiation; no definitive agreement filed as of Oct 18, 2026
    “On July 30, 2026, Nixxy, Inc. (the Company) terminated the binding Letter of Intent (the Binding Letter of Intent) with Tachyon 9 Corporation, a Delaware corporation, dated as of June 15, 2026”
  • Sponsor structure status: Nixxy states it is in negotiations directly with the developer of the Nakota project to procure the property and fund permits, and is working on a definitive agreement to acquire the entire proj
    “it is currently in negotiations directly with the developer of the Nakota project to procure the Nakota property and provide all funds required to obtain the necessary permits and approvals to advance the project”
  • Tenant status: Offtake agreement announced as executed June 22, 2026 for the initial 100 MW (~$156M claimed annual revenue); no lease, construction, or deliveries; status after the July 30, 2026 LOI expiration is addressed by
    “The agreement provides for approximately $156 million in annual recurring revenue from the initial 100 MW phase”
  • Stage: Announced only - paper project: optioned land, expired sponsor LOI, announced offtake, no permits, no closed financing, no construction
    “the previously disclosed Letter of Intent relating to the proposed Tachyon9 transaction has concluded upon its expiration”
  • Through this date: the $5B GPU-financing MoU counterparty was never named, and no PIPE closing, turbine order, gas supply agreement, or permit filing for Nakota has been announced in any source.
    “Planned Investment on phase 1 of $5 billion in GPU financing through a major offtake partner, with MoU already executed”
  • Sponsor credit: Nixxy 10-Q (Q2 2026): going-concern substantial doubt; cash $330K and working-capital deficit ~$1.5M at June 30, 2026; accumulated deficit $115.6M
    “management has evaluated whether there is substantial doubt about the Company's ability to continue as a going concern and has determined that substantial doubt existed”
  • Nixxy's Q2 2026 10-Q (period ended June 30, 2026, filed Aug. 12, 2026) contains no mention of Nakota, Tachyon, or any letter of intent, and its subsequent-events note (through Aug. 13, 2026) omits the July 30 LOI expiration.
    “The Company has evaluated subsequent events through August 13, 2026, the date the accompanying condensed consolidated financial statements were available to be issued”
  • 10-Q going-concern disclosure: substantial doubt; $330K cash and ~$1.5M working-capital deficit at June 30, 2026; $115.6M accumulated deficit; $1.4M cash used in operations in H1 2026.
    “the Company used cash of approximately $1.4 million in operations during the six months ended June 30, 2026, and has a working capital deficit of approximately $1.5 million”
  • Sponsor status: LOI expired July 30, 2026; Nixxy negotiating directly with the project developer; no definitive agreement announced as of Oct. 18, 2026
    “the previously disclosed Letter of Intent relating to the proposed Tachyon9 transaction has concluded upon its expiration”
  • business combination LOI: expiration
    “the previously disclosed Letter of Intent relating to the proposed Tachyon9 transaction has concluded upon its expiration”
  • The Tachyon9 LOI concluded upon its expiration. Nixxy pivoted to negotiating directly with the (unnamed) developer of the Nakota project to buy the property and fund permitting; no definitive agreement has been announced
    “currently in negotiations directly with the developer of the Nakota project to procure the Nakota property”
  • Site control: Land option rights only (held by Tachyon9); no purchase or closing documented
    “contributing approximately $64 million in equipment, land option rights for the Nakota project, and a signed LOI for the entire 1 GW development”
  • Target date first phase: 2027-Q2
    “The first 120-150 megawatts of computing capacity are targeted to become operational in the second quarter of 2027, subject to financing, regulatory approvals and completion of the proposed transaction”
  • Nixxy regained compliance with Nasdaq's minimum bid price rule (5550(a)(2)) - the stock had been below $1 during the LOI period (the June registered direct priced at $0.64).
    “received written notification from The Nasdaq Stock Market LLC confirming that the Company had regained compliance with Nasdaq Listing Rule 5550(a)(2)”
  • Tenant status: executed offtake - Nidar Infrastructure Limited (parent and majority shareholder of Yotta Data Services) EXECUTED an offtake agreement on Jun 22, 2026 covering the initial 100 MW phase (~$156M annual recur
    “Tachyon9 Corporation and Nixxy Inc. (NASDAQ: NIXX) today announced the execution of an offtake agreement with Nidar Infrastructure Limited, the parent company and majority shareholder of Yotta Data Services”
  • Tenants: Nidar Infrastructure Limited / Yotta Data Services
    “announced the execution of an offtake agreement with Nidar Infrastructure Limited, the parent company and majority shareholder of Yotta Data Services”
  • offtake agreement: scope / revenue 156000000 USD per year (claimed ARR, initial 100 MW)
    “The agreement provides for approximately $156 million in annual recurring revenue from the initial 100 MW phase”
  • offtake agreement: option - right of first offer
    “grants Nidar/Yotta a right of first offer on the remaining campus capacity”
  • memorandum of understanding: scope - predecessor to offtake
    “The offtake agreement reflects the commercial terms contemplated under the parties' previously announced Memorandum of Understanding”
  • Offtake announced as executed with Nidar Infrastructure / Yotta: ~$156M claimed annual revenue on the initial 100 MW, plus a right of first offer on remaining campus capacity.
