Data center profile · Mercer County, North Dakota, next to the Leland Olds 345 kV substation off Highway 200

River Run Energy Center

NextEra and Basin Electric's proposed 1,450 MW gas plant in Mercer County, North Dakota, meant to anchor a multi-gigawatt data-center campus that has no customer yet

Early development. NextEra and Basin Electric signed a development MOU in Dec. 2025 and applied for a regional grid study, but no data-center customer, state siting certificate or air permit is on record. Mercer County paused data-center applications for a year in March 2026.
1,450 MW
planned combined-cycle gas plant
generation capacity, not data-center load
1,500 acres
data-center land NextEra is optioning
up to; landowners not named
$18B
investment the developers project
gas plant and data center together
2030
plant operations target
site preparation as soon as 2027, subject to permits
OperatorNextEra Energy Resources with Basin Electric Power Cooperative
CustomerNot identified; developer says commercial talks are under way
Planned IT capacity892 MW at full build-out (our estimate from the company or utility power figure)
First building in serviceOur estimate: 2029 or later (no dated power path yet).
Next deadline2027: Earliest site preparation for the gas plant, per the developer, subject to permits
Power

Power and the grid

None energized or contracted yet

Combined-cycle natural gas plantProposed, not permitted
1,450 MW
planned capacity (company); no siting certificate or air permit yet Company · Dec. 2025
Proposed

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. Oct. 2025
    Grid study application
    The partners apply to the Southwest Power Pool's expedited resource adequacy study to test interconnection and transmission needs. Company · Oct. 2025
  2. Dec. 8, 2025
    Development MOU signed
    NextEra, Basin Electric and two member co-ops agree to explore building the plant under Basin's Large Load Commercial Program. Company · Dec. 2025
  3. Not set
    State siting certificate: not filed
    No North Dakota Public Service Commission siting docket for the plant was found as of Oct. 2026. see Permits
  4. 2030
    Plant operations target
    Developer's target, subject to permitting; construction typically takes up to 40 months. Company · March 2026
Permits

Permits checklist

1 pending · 3 checked, nothing on file

Approvals the developer says the project needs, and what has been filed.

Risks

What could slow it down

Money

Money on record

$18B
projected investment, plant and data center
developer figure, Mar. 2026 Company · March 2026
~$15M
annual property tax for Mercer County
developer estimate Company · March 2026

Not on record: final investment decision: gated on grid study, permits, financing and a customer News report · Dec. 2025

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Oct. 2025
    Power NextEra and partners apply for a Southwest Power Pool grid study Company · Oct. 2025
  2. Dec. 8, 2025
    Site NextEra and Basin Electric announce an MOU for a 1,450 MW gas plant to anchor a data-center campus Company · Dec. 2025
  3. March 3, 2026
    Permits Mercer County passes a one-year moratorium on data-center applications, 3-2, after residents pack the room News report · March 2026
  4. March 18, 2026
    Site Basin Electric and NextEra brief the County Commission News report · March 2026
  5. March 30, 2026
    Site Open house in Stanton; developers project $18B of investment and about 230 jobs Company · March 2026
  6. April 17, 2026
    Permits NextEra tells the county it plans to apply for a conditional use permit for the gas plant (press) News report · April 2026
  7. 2027
    Construction Earliest site preparation for the gas plant, per the developer Company · March 2026
  8. 2030
    Power Target for the gas plant to begin operating Company · March 2026
The buildings

Specs

150 acres
gas plant site; data-center land options up to about 1,500 acres
345 kV
existing Leland Olds substation next to the plant site
230 jobs
permanent, once operating (company estimate)
Who is involved

Owners, partners and builders

Developers
  • NextEra Energy Resources: plant developer, optioning data-center land
  • Basin Electric Power Cooperative: generation and transmission co-op, Large Load Commercial Program
  • Upper Missouri Power Cooperative and Roughrider Electric Cooperative: member co-ops in the MOU
Decision-makers
  • Mercer County Commission: moratorium and local zoning
  • North Dakota Public Service Commission: siting certificate
  • North Dakota Department of Environmental Quality: air and water permits
  • Southwest Power Pool: grid study
Power partners
  • WBI Energy: proposed Bakken East gas pipeline
Still unknown

Open questions

Where this comes from

44 records from 12 documents

Drawn from company statements, news reports and public and commercial datasets, each kept with its date and source. The bar shows documents by type.

