The site from above
The site
Latest clear satellite view, Sept. 19, 2015.
Power and the grid
None energized or contracted yet
- Advanced nuclear (later) Proposedstated intention only; no reactor vendor, design or licence application News report · Oct. 2026
- Dominion Energy South Carolina grid Not contractedserves the site on three 115 kV lines; the partner must secure its own agreement, none announced Company · July 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Dec. 9, 2025Industry dayDOE says the site grid is fed by Dominion on three 115 kV lines and owned by DOE; any project must include new generation. News report · Dec. 2025
- As of Oct. 2026No interconnection agreementThe bid rules require the partner to secure utility interconnection; none has been announced. see Permits
- The whole site peaks at about 50 MW today, so even the 1 GW stated campus dwarfs the existing system. News report · Dec. 2025
- The existing 20 MW biomass plant belongs to DOE and its contractor, and is not committed to the campus. State agency · Oct. 2026
- No plant for this campus appears in EIA's federal generator inventory (EIA-860M, Aug. 2026). That inventory covers grid-connected plants only, so an off-grid plant may not be listed yet. State agency · Oct. 2026
Permits checklist
1 pending · 1 granted · 4 checked, nothing on file
Because the land is federal, county zoning does not apply; DOE approvals gate everything.
- ◷Executed lease PendingDOE / NNSA · as of Oct. 2026: negotiations open, no lease signed State agency · July 2026
- ✓Land lease solicitation and selection GrantedDOE / NNSA · July 20, 2026: Amentum selected to negotiate; this is not a lease State agency · Oct. 2026
- –Checked, nothing on file: Environmental review (NEPA), Air permit for gas generation, Utility interconnection, Reactor licence or authorization
What could slow it down
- HighNo lease, no money, no tenantSelection is not an award, and the financial framework is unsettled. State agency · July 2026
- HighPower is a planGas and later nuclear are stated intentions with no plant, permit, vendor or utility agreement. Company · July 2026
- MediumFederal reviews aheadEnvironmental, safety and security reviews gate any lease, and no review notice has been published. see Permits
- WatchLocal concernsRegional coverage flags electricity, water and public-participation worries; no organized opposition on record. News report · Oct. 2026
Money on record
~$1B Amentum's own revenue frame (for a 2 GW nuclear project over its life; services revenue, not project funding). News report · Aug. 2026
- Loans possible: DOE loan office told bidders federal loans exist (programme availability, not a commitment) News report · Dec. 2025
Not on record: financing: Amentum said Aug. 11, 2026 the financial framework is still under negotiation News report · Aug. 2026
What happened, and what is due
- April 2025Site DOE asks industry about 16 federal sites, including Savannah River, for AI data centers State agency · April 2025
- July 24, 2025Site DOE picks four sites to advance, including Savannah River State agency · July 2025
- Sept. 2025Permits NNSA issues the lease request for 10 tracts totaling 3,103 acres State agency · Sept. 2025
- Dec. 9, 2025Site Industry day draws about 115 organizations; attendance is not a commitment News report · Dec. 2025
- Jan. 9, 2026Permits Final offers due after the deadline was pushed back from Dec. 5 State agency · Dec. 2025
- July 20, 2026Permits NNSA selects the Amentum-led team, with DC BLOX, to negotiate a phased lease Company · July 2026
- Aug. 11, 2026Money Amentum says the financial framework is still under negotiation News report · Aug. 2026
Satellite captures by quarter
Since Sept. 2015: 67 satellite captures. The chart starts in the first quarter of 2023; 5 earlier records are not drawn.
Specs
- Phased lease: number and size of phases not stated; term and rent not public State agency · July 2026
- Federal land: Aiken County zoning does not apply; all gating approvals are federal State agency · July 2026
- Behind the meter: campus meant to run on its own generation State agency · Sept. 2025
Owners, partners and builders
- Amentum Holdings: consortium lead, selected to negotiate
- DC BLOX: digital infrastructure partner and lead data-center developer
- DOE and its National Nuclear Security Administration: lessor and all gating approvals
- Dominion Energy South Carolina: serves the site grid; no campus agreement
- Google, Milliken and Nucor are named by one press report but not by DOE or the companies; they are not counted as partners
- Savannah River Nuclear Solutions LLC (SRNS): Incumbent SRS management and operations contractor
Open questions
- Lease term, rent and number of phases.
