Data center profile · Briscoe County, Texas

Soluna Project Dorothy (Dorothy 1 + 3)

Data center campus proposed by Soluna in Briscoe County, Texas, on grid power with an on-site gas bridge; 300 MW of IT capacity planned.

Land assembled. Utility and grid approval granted. A utility or grid-operator filing is on record, with no final approval or signed service agreement yet. Newest record Oct. 2026.
The campus, Lower-resolution satellite image, Oct. 18, 2026
300 MW
IT capacity the company states
150 MW
on-site generation on record
prime or bridge power, not backup
397
acres in the site
OperatorSoluna
CustomerNone named
Planned IT capacity300 MW at full build-out (company IT figure)
First building in serviceOur estimate: 2029 or later (no dated power path yet).
The site

The site from above

Satellite overview
Lower-resolution satellite image, Oct. 18, 2026.
Power

Power and the grid

The plan on record is the grid, with on-site gas as a bridge. An interconnection study is under way.

We checked utility filings, regulator dockets and air-permit records for this campus.

Permits

Permits checklist

1 granted · 5 checked, nothing on file

Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. May 12, 2022
    Site Project first appears in the public record
  2. Aug. 25, 2026
    Power Soluna's release states it currently operates approximately 192 MW of energized capacity across its whole portfolio. Company · Aug. 2026
  3. Sept. 14, 2026
    Power Interconnection queue approved by ERCOT. Company · Sept. 2026
Construction activity

Satellite captures by quarter

Since Sept. 2025: 2 satellite captures.

Satellite
’26
Dot size: records in the quarter, largest = 1. Two-digit years mark each first quarter.
Who is involved

Owners, partners and builders

Owners and developers
  • Soluna Holdings, developer
Still unknown

Open questions

Where this comes from

21 records from 5 documents

Drawn from company statements, satellite captures and news reports, each kept with its date and source. The bar shows documents by type.

Company 3Satellite 1News report 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (9)
  • interconnection queue (ERCOT): conditionally classified Base Load (100 MW)
    “ERCOT has conditionally classified its 100 MW Project Dorothy campus as Base Load in Batch Zero”
  • Campus name: Soluna Project Dorothy (Dorothy 1 + 2 + 3)
    “The land will host Project Dorothy 3, Soluna's planned renewable-first AI computing campus with a potential capacity of up to 300 MW”
  • IT capacity: 300 MW
    “The land will host Project Dorothy 3, Soluna's planned renewable-first AI computing campus with a potential capacity of up to 300 MW”
  • On-site generation: 150 MW
    “The parcel sits adjacent to Projects Dorothy 1 and 2 and to the 150 MW Briscoe Wind Farm, which Soluna acquired in April”
  • Role of the on-site plant: prime
    “positioning Dorothy 3 for direct, behind-the-meter access to generation the Company owns outright”
  • On-site power technology: wind (onshore wind farm)
    “The parcel sits adjacent to Projects Dorothy 1 and 2 and to the 150 MW Briscoe Wind Farm, which Soluna acquired in April”
  • Soluna's release states it currently operates approximately 192 MW of energized capacity across its whole portfolio; the Dorothy site's own operating load is the roughly 98 MW of Bitcoin mining at Dorothy 1/2.
    “Soluna currently operates approximately 192 MW of energized capacity”
  • The 397-acre Dorothy 3 parcel exceeds the 300 acres originally identified for the campus, leaving room to add data halls if further generation or storage becomes available at the site.
    “The 397 acres exceed the 300 acres Soluna originally identified for the campus”
  • Project status: Dorothy 1 + 2 OPERATING as Bitcoin mining/hosting (about 98 MW energized mining load - mining is not IT capacity); Dorothy 3 (300 MW AI campus) in development on 397 acres closed August 2026
    “Dorothy 1 and Dorothy 2 already account for 98 MW of energized capacity across a shared 30-acre complex”
Money and contracts (2)
  • Announced: May 12, 2022
    “The funding is the first of the up to $35 million in project financing committed by funds managed by Spring Lane Capital, originally announced on May 12, 2022.”
  • land purchase: closed
    “The land will host Project Dorothy 3, Soluna's planned renewable-first AI computing campus with a potential capacity of up to 300 MW”
Site and other (2)
  • Site acreage: 397 acres
    “announced it has closed the purchase of 397 acres in Briscoe County, Texas”
  • County code: 48045
    “announced it has closed the purchase of 397 acres in Briscoe County, Texas”

Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).