Company 6News report 6Dataset 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (12)
  • NextEra FAQ timeline for the gas plant: site preparation as soon as 2027 possible, operations by 2030, subject to permitting (construction typically up to 40 months). No 2029 in-service date is stated in the company sour
    “The natural gas plant could begin site preparation as soon as 2027 and reach operations by 2030.”
  • Project identity: River Run Energy Center: proposed combined-cycle natural gas generation facility in Mercer County, ND, intended as the foundation for an associated multi-gigawatt data center campus; primarily a power p
    “The River Run Energy Center is a proposed combined-cycle natural gas-fueled generation facility planned for Mercer County, North Dakota.”
  • Data center component: associated multi-gigawatt data center campus described by the developers
    “Basin Electric Power Cooperative (Basin Electric), in partnership with NextEra Energy Resources, is exploring the development of the River Run Energy Center and associated multi-gigawatt data center campus in Mercer County, North Dakota.”
  • Utility: Basin Electric Power Cooperative (generation and transmission cooperative; project under its Large Load Commercial Program, in which the requesting customer funds the infrastructure needed to support it)
    “Under the program, the customer requesting service is responsible for the infrastructure costs needed to support it, helping insulate existing cooperative members from financial risk.”
  • Plant location: Mercer County next to the existing Leland Olds 345-kV Substation off Highway 200; plant site about 150 acres; data center land options up to about 1,500 acres
    “The natural gas power plant is proposed to be located in Mercer County next to the existing Leland Olds 345-kV Substation off Highway 200.”
  • On-site generation: 1,450 MW
    “Approximately 1,450 MW plant in North Dakota, developed through Basin Electric's Large Load Commercial Program.”
  • Developer: NextEra Energy Resources, LLC and Basin Electric Power Cooperative, with member cooperatives Upper Missouri Power Cooperative and Roughrider Electric Cooperative
    “In December 2025, Basin Electric and NextEra Energy Resources signed a memorandum of understanding to explore the joint development of the River Run Energy Center”
  • Project status: announced / early development - MOU signed Dec 8, 2025; SPP Expedited Resource Adequacy Study application submitted Oct 2025; final investment decision gated on SPP study results, permitting, financing an
    “NextEra Energy Resources, LLC and Basin Electric Power Cooperative (Basin Electric) have signed a memorandum of understanding to explore the joint development”
  • The ~1,450 MW figure is the PLANNED CAPACITY of the proposed combined-cycle plant (company-stated), which would anchor a 'multi-gigawatt' data center campus whose tenant is unnamed and whose load is unstated. Basis: plan
    “With a planned capacity of approximately 1,450 megawatts, the proposed facility would help meet demand from large-scale technology infrastructure such as data centers.”
  • Mercer County process is active but pre-application: Basin/NextEra briefed the County Commission Mar 18, 2026 and held a public open house in Stanton Mar 30, 2026; the county is drafting a data center ordinance, and Next
    “Representatives from NextEra Energy told the commission they plan to submit a conditional use permit (CUP) application for the proposed natural gas plant”
  • Project status: early development; MOU signed Dec 2025, SPP Expedited Resource Adequacy Study application submitted Oct 2025, site studies and field surveys under way, open house held Mar 30, 2026; no ND PSC siting certi
    “In October, the companies submitted an application to the Southwest Power Pool Expedited Resource Adequacy Study process to evaluate interconnection and transmission requirements”
  • Fid status: no final investment decision; FID gated on SPP study results, permitting, financing and confirmed long-term data-center demand - i.e. no load is attached yet
    “NextEra and Basin Electric will base the final investment decision on the Southwest Power Pool study, permitting, financing, and confirmed long-term data-center demand.”
Money and contracts (7)
  • Basin Electric (open house report, Mar 30, 2026): the combined project (gas plant plus data center) is expected to bring over $18 billion in new investment, conservatively employ around 230 permanent full-time workers on
