Data center profile · 4186 Scioto Darby Creek Road, Hilliard, Franklin County, Ohio

Amazon Hilliard (Scioto Darby Creek Rd)

Amazon's approved seven-building site in Hilliard, Ohio, where AEP Ohio is building a 72.9 MW fuel-cell plant because the grid cannot yet serve all buildings.

Permitted, power bridge. Ohio's siting board approved the 72.9 MW fuel-cell plant on Sept. 22, 2025; Hilliard dropped its appeal of the state air permit on Sept. 15, 2026. AEP said construction would start in Jan. 2026, with operation projected for Sept. 2027.
72.9 MW
fuel-cell plant for the campus
228 Bloom Energy units; on-site generation, not IT capacity; Amazon calls it temporary (press)
7 buildings
in the approved site plan on 151 acres
approved July 2022; the fuel cells replace the planned Building G
Sept. 2027
projected start of fuel-cell operation
AEP projection; construction was to begin in Jan. 2026
OperatorAmazon Data Services, Inc.; AEP Ohio owns the fuel-cell plant
CustomerAmazon Web Services (fuel-cell service contract with AEP Ohio)
First building in serviceOur estimate: 2027 (range 2027 to 2029); company says 2026.
Next deadlineEnd of 2026: Amazon's deadline under its city tax abatement to reach $200 million of investment
Power

Power and the grid

None energized or contracted yet · 72.9 MW permitted

AEP Ohio fuel cells (228 Bloom units)Permitted, projected Sept. 2027
72.9 MW
AEP Ohio builds and runs the plant under a contract in which Amazon pays all costs; Amazon calls the fuel cells temporary until grid upgrades are done (press) Company · Oct. 2026
Permitted
Other sources, size not disclosed
Backup generators (emergency use, not a power supply)

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. Sept. 22, 2025
    State siting board approves the fuel-cell plant
    The Ohio Power Siting Board certifies the 72.9 MW, 228-unit plant for AEP Ohio. see Permits
  2. Oct. 2026
    Gas pipeline due in service
    A new 8-inch gas pipeline for the fuel cells is expected to be finished and in service by October 2026 (press). News report · Oct. 2026
Permits

Permits checklist

2 withdrawn · 1 pending · 3 granted

Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.

Risks

What could slow it down

Money

Money on record

$200M investment Amazon must reach by Dec. 31, 2026 (condition of the city tax abatement; the city says Amazon has met or exceeded its requirements). Local government · Oct. 2026

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. July 14, 2022
    Permits Hilliard approves a site plan for a seven-building data-center complex on 151 acres Local government · Aug. 2024
  2. Sept. 22, 2025
    Permits Ohio Power Siting Board approves the 72.9 MW fuel-cell plant Local government · Oct. 2026
  3. Oct. 20, 2025
    Permits AEP withdraws its local site-plan application, relying on the state approval (press) News report · Sept. 2026
  4. Nov. 7, 2025
    Legal The city of Hilliard appeals the Ohio EPA air permit for the fuel cells (press) News report · Sept. 2026
  5. Sept. 15, 2026
    Legal Hilliard withdraws its appeal of the air permit (press) News report · Sept. 2026
  6. Oct. 2026
    Power Gas pipeline for the fuel cells is due in service (press) News report · Oct. 2026
  7. End of 2026
    Money Deadline for Amazon to reach $200 million of investment under the city tax abatement Local government · Oct. 2026
  8. Sept. 2027
    Power Fuel-cell plant projected to be operating (AEP projection) Local government · Oct. 2026
Who is involved

Owners, partners and builders

Owners
  • Amazon Data Services, Inc.: site applicant
Power partners
  • Ohio Power Company (AEP Ohio): builds and runs the fuel-cell plant
  • Bloom Energy: fuel-cell supplier
  • Northeast Ohio Natural Gas Corporation: builds the gas pipeline (press)
Decision-makers
  • Ohio Power Siting Board and Ohio EPA: state approvals
  • City of Hilliard: appealed, then withdrew
Still unknown

Open questions

Where this comes from

49 records from 8 documents

Drawn from local government records, news reports, public and commercial datasets and company statements, each kept with its date and source. The bar shows documents by type.