    “announced the execution of an offtake agreement with Nidar Infrastructure Limited”
  • Contributed assets: Land option rights for the Nakota project plus approx $64M in equipment / infrastructure assets; planned $75M private placement
    “contributing approximately $64 million in equipment, land option rights for the Nakota project, and a signed LOI for the entire 1 GW development.”
  • Financing status: No closed financing. Unclosed plans: $75M PIPE (LOI-dependent); ~$1B planned infrastructure investment; $5B Phase 1 GPU financing MoU via unnamed partner. Only closed raise found: Nixxy $310,000 registe
    “Tachyon will seek to raise up to $75 million via a PIPE investment (the PIPE) in the form of five-year secured convertible promissory notes”
  • business combination LOI: scope
    “The Company will acquire 100% of the capital stock, or substantially all of the assets, of Tachyon”
  • business combination LOI: consideration / valuation 1000000000 USD (estimated Tachyon stock value)
    “Tachyon's capital stock for the Business Combination is estimated to be valued at approximately $1 billion, to be substantiated by an external valuation report”
  • business combination LOI: ownership split 90 % minimum fully diluted shares to Tachyon stockholders
    “Tachyon's stockholders are expected to hold at least 90% of the fully diluted shares of the combined company”
  • business combination LOI: conditions precedent
    “Completion of the Business Combination is subject to, among other things, approval of the Company's board of directors and stockholders, satisfaction of customary due diligence, approval by Nasdaq”
  • business combination LOI: condition - audited financials
    “availability of PCAOB-audited financial statements of Tachyon”
  • business combination LOI: exclusivity 30 days
    “The Binding Letter of Intent provides for a 30-day exclusivity period during which neither party will solicit or pursue alternative acquisition transactions”
  • business combination LOI: financing - PIPE 75000000 USD (up to)
    “Tachyon will seek to raise up to $75 million via a PIPE investment (the PIPE) in the form of five-year secured convertible promissory notes”
  • business combination LOI: termination consequence - PIPE notes
    “the PIPE Notes will automatically terminate and be deemed satisfied and discharged in full upon the PIPE holders' assumption of all of Tachyon's right, title and interest in and to such equipment”
  • business combination LOI: finding - no termination fee clause located
    “The Binding Letter of Intent is intended by the parties to be legally binding and enforceable in accordance with its terms”
  • registered direct offering: financing - closed equity sale 310000 USD gross proceeds
    “an aggregate of 484,375 shares of common stock at a purchase price of $0.64 per Share for aggregate gross proceeds to the Company of $310,000”
  • Amended and restated binding LOI executed and reported on Form 8-K (LOI filed as Ex. 10.1): 30-day exclusivity, up to $75M PIPE, closing conditioned on PCAOB-audited Tachyon financials and Nasdaq approval.
    “On June 15, 2026, Nixxy, Inc. (the Company) entered into an amended and restated binding Letter of Intent”
  • Planned investment: 1000000000 USD
    “Planned investment of approximately $1 billion into power and energy infrastructure supporting the 620 Acre Nakota Project”
  • GPU financing MoU: financing - claimed MoU 5000000000 USD (Phase 1, claimed)
    “Planned Investment on phase 1 of $5 billion in GPU financing through a major offtake partner, with MoU already executed”
  • Nixxy-Tachyon9 binding LOI announced: TACC combination, ~$1B claimed Tachyon valuation, ~$1B planned Nakota investment, $75M planned private placement.
    “announced that it has entered into a transformative and binding Letter of Intent (LOI) with Tachyon9 Corporation”
  • The only closed financing in the record: Nixxy sold 484,375 shares for $310,000 gross in a registered direct offering the same day the ~$1B campus LOI was announced.