    “In total, the project includes both the natural gas generator and the data center, which is expected to bring over $18 billion in new investment to the area.”
  • Tenant status: not identified - customer / data center tenant not yet identified; commercial discussions in progress
    “Not yet. We are still in the early stages of planning with commercial discussions currently in progress.”
  • Land option agreements (data center land): land option for potential data center development 1500 acres (up to, footprint under option)
    “NextEra Energy Resources is securing land options for potential data center development with a footprint of up to approximately 1,500 acres.”
  • memorandum of understanding: joint development exploration - combined-cycle natural gas facility as foundation for a data center campus (Basin Electric Large Load Commercial Program; participating customers fund the infr
    “have signed a memorandum of understanding to explore the joint development of a new combined-cycle natural gas-fueled generation facility”
  • Announced investment: 18 USD billions
    “developers highlighted the project's potential impact: an estimated $18 billion investment, approximately 230 direct jobs, and roughly $15 million in annual tax revenue.”
  • Memorandum of understanding (joint development): joint development exploration
    “have signed a memorandum of understanding to explore the joint development of a new combined-cycle natural gas-fueled generation facility in Basin Electric's North Dakota service territory.”
  • FID depends on SPP study, permitting, financing and confirmed long-term data-center demand, and the developer confirms the customer has not been identified - the campus currently has no attached load or tenant
    “No public construction timeline or cost estimate exists yet.”
Permits and government (9)
  • The associated data center has no identified customer or tenant: NextEra's FAQ states the customer has not been identified and commercial discussions are in progress; NextEra is securing land options for a data center fo
    “Not yet. We are still in the early stages of planning with commercial discussions currently in progress.”
  • Basin Electric / NextEra Energy Resources (public open house):
    “Basin Electric Power Cooperative (Basin Electric), in partnership with NextEra Energy Resources, is exploring the development of the River Run Energy Center, a 1,450-megawatt combined-cycle natural gas generation facility”
  • Developer FAQ lists the ND PSC Certificate of Site Compatibility, NDDEQ air and : required before construction - not yet obtained / no application found
    “the project will also need to obtain a Certificate of Site Compatibility from the North Dakota Public Service Commission.”
  • Month precision. NextEra Energy Resources and partners submitted an application : Application SUBMITTED (Oct 2025)
    “In October, the companies submitted an application to the Southwest Power Pool Expedited Resource Adequacy Study process to evaluate interconnection and transmission requirements”
  • Mercer County Commission:
    “Speakers from Basin Electric Power Cooperative and NextEra Energy Resources, along with Roughrider Electric Cooperative and the Lignite Energy Council, provided information and updates”
  • Moratorium pauses data center permitting for one year while the county develops : moratorium approved 3-2
    “On March 3, the Mercer County Commission narrowly approved a one-year moratorium on data center applications in the county”
  • Mercer County's Mar 3, 2026 one-year data center moratorium followed resident pressure for local control and zoning clarity; the county had no data center ordinance when River Run was announced in late Feb 2026 coverage
    “the desire to use the time to develop an ordinance that would govern data center applications and permitting.”
  • Mercer County Commission:
    “On March 3, the Mercer County Commission narrowly approved a one-year moratorium on data center applications in the county, after a packed room of local residents voiced their concerns”
  • Key early milestone evaluating interconnection and transmission requirements for: application submitted
    “In October, the companies submitted an application to the Southwest Power Pool Expedited Resource Adequacy Study process to evaluate interconnection and transmission requirements, a key milestone in advancing the project.”
Site and other (1)
  • County code: 38057
    “FCC Census Block API for site point 47.308982,-101.831767: Block FIPS 380579618001170; County FIPS 38057, Mercer County, North Dakota”