Power and the grid
- Proposed gas plant with battery storage (separate docket) Proposed, no air permit500 MW; proposed generation by Copia GDC LLC; not campus load; not approved; links among Copia entities not established News report · Sept. 2024
- Grid service via Harry Allen Substation Not on recordno service or interconnection agreement; unclear whether NV Energy or another arrangement would serve it News report · Oct. 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Sept. 2024Gas plant advance noticeCopia GDC LLC files a notice for a 500 MW gas plant, battery and 500 kV generation tie. see Permits
- Dec. 8, 2025Federal right-of-way applicationCopia submits an SF-299 to the Bureau of Land Management, which starts the federal process but authorizes nothing. see Permits
- Jan. 27, 2026Transmission advance noticeCopia Digital LLC opens state docket 26-01035 for up to two 500 kV lines. see Permits
Permits checklist
3 pending · 2 checked, nothing on file
Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.
- ◷Right-of-way application (SF-299) for the transmission route PendingBureau of Land Management · Dec. 8, 2025: submitted; no case serial, scoping or environmental document public by Oct. 2026 News report · Dec. 2025
- ◷Advance notice, two 500 kV lines (Docket 26-01035) PendingPublic Utilities Commission of Nevada · Jan. 27, 2026: a notice step under the state utility siting law News report · Jan. 2026
- ◷Advance notice, 500 MW gas plant (Docket 24-09023) PendingPublic Utilities Commission of Nevada · Sept. 2024: filed by Copia GDC LLC; no detailed permit application found News report · Sept. 2024
- –Checked, nothing on file: Local zoning, Air permit
What could slow it down
- HighFederal review aheadThe federal right-of-way application has no public project page, scoping notice or environmental document yet. News report · Oct. 2026
- MediumNo tenant or power dealNo tenant, contracted load or service agreement is in the record. News report · Oct. 2026
- MediumSponsor changeCopia Power is being sold by Carlyle to EQT, with closing expected by the end of 2026. Company · July 2026
What happened, and what is due
- Sept. 2024Power Copia GDC LLC files a Nevada advance notice for a 500 MW gas plant and battery News report · Sept. 2024
- Dec. 8, 2025Permits Copia submits a federal right-of-way application for the transmission route News report · Dec. 2025
- Jan. 27, 2026Power Copia Digital LLC opens a state docket for up to two 500 kV lines to Harry Allen Substation News report · Jan. 2026
- July 9, 2026Paper trail EQT agrees to buy Copia Power from Carlyle; no campus-specific terms disclosed Company · July 2026
- Oct. 4, 2026Site A records review finds no tenant, no requested load and no approvals, only filings News report · Oct. 2026
Specs
~744 acres site per an application to the Nevada Department of Wildlife (applicant statement). News report · Dec. 2025
Owners, partners and builders
- Copia Digital LLC: data center applicant
- Copia GDC LLC: gas plant applicant
- Copia Power: sponsor, being acquired by EQT from Carlyle
- Bureau of Land Management: right-of-way
- Public Utilities Commission of Nevada: siting notices
Open questions
- Data center load in MW.
- Tenant.
- Federal environmental review.
- Relationship between the gas plant and the data center.
24 records from 3 documents
Drawn from news reports and company statements, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (5)
- EQT (EQT Infrastructure VII) acquired Copia Power from Carlyle in October 2026 - the sponsor behind Bergen (and Monarch) changed hands while Bergen sits at the advance-notice stage; Copia reports 2.6+ GW of generation/st“Swedish investment firm EQT has acquired Copia Power, a developer of integrated energy and digital infrastructure campuses, from Carlyle”News report · Oct. 2026 · grade C
- County code: 32003“a proposed 500 MW natural-gas generating facility, a roughly 0.8-mile 500 kV generation-tie line, a gas pipeline, battery storage and associated facilities on federally managed Clark County land”News report · Jan. 2026 · grade C
- Applicant targets only (not approvals): BLM SF-299 right-of-way application submitted Dec 2025; NDOW application dated Dec 8, 2025 describes an approximately 744-acre site; Copia targets a 2027 notice to proceed and comm“An attached Nevada Department of Wildlife application describes an approximately 744-acre data-center site and says Copia targets a 2027 notice to proceed”News report · Dec. 2025 · grade C
- On-site generation: 500 MW“PUCN Docket 24-09023, filed by Copia GDC LLC in September 2024, describes a proposed 500 MW natural-gas generating facility”News report · Sept. 2024 · grade C
- Docket 24-09023 states a proposed 500 MW natural-gas generating facility (mw generation onsite basis, proposed only); no document reviewed states the campus requested or contracted load in MW, and a 500 kV line voltage i“a proposed 500 MW natural-gas generating facility, a roughly 0.8-mile 500 kV generation-tie line, a gas pipeline, battery storage and associated facilities on federally managed Clark County land.”News report · Sept. 2024 · grade C
Money and contracts (2)
- EQT Infrastructure VII agreed to acquire Copia Power from Carlyle (announced Jul 9, 2026; amount undisclosed; closing expected by end of 2026); Copia was established by Carlyle in 2021; Platform-level figures in the rele“EQT is pleased to announce that EQT Infrastructure VII (EQT) has agreed to acquire Copia Power (Copia or the Company) from global investment firm Carlyle (NASDAQ: CG).”Company · July 2026 · grade B
- Bergen remains pre-application for local land use: the reviewed records show a BLM right-of-way application and PUCN advance notices only, with a targeted 2027 notice to proceed after permits and federal environmental re“Those dates and dimensions are applicant statements, not agency approvals or construction evidence.”News report · Dec. 2025 · grade C
Permits and government (3)
- see confli: Advance notice filed opening Docket 26-01035 (UEPA, NRS 704.870): up to two 500 kV lines to Harry Allen Substation“The January 27 filing opened Public Utilities Commission of Nevada Docket 26-01035”News report · Jan. 2026 · grade C
- Copia submitted a Standard Form 299 right-of-way application to BLM in December : SF-299 right-of-way application submitted for the Bergen transmission route (December 2025)“Copia described a route about 0.85 mile long and said it submitted a Standard Form 299 right-of-way application to the Bureau of Land Management in December 2025”News report · Dec. 2025 · grade C
- In September 2024 Copia GDC LLC filed a separate UEPA advance notice (PUCN Docke: Earlier advance notice, Docket 24-09023 (Copia GDC LLC): proposed 500 MW gas plant + BESS + gas pipeline + 500 kV gen-tie“PUCN Docket 24-09023, filed by Copia GDC LLC in September 2024, describes a proposed 500 MW natural-gas generating facility”News report · Sept. 2024 · grade C
Site and other (1)
- Project status: proposed“The January 27 filing opened Public Utilities Commission of Nevada Docket 26-01035.”News report · Jan. 2026 · grade C