Permits
Permits checklist
1 draft · 1 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- ◷County data-center zoning rules DraftFranklin County · May 12, 2026: restrictions drafted ahead of any project: 200-foot setbacks, air cooling, public water, noise testing (press) News report · May 2026
- –Checked, nothing on file: Rezoning, site plan or approval
Risks
Why it stopped, what could revive it
- WatchProject withdrawnThe county and the tracker both say the project is not moving forward, so no build is expected unless a new proposal appears. News report · Oct. 2026
- MediumOrganized resident oppositionThe project surfaced through residents' records requests and drew organized opposition, a supervisor's resignation and a complaint over transparency (press). News report · Oct. 2026
- MediumDeveloper link unconfirmedCrusoe is named only by local press and records requests; the county has not confirmed it and Crusoe has issued no statement. News report · July 2026
Power
Power and the grid
Sources on record, size not disclosed
- Utility grid at the business park None on recordthe park reportedly has grid and natural gas infrastructure; no Appalachian Power, state regulator or interconnection filing for this project was found News report · Oct. 2026
Getting on the grid
- No Appalachian Power, Virginia State Corporation Commission or interconnection filing naming the project was found as of Oct. 2026. News report · Oct. 2026
Timeline
What happened, and what is due
SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
- May 12, 2026Permits Franklin County drafts data-center zoning limits while no project has been announced News report · May 2026
- July 16, 2026Site Records requests reveal a proposed data center, code-named Project Flash, at Summit View Business Park; press names Crusoe as the interested company (in talks with the county since November) News report · July 2026
- Aug. 16, 2026Site A Boone District supervisor tells the public about the project (press) News report · Sept. 2026
- Aug. 17, 2026Site A Virginia project tracker records the project as withdrawn by the developer Dataset · Aug. 2026
- Aug. 18, 2026Legal The supervisor resigns during a board meeting; a formal complaint against county leadership follows (press) News report · Sept. 2026
- Oct. 3, 2026Site Public radio reports residents used public records requests to uncover the project and that the county said it was not moving forward News report · Oct. 2026
Who is involved
Owners, partners and builders
Owners
- Franklin County, Virginia: owner of Summit View Business Park
Developer
- Crusoe: linked by local press and records requests only
Decision-makers and critics
- Mike Meredith: Boone District supervisor who resigned Aug. 18, 2026 (press)
Still unknown
Open questions
- Whether Crusoe or another developer still wants the site.
- The power and size the developer actually sought.
- Why the project was withdrawn, beyond the resident opposition.
Where this comes from
20 records from 6 documents
Drawn from news reports, local government records and public and commercial datasets, each kept with its date and source. The bar shows documents by type.
News report 4Local government 1Dataset 1
Evidence
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (4)
- County code: 51067“Utilities include electricity, natural gas, water/sewer, fiber/broadband, and is centrally located along U.S. 220 in Franklin County, Virginia, just 20 minutes from downtown Roanoke.”Local government · Oct. 2026 · grade B
- A Virginia data center project tracker records the Crusoe/Summit View project as withdrawn by the developer on Aug 17, 2026, at 150 acres and 100 MW - the tracker's 100 MW is the top of DCD's reported 50-100MW range, wit“Rocky Mount, Franklin County Crusoe Withdrawn by the developer The data center proposed for Summit View Business Park will not be built.”Dataset · Aug. 2026 · grade B
- Site acres: 150 acres“Few details are available, but Franklin County-owned Summit View Business Park may host the development if it goes ahead, and may total 50-100MW on some 150 acres.”News report · July 2026 · grade C
- Park acres: 540 acres“Summit View Business Park totals 540 acres located along US 220, and reportedly includes grid and natural gas infrastructure.”News report · July 2026 · grade C
Permits and government (2)
- County public position: As of May 2026 the county said data center companies had contacted it and that no projects had officially been announced in the county“The current draft zoning ordinance includes several restrictions aimed at limiting the impact of future data center development, though no projects have officially been announced in the county.”News report · May 2026 · grade C
- While Project Flash was still unannounced, Franklin County was rewriting its zoning code with data center restrictions (200-foot setbacks from non-commercial districts, air-cooling preference, public-water requirements,“Under the proposal, any data center would have to be located at least 200 feet from non-commercial zoning districts.”News report · May 2026 · grade C
Site and other (5)
- Site location: Summit View Business Park, just north of Rocky Mount, VA (county-owned business park along U.S. 220)“The project was later identified as a proposed data center development at Summit View Business Park, just north of Rocky Mount.”News report · Oct. 2026 · grade C
- Project status: cancelled - withdrawn in August 2026 before any public approval, application or site work; the county announced in mid-August 2026 that the project was not moving forward“As details emerged, residents opposed the project, and the county announced in mid-August that it was not moving forward.”News report · Oct. 2026 · grade C
- The project surfaced only through residents' FOIA requests and drew organized resident opposition; a supervisor's resignation and a formal complaint against county leadership followed in the ensuing transparency dispute.“Residents in Franklin and Roanoke counties used public records requests to uncover details about proposed data centers as scrutiny of the projects grows, WVTF reported.”News report · Oct. 2026 · grade C
- Project code name: Project Flash“Local press, including WDBJ, 10News, and the Roanoke Times, report that officials have been in discussions with a data center developer about the potential 'Project Flash' data center.”News report · July 2026 · grade C
- Developer linkage: Crusoe - linked by local press / FOIA reporting only; never confirmed by Franklin County or by Crusoe“The interested company behind the planned development is Crusoe. The company has been in discussions with county officials since November.”News report · July 2026 · grade C