Data center profile · Ector County, outside Odessa, Texas, next to Vistra's Odessa gas plant

Texas Critical Data Centers (Odessa)

New Era Energy & Digital's 438-acre campus outside Odessa, Texas, with a 20-year, 207 MW power deal from Vistra's next-door gas plant, a 1 GW-plus ambition and no tenant yet

Power contracted, no tenant. New Era says it has county construction permits and state approval to grade, and it signed a 20-year Phase 1 power contract with Vistra in Sept. 2026. No tenant is signed, and power beyond Phase 1 is only planned.
207 MW
Phase 1 power contracted from Vistra
minimum 200 MW; 20-year term; signed Sept. 2026
1 GW+
long-term campus target (company)
three phases; not contracted beyond Phase 1
438 acres
land owned
plus a 54-acre corridor pending
$70M
paid to buy out SharonAI's 50% stake
signed Jan. 2026; mostly a secured convertible note
OperatorNew Era Energy & Digital (Nasdaq: NUAI), with Stream Data Centers as development partner
CustomerNone signed; marketed to large tenants
Planned IT capacity800 MW at full build-out (our estimate from the company's 1 GW campus power figure)
First building in serviceOur estimate: 2028 (range 2027 to 2031).
Next deadlineQ3 2027: Firm Phase 1 power from Vistra expected to be available
Power

Power and the grid

207 MW contracted

Vistra's Odessa gas plant (Luminant power purchase)Contracted
207 MW
Phase 1 contract, 200 to 207 MW for 20 years, from the adjacent 1,180 MW plant; delivery expected Q3 2027 Company · Sept. 2026
On-site gas generation (Phase 2)Planned
450 MW
company plan for the second phase; not contracted or built Company · April 2026
ContractedProposed

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. April 1, 2026
    Phased power plan
    New Era and Stream plan about 200 MW of utility-powered capacity first, then about 450 MW of on-site gas, then more than 1 GW in total. Company · April 2026
  2. Sept. 18, 2026
    20-year power contract signed
    A New Era subsidiary signs with Luminant, a Vistra affiliate, for 200 to 207 MW from the Odessa gas plant next to the site. Company · Sept. 2026
  3. Q3 2027
    Firm power expected
    Company's expected date for Phase 1 power to be available. Company · Sept. 2026
Permits

Permits checklist

2 granted

Approvals New Era has reported. The underlying permit records were not retrieved.

Risks

What could slow it down

Money

Money on record

$70M
buyout of SharonAI's 50% stake
agreement dated Jan. 16, 2026 (securities filing) SEC filing · Jan. 2026
$50M
of that paid as a senior secured convertible note
plus $10M cash and $10M stock Company · Jan. 2026
5%
non-voting stake Vistra gets after first power
press account of the power deal News report · Sept. 2026
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. 2024
    Site Site first announced as a 90 MW off-grid project (press) News report · Oct. 2026
  2. Jan. 16, 2026
    Money New Era agrees to buy SharonAI's 50% stake in the project for $70M SEC filing · Jan. 2026
  3. Jan. 18, 2026
    Money Deal closes; New Era owns 100% of Texas Critical Data Centers Company · Jan. 2026
  4. April 1, 2026
    Site Stream Data Centers signs a letter of intent to develop the campus in three phases Company · April 2026
  5. Aug. 2026
    Permits New Era says it has county construction permits and state approval to begin grading (press) News report · Aug. 2026
  6. Sept. 18, 2026
    Power 20-year power contract signed with Vistra's Luminant for up to 207 MW Company · Sept. 2026
  7. Q3 2027
    Power Phase 1 power expected to be available (company) Company · Sept. 2026
The buildings

Specs

438 acres
owned, plus a 54-acre corridor pending
3 phases
on land New Era contributes to the Stream partnership
1,180 MW
Vistra gas plant immediately adjacent to the site
90 MW
the site's original 2024 off-grid plan (press)
Who is involved

Owners, partners and builders

Owners
  • New Era Energy & Digital, Inc.: developer, sole owner since Jan. 2026
  • Texas Critical Data Centers LLC: project company
  • SharonAI: former 50% partner, sold out
Builders
  • Stream Data Centers: development partner (letter of intent)
Power partners
  • Luminant ET Services (Vistra): Phase 1 power supplier
  • TCDC PowerCo LLC: New Era subsidiary that signed the power contract
  • Mawgan Capital: non-binding letter of intent for on-site gas
Decision-makers
  • Ector County: construction permits
  • Texas Commission on Environmental Quality: grading approval
Still unknown

Open questions

Where this comes from

40 records from 11 documents

Drawn from company statements, news reports, securities filings and public and commercial datasets, each kept with its date and source. The bar shows documents by type.

