Data center profile · Dallas County, Texas

AREP Powerhouse Las Colinas

Data center campus developed by American Real Estate Partners in Dallas County, Texas, on grid power; about 161 MW of IT capacity planned.

Under construction. FAA airspace clearance granted. A utility is named, but no signed service agreement is on record. Newest record Oct. 2026.
The campus, Lower-resolution satellite image, Oct. 19, 2026
201 MW
utility load on file
facility power, not split into IT capacity
Oncor
serving utility
Grid power
50
acres in the site
3
data center buildings planned
OperatorAmerican Real Estate Partners
CustomerNone named
Planned IT capacity161 MW at full build-out (our estimate from the company or utility power figure)
First building in serviceOur estimate: 2029 or later (no dated power path yet).
The site

The site from above

Satellite overview
Lower-resolution satellite image, Oct. 19, 2026.
Power

Power and the grid

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. Oct. 15, 2026
    Utility MW on record
Permits

Permits checklist

1 granted · 5 checked, nothing on file

Approvals a campus like this normally needs, and what we found.

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. May 27, 2025
    Permits FAA airspace clearance granted by the FAA. FAA · July 2025
  2. June 15, 2026
    Permits Searched through Oct. 20, 2026: ERCOT Monthly Operational Overviews, ERCOT Board Item 14 Batch Zero Update, and web searches. State agency · June 2026
  3. Sept. 15, 2026
    Site ERCOT's Batch Zero conditional classifications were published only as aggregates, 204 projects (66.4 GW) conditionally base load. State agency · Sept. 2026
Construction activity

Building activity by quarter

Since May 2025: 2 FAA filings (May 2025 to July 2025): tallest crane 370 ft (May 2025); 3 satellite captures.

FAA filings
Satellite
’26
Dot size: records in the quarter, largest = 1. Two-digit years mark each first quarter.
Who is involved

Owners, partners and builders

Investors and lenders
  • PowerHouse Data Centers, partner
  • Harrison Street, partner
Builders and advisers
  • Brasfield & Gorrie, general contractor
Still unknown

Open questions

Where this comes from

32 records from 9 documents

Drawn from state agency records, company statements, satellite captures, news reports, public and commercial datasets and local government records, each kept with its date and source. The bar shows documents by type.

State agency 3Company 2Satellite 1News report 1Dataset 1Local government 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (13)
  • ERCOT's Batch Zero conditional classifications (Board update, September 14-15, 2026) were published only as aggregates - 204 projects (66.4 GW) conditionally base load and 158 projects (127.9 GW) conditionally studied lo
    “ERCOT has provided conditional classification for all Batch Zero Large Loads”
  • Searched through Oct. 20, 2026: ERCOT Monthly Operational Overviews, ERCOT Board Item 14 Batch Zero Update (Sept. 14, 2026/15), and web searches for 'PowerHouse Irving ERCOT', '111 Customer Way ERCOT' and 'Powerhouse Data LCX P
    “Planning Studies Approved – Projects that have received ERCOT approval of required interconnection studies”
  • Announced: May 15, 2024
    “The site, located at 111 Customer Way, will be home to PowerHouse Irving, a nearly one million square foot data center campus that will deliver 200 MW of power when completed.”
  • Campus name: PowerHouse Irving (Las Colinas)
    “The site, located at 111 Customer Way, will be home to PowerHouse Irving”
  • Stated campus size: 200 MW
    “PowerHouse Irving, a nearly one million square foot data center campus that will deliver 200 MW of power when completed”
  • Street address: 111 Customer Way, Irving, TX
    “The site, located at 111 Customer Way, will be home to PowerHouse Irving”
  • Utility: Oncor
    “The site has immediate access to permanent power from an existing adjacent substation, serviced by Oncor”
  • Power step: utility named
    “The site has immediate access to permanent power from an existing adjacent substation, serviced by Oncor”
  • First shell delivery stated: late 2025
    “Construction is scheduled to begin in early 2025, with the first powered shell set to be delivered by late 2025”
  • Project status: Under construction: land closed May 2024, construction from early 2025, and the first of three powered-shell buildings was topped out in October 2026 (structure complete; interior systems and infrastructu
    “With the structure now complete, work continues on interior systems, infrastructure, and the next phases of development across the campus”
  • Utility service: 201 MW
    “the campus will support up to 201MW of utility power across three two-story buildings, totaling approximately 900,000 sq ft”
  • First building at PowerHouse Irving topped out (October 2026); structure complete, interior systems and infrastructure work continuing. Construction is by Brasfield & Gorrie for the PowerHouse/Harrison Street JV.
    “The company announced the topping out of the first building at its Irving campus over the weekend”
  • Building count: 3 buildings
    “The campus includes three powered shell data centers totaling over 946,000 square feet, with a total power load of 67 MW per building”
Money and contracts (3)
  • tax abatement agreement: tax abatement 50 %
    “would be eligible to receive a 50% property tax abatement”
  • land purchase: closed
    “announced the completed land purchase of 50 acres in Irving-Las Colinas”
  • No Oncor substation work, Oncor service agreement, PUCT filing or CCN naming PowerHouse Irving / Powerhouse Data LCX / 111 Customer Way was found in public sources through Oct. 20, 2026. The sole Oncor evidence is the devel
    “serviced by Oncor, the largest energy delivery company in Texas”
Permits and government (2)
  • FAA OE/AAA archive case: Determined - No Hazard
    “New Construction of Data Centers”
    FAA · July 2025 · grade A
  • FAA OE/AAA archive case: Determined - No Hazard
    “New Construction of Data Centers”
    FAA · May 2025 · grade A
Site and other (3)
  • ERCOT public listing: not found in ERCOT public large-load reporting (aggregate-only)
    “No Studies Submitted – Projects that are tracked by ERCOT but that have not yet provided sufficient information”
  • County code: 48113
    “First announced in 2024, the project is located at 111 Customer Way in Dallas County”
  • Site acreage: 50 acres
    “announced the completed land purchase of 50 acres in Irving-Las Colinas”

Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).