    “for aggregate gross proceeds to the Company of $310,000, before deducting estimated offering expenses payable by the Company”
  • joint venture agreement: scope - developer track record (not Nakota) 20 MW (first JV project target, APAC/MENA)
    “The JV, which will be majority owned by Robo.ai, has established its first strategic initiative: the development of a 20 MW AI data center”
  • Land status: site held under land option rights contributed by Tachyon 9 to the proposed Nixxy combination; land not owned
    “Tachyon 9 is contributing approximately $64 million in equipment, land option rights for the Nakota project, and a signed letter of intent for the full 1GW development”
  • offtake agreement: term 15 years
    “The 15-year commitment is expected to contribute approximately $2.34 billion in revenue associated with the initial 100 MW deployment”
  • joint venture agreement: term / termination 10 years
    “The joint venture agreement has a term of 10 years, which can be renewed by written mutual consent or terminated by the board of directors of the joint venture”
Permits and government (12)
  • Nixxy terminated the binding Tachyon9 Letter of Intent on July 30, 2026 (8-K Item 1.02, no termination penalties) and announced it is negotiating directly with the Nakota project developer to procure the property, fund p
    “On July 30, 2026, Nixxy, Inc. (the Company) terminated the binding Letter of Intent (the Binding Letter of Intent) with Tachyon 9 Corporation, a Delaware corporation, dated as of June 15, 2026”
  • certificate of site compatibility: jurisdiction confirmed - process a ~1 GW Nakota plant would have to use
    “Basin Electric filed with the North Dakota Public Service Commission an application for a certificate of site compatibility (Application) for the Bison Generation Station (Project)”
  • certificate of site compatibility: no application found
    “On March 5, 2025, Basin Electric Power Cooperative (Basin Electric) filed with the North Dakota Public Service Commission (Commission) an application for a certificate of site compatibility (Application) for the Bison Generation Station (Project)”
  • air permit to construct: no application found
    “Take notice that the North Dakota Department of Environmental Quality (NDDEQ or the Department) proposes to issue an Air Pollution Control Permit to Construct to Applied Digital Corporation”
  • zoning / building permit: no action found
    “Planned investment of approximately $1 billion into power and energy infrastructure supporting the 620 Acre Nakota Project, in Williston, North Dakota”
  • air permit to construct: jurisdiction confirmed - notice system carries ND data-center generation permits
    “the North Dakota Department of Environmental Quality proposes to issue an Air Pollution Control Permit to Construct to Applied Digital Corporation for the construction of 192 emergency generators at the FAR Generation Plant”
  • land use / conditional use: no application found
    “Summary of formal actions taken at the meeting: consent agenda approved; LU-0063 and LU-0064 approved (LU-0064 with road-maintenance contingency)”
  • Williams County Board of County Commissioners: Regular meeting actions (land-use items LU-0063 and LU-0064 and routine business) - no Nakota / Tachyon9 item
    “consent agenda approved; LU-0063 and LU-0064 approved (LU-0064 with road-maintenance contingency)”
  • Williams County commissioners attended a general data-center information session in Tioga hosted by a state senator; no Nakota item has come before the county.
    “A quorum of the Williams County Board of County Commissioners may be present at the Data Center Info Session”
  • Williams County Board of County Commissioners: Data Center Info Session at Tioga Community Center (hosted by Sen. Mark Enget, District 2); commission quorum notice only - Nakota not mentioned
    “A quorum of the Williams County Board of County Commissioners may be present at the Data Center Info Session, to be held at the Tioga Community Center”
  • ND legislative AI and Data Center Committee hearing debated data-center costs and benefits; Williston's Atlas Power project was cited as the state's poor-engagement example. Nakota was not mentioned - no project-specific
    “He said Atlas Power in Williston ran into problems because it built a data center with shorter setbacks that exposed residents to constant noise”
  • North Dakota Legislative Assembly - Artificial Intelligence and Data Center Committee: Interim hearing on data-center costs and benefits; Atlas Power (Williston) cited as the state's poor-engagement example; Nakota not m
    “Mayo said North Dakota has experienced examples of good and bad development practices for data centers in recent years”
Site and other (8)
  • Site acres: 620 acres
    “A 620 - acre hyperscale AI data center development in Williams County, North Dakota”
  • Cooling: Closed-loop liquid cooling; initial water fill only (sponsor claim)
    “a closed-loop liquid cooling system that requires only an initial water fill and then continuously recirculates it”
  • Developer: Tachyon9 Corporation
    “entered into an amended and restated binding Letter of Intent with Tachyon 9 Corporation, a Delaware corporation”
  • Name: Nakota AI Campus
    “the 620 Acre Nakota Project, in Williston, North Dakota, designed to deliver up to 1 gigawatt of capacity”
  • Sponsor: Nixxy, Inc. (NASDAQ: NIXX)
    “Nixxy, Inc. (NASDAQ: NIXX) today announced that it has entered into a transformative and binding Letter of Intent (LOI) with Tachyon9 Corporation”
  • Location: Williston, Williams County, North Dakota
    “the 620 Acre Nakota Project, in Williston, North Dakota”
  • Site area: 620 acres
    “Development of the 620-acre Nakota Project in Williston, North Dakota”
  • County code: 38105
    “It is planned on roughly 620 acres in Williams County, North Dakota, in the Williston Basin”