Company 5News report 4SEC filing 1Dataset 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (9)
  • Announced: Nov. 12, 2024
    “today announce that they have executed a non-binding letter of intent to form a joint venture for the design, development, and operation of an initial 90MW net-zero energy data center in the Permian Basin”
  • Construction stage: permitted, pre-construction - land secured, Ector County construction permits and TCEQ grading approval in hand (Aug 2026); Phase 1 power delivery expected Q3 2027
    “With the land secured, construction permits in hand, Phase 1 power contracted for 20 years, and room to expand to multiple phases”
  • On-site generation: 550 MW
    “A subsidiary of Thunderhead Energy Solutions, New Era's Phase 2 power partner, submitted a standard air permit application to TCEQ, which would support ~550MW of Phase 2 capacity at TCDC”
  • Stated campus size: 1,000 MW
    “Designed for phased expansion toward 1+ GW of total capacity”
  • Utility service: 200 MW
    “Phase 1: ~200 MW of utility-powered capacity”
  • On-site generation: 450 MW
    “Phase 2: ~450 MW of on-site gas-fired generation capacity”
  • Developer: New Era Energy & Digital, Inc. (Nasdaq: NUAI), with Stream Data Centers as development partner
    “New Era is a developer and operator of next-generation digital infrastructure and integrated power assets”
  • Non-binding LOI with Mawgan Capital / Thunderhead Energy Solutions to deploy ~250 MW of behind-the-meter gas generation at TCDC - not a contract; do not sum with the Phase 2 450 MW figure
    “TCDC has signed a non-binding LOI with Mawgan Capital to deploy 250MW of gas generation to supply the data center”
  • One secondary source puts the long-term TCDC target at ~1.4 GW (CryptoBriefing); The site started as a 90 MW off-grid announcement in 2024 and a 250 MW initial-capacity figure in the buyout coverage
    “The project is expected to have an initial capacity of 250MW, with the potential to scale beyond 1GW”
Money and contracts (8)
  • Membership Interest Purchase Agreement (JV buyout): ownership transfer - 50% JV interest 50 percent of TCDC membership interests
    “Seller owns Membership Interests of the Company constituting 50% of the Percentage Interest”
  • Membership Interest Purchase Agreement (JV buyout): purchase price 70 USD million
    “The aggregate purchase price for the Purchased Interests shall be $70,000,000 (the "Purchase Price")”
  • Tenant status: none found - no tenant signed; project marketed to hyperscale tenants
    “we believe this is an attractive opportunity to any quality tenant currently in the market”
  • Power Purchase Agreement: contracted capacity 207 MW
    “Luminant has agreed to supply a minimum of 200 MW and up to 207 MW of power for Phase 1 of New Era’s Texas Critical Data Center ("TCDC") project”
  • Power Purchase Agreement: term 20-year initial term, automatic one-year renewals
    “The PPA has an initial 20-year term, with automatic one-year renewal periods thereafter. The firm, contracted power is expected to be available to TCDC in Q3 of 2027”
  • Development partnership (LOI): development partnership three-phase delivery on land contributed by New Era
    “Expected to be delivered in three phases on land contributed by New Era”
  • Membership Interest Purchase Agreement (JV buyout): consideration structure $10M cash + $10M common stock + $50M senior secured convertible note (matures June 30, 2026)
    “The consideration New Era will pay Sharon AI will be an aggregate of US$70m and is comprised of a US$50m Senior Secured Convertible Promissory Note, US$10m in Cash and US$10m in Equity”
  • Power Purchase Agreement: ROFO / ROFO rights Vistra: first refusal rights on future TCDC development opportunities; first offer rights on certain future projects; 5% non-voting stake after first power delivery
    “The agreement gives Vistra a 5% non-voting stake in the data center after the first power delivery. Vistra will also have first refusal rights on future TCDC development opportunities and first offer rights on certain future projects”
Permits and government (3)
  • TCEQ standard air permit application (Phase 2 behind-the-meter plant): application submitted (per New Era Q2 2026 report); not issued
    “A subsidiary of Thunderhead Energy Solutions, New Era's Phase 2 power partner, submitted a standard air permit application to TCEQ, which would support ~550MW of Phase 2 capacity at TCDC”
  • construction permits: issued
    “In August, New Era said it had received construction permits from Ector County and TCEQ approval to begin grading”
  • grading approval: approved
    “In August, New Era said it had received construction permits from Ector County and TCEQ approval to begin grading”
Site and other (3)
  • Campus name: New Era Texas Critical Data Center (TCDC)
    “The Company is developing Texas Critical Data Centers LLC ("TCDC"), a 438 acre large-scale AI and high-performance computing data center campus located in Ector County, outside Odessa, Texas”
  • Site acres: 438 acres
    “438 acres owned, plus a 54-acre corridor pending (Ector County, Texas)”
  • County code: 48135
    “438 acres owned, plus a 54-acre corridor pending (Ector County, Texas)”