Data center profile · Taylor, Williamson County, Texas

Taylor Technology Campus (formerly Project Mustang)

Data center campus planned by PowerHouse Data Centers and Big Watt Digital in Williamson County, Texas, powered mainly by on-site gas; about 462 MW of IT capacity planned.

Approved, not yet permitted. Zoning approval granted. No utility agreement or generation permit is on record. Newest record Oct. 2026.
The campus, Lower-resolution satellite image, Oct. 17, 2026
750 MW
on-site generation on record
prime or bridge power, not backup
664
acres in the site
2029+
first building in service, our estimate
no dated power path yet; company says 2028
OperatorPowerHouse Data Centers and Big Watt Digital
CustomerNone named
Planned IT capacity462 MW at full build-out (our estimate from on-site generation)
First building in serviceOur estimate: 2029 or later (no dated power path yet); company says 2028.
The site

The site from above

Satellite overview
Lower-resolution satellite image, Oct. 17, 2026.
Power

Power and the grid

The plan on record is on-site gas generation. No utility agreement or generation permit is on record yet.

We checked utility filings, regulator dockets and air-permit records for this campus.

Permits

Permits checklist

1 granted · 5 checked, nothing on file

Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.

Money

Money on record

$28M Economic development agreement (Approved). News report · Oct. 2026

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Aug. 16, 2026
    Site Project first appears in the public record
  2. Oct. 8, 2026
    Permits Rezoning approved by City of Taylor. News report · Oct. 2026
  3. Oct. 12, 2026
    Power The approved agreement includes an option to add another 500 MW beyond the 500 MW provided for (up to 1 GW total campus design). News report · Oct. 2026
Construction activity

Since Oct. 2026: 1 satellite capture. Satellite · Oct. 2026

Who is involved

Owners, partners and builders

Owners and developers
  • Big Watt Digital, developer
Investors and lenders
  • PowerHouse Data Centers, partner
Government
  • City of Taylor, public agency
Still unknown

Open questions

Where this comes from

18 records from 4 documents

Drawn from news reports and satellite captures, each kept with its date and source. The bar shows documents by type.

News report 3Satellite 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (6)
  • On-site generation: 750 MW
    “the 664-acre campus is designed to deliver up to 1GW of data center capacity using dedicated, behind-the-meter power via a new 750MW natural gas plant”
  • Role of the on-site plant: prime
    “using dedicated, behind-the-meter power via a new 750MW natural gas plant”
  • On-site power technology: natural gas generation (plant configuration not specified in sources)
    “via a new 750MW natural gas plant”
  • Project status: approved Oct. 8, 2026 (annexation + economic development agreement, unanimous council vote); construction slated 2027-2029; first power targeted H1 2028
    “Construction is slated to take place between 2027 and 2029, with initial power availability expected in the first half of 2028”
  • Stated campus size: 500 MW
    “the city will annex the site into its limits while providing for 500 megawatts of power capacity, with the option to add another 500 megawatts”
  • The approved agreement includes an option to add another 500 MW beyond the 500 MW provided for (up to 1 GW total campus design); The option is documented here only
    “the city will annex the site into its limits while providing for 500 megawatts of power capacity, with the option to add another 500 megawatts”
Money and contracts (1)
  • economic development agreement: approved 28200000 USD
    “Big Watt Digital and PowerHouse Data Centers will also commit approximately $28.2 million in local investments, including funds for Taylor Independent School District programs”
Permits and government (1)
  • rezoning: approved (unanimous)
    “Taylor City Council unanimously approved the proposals last week, which were previously known as Project Mustang”
Site and other (4)
  • Campus name: Taylor Technology Campus
    “it has secured approval for the Taylor Technology Campus in Taylor, a city in Williamson County, Texas”
  • County code: 48491
    “the Taylor Technology Campus in Taylor, a city in Williamson County, Texas”
  • Site acreage: 664 acres
    “The campus will rise on roughly 664 acres east of Taylor's city limits, within the broader Austin, Texas, metro area”
  • Announced: Aug. 2026
    “The City of Taylor announced on its Facebook page and website that two companies had proposed a joint venture to build a data center campus on a 665-acre site just east of the city limits”

Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).