- Who the tenant would be.
- What generation is built, and when nuclear replaces gas.
- Environmental review schedule.
265 records from 32 documents
Drawn from state agency records, news reports, securities filings, public and commercial datasets, company statements and satellite captures, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (33)
- Existing site generation: 20 MW biomass cogeneration facility (DOE-owned, built and operated by Ameresco under a $795M ESPC, in operation since 2012) serving SRS site missions - NOT committed to the campus“20 MW Biomass CHP System; GENERATING CAPACITY: 20 MW; IN OPERATION SINCE: 2012; JOINT PROJECT BY: U.S. DOE, Ameresco”State agency · Oct. 2026 · grade A
- Utility: Dominion Energy (named RFP point of contact for interconnection; not an executed agreement)“Dominion Energy Point of Contact.pdf”State agency · Dec. 2025 · grade A
- Aliases: SRS AI Infrastructure and Energy Generation Project; Savannah River Site Artificial Intelligence Infrastructure and Energy Generation Project“Request for Proposals: Artificial Intelligence Infrastructure and Energy Generation on DOE Land at Savannah River Site”State agency · Sept. 2025 · grade A
- Power plan: onsite“data center facilities with specialized Information Technology (IT) equipment; associated cooling facilities; energy supply infrastructure; transmission and storage infrastructure”State agency · Sept. 2025 · grade A
- NNSA issued RFP-AI-1 for a long-term lease of SRS tracts (10 tracts, 3,103 acres); proposals due Dec. 5, 2025“Request for Proposals: Artificial Intelligence Infrastructure and Energy Generation on DOE Land at Savannah River Site”State agency · Sept. 2025 · grade A
- IT capacity: not stated“The project includes a 1-gigawatt data center and approximately 2-gigawatts of on-site energy generation”State agency · Oct. 2026 · grade B
- Utility service: not stated“Partners must secure utility interconnection agreements”State agency · Oct. 2026 · grade B
- Utility: none contracted for the campus“Partners must secure utility interconnection agreements”State agency · Oct. 2026 · grade B
- Electric service agreement signed: not stated“Selection for negotiations does not constitute a final lease award”State agency · Oct. 2026 · grade B
- Utility interconnection: none executed“Partners must secure utility interconnection agreements”State agency · Oct. 2026 · grade B
- Stated campus size: 1,000 MW“the public-private project would establish a 1-gigawatt artificial intelligence data center supported by approximately 2 gigawatts of on-site energy generation”Company · July 2026 · grade B
- On-site generation: 2,000 MW“supported by approximately 2 gigawatts of on-site energy generation, initially powered by natural gas bridging to advanced nuclear energy”Company · July 2026 · grade B
- On-site generation: 2,000 MW“The proposed project features a 1-gigawatt data center campus and approximately 2 gigawatts of on-site energy generation.”Company · July 2026 · grade B
- Stated campus size: 1,000 MW“the public-private project would establish a 1-gigawatt artificial intelligence data center supported by approximately 2 gigawatts of on-site energy generation”Company · July 2026 · grade B
- On-site generation: 2,000 MW“supported by approximately 2 gigawatts of on-site energy generation, initially powered by natural gas bridging to advanced nuclear energy”Company · July 2026 · grade B
- Interconnection status: none - no grid position exists or is planned: the campus sits on the federal Savannah River Site reservation and the DOE/NNSA plan is behind-the-meter on-site generation (about 2 GW, gas bridging“Amentum has been selected by the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) to enter negotiations for a phased lease”Company · July 2026 · grade B
- Name: DOE Savannah River Site AI Campus“announced the selection of Amentum to enter negotiations for a phased lease to develop an artificial intelligence data center and dedicated on-site energy generation source at the Savannah River