Local government 3News report 3Dataset 2Company 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (10)
  • Campus name: Amazon Hilliard (Scioto Darby Creek Road)
    “The project is a proposed 72.9-megawatt solid oxide fuel cell (SOFC) electric generation facility at 4186 Scioto Darby Creek Road, within Amazon's 142-acre data-center campus”
  • On-site generation: 72.9 MW
    “Amazon Web Services (AWS) contracted with Ohio Power to construct, install and operate a solid oxide fuel cell (SOFC) system made up of 228 Energy Servers® to provide 72.9 megawatts (MW) of power”
  • On-site fuel cell units: 228 units
    “The project will consist of 228 Bloom Energy fuel cell units that produce electricity through an electrochemical reaction, not combustion”
  • Utility: AEP Ohio (Ohio Power Company)
    “AEP has indicated that it does not have sufficient electrical capacity to service all of the planned data center buildings on Amazon's Scioto Darby Road campus”
  • Source record
    “There are currently no plans to install fuel cells at any other location within the city of Hilliard”
  • Construction stage: Approved plan comprises 7 data center buildings, an Amazon transformer yard and an AEP substation; construction documents run from the Nov 2022 permit set through a Dec 2024 construction set; the fuel
    “The approved Level “B” Site Plan originally consisted of 7 data center buildings, an Amazon transformer yard, and an AEP substation”
  • Level B Site Plan modification (landscaping / transmission easements): approved
    “On August 8, 2024, the Commission approved modifications to the Level “B” Site Plan necessary to adjust landscaping to conform to easement restrictions associated with the installation of transmission lines for the AEP substation located at the site”
  • Amazon states the fuel cells are a temporary measure: AEP will use them to power part of the data center operations while larger Ohio grid infrastructure upgrades are completed; the city FAQ likewise anticipates fuel cel
    “In Hilliard, the local utility, AEP, will temporarily use fuel cells to power part of our data center operations while larger Ohio power infrastructure upgrades are completed”
  • Bloom Energy's November 2024 agreement with AEP covers up to 1 GW of fuel cells for Ohio data center sites with an initial 100 MW order - PORTFOLIO figure only (AEP also supplies Cologix and Amazon sites); it is NOT this
    “The fuel cells would be supplied by Bloom Energy, which signed a 1GW deal with AEP Ohio in November 2024”
  • After the Oct. 9, 2025 P&Z hearing on PZ-25-59 (decision postponed), AEP withdrew its application to the city's Planning and Zoning Commission, asserting the OPSB approval was all that was required under ORC 4906.13(B);
    “The city's appeal was in response to American Electric Power, which own the natural-gas powered fuel cells, withdrawing its application to the city's planning and zoning commission”
Money and contracts (3)
  • Community Reinvestment Area (CRA) abatement agreement: property tax abatement with investment commitment Total investment of $200 million required by Dec. 31, 2026; Hilliard School District receives up to $3.4 million an
    “The CRA required Amazon to make a total investment of $200 million by Dec. 31, 2026”
  • Behind-the-meter fuel cell service contract: private agreement - construct, install and operate; customer bears all costs 72.9 MW SOFC system (228 Bloom Energy Servers); AWS covers all project costs (fuel cell equ
    “The fuel cell project is part of a contract between Ohio Power and AWS, which will cover all costs (fuel cell equipment, pipeline infrastructure, etc.) associated with it”
  • Natural gas pipeline construction and operation agreement: build, operate and maintain the fuel supply pipeline and associated natural gas facilities 8-inch natural gas pipeline serving the fuel cell facility; pipeline a
    “As part of the agreement, Hope Utilities' local subsidiary, Northeast Ohio Natural Gas Corporation (NEO), will build, operate, and maintain the pipeline and associated natural gas facilities for this project”
Permits and government (12)
  • Certificate: approved (effective)
    “The Ohio Power Siting Board approved this fuel cell project on Sept. 22, 2025”
  • Permit to Install and Operate (air, minor source): issued
    “Based on the project's low overall air emissions, the project is considered a “minor source” and the Ohio EPA issued a Permit to Install and Operate (PTIO) for this project”
  • Zoning: M-1, Restricted Industrial District
    “On October 27, 2014, the site was zoned to M1, Restricted Industrial District (Ordinance 14-29). On November 12, 2020, data centers were added as permitted uses within the M-1 zoning district (Ordinance 20-36)”
  • Variance (tree replacement amendment): approved
    “On August 15, 2024, the Board of Zoning Appeals approved a variance (BZA-24-13) to amend tree replacement requirements associated with this modification”
  • Level B Site Plan Minor Change (fuel cell system): heard Oct. 9, 2025 - staff recommended approval; local application later withdrawn by the applicant side (see signals)
    “The proposal consists of installing 228 fuel cells (outdoor natural gas clean packaged energy servers) in place of the previously approved Building G located in the southern central portion of the site”
  • Buildings planned: 7 buildings
    “On July 14, 2022, a Level “B” Site Plan was approved by the Planning and Zoning Commission (PZ-22-33) for the construction of a seven-building data center complex”
  • Level B Site Plan approval: approved
    “On July 14, 2022, a Level “B” Site Plan was approved by the Planning and Zoning Commission (PZ-22-33) for the construction of a seven-building data center complex”
  • Variances: granted
    “On July 21, 2022, a series of variances were granted by the Board of Zoning Appeals (BZA-22-24) necessary for the approved Level “B” Site Plan”
  • Announced: July 14, 2022
    “On July 14, 2022, a Level "B" Site Plan was approved by the Planning and Zoning Commission (PZ-22-33) for the construction of a seven-building data center complex.”
  • Amazon is seeking a permit to operate 158 diesel backup generators at the site (per DCD, reporting Signal Ohio)
    “Amazon is also seeking a permit to operate 158 diesel backup generators at the site”
  • Administrative appeal: filed
    “The City of Hilliard filed the appeal on Nov. 7, 2025, the final day in a 30-day window that was allowed to file an appeal after the Ohio EPA had issued a permit to install the fuel cells”
  • Administrative appeal: withdrawn
    “The operation of up to 228 natural-gas powered fuel cells for an Amazon Web Services data center on Scioto-Darby Road can occur after the City of Hilliard announced on Sept. 15 that is has withdrawn its appeal”
Site and other (6)
  • Address: 4186 Scioto Darby Creek Rd, Hilliard, OH 43026
    “at 4186 Scioto Darby Creek Road, within Amazon's 142-acre data-center campus”
  • Project status: building
    “AEP has indicated that construction for the project will start in January 2026 with the facility projected to be operational by September 2027”
  • Parcel ID: 050-002806
    “Parcel Number(s): 050-002806”
  • County code: 39049
    “PARCEL NUMBER: 050-002806”
  • Site acres: 151.27 acres
    “Review and approval of changes to the Level “B” Site Plan to modify the approved landscaping plan for a data center complex on a 151.27-acre site”
  • Developer: Amazon Data Services, Inc.
    “APPLICANT: Amazon Data Services Inc., 410 Terry Avenue N, Seattle, WA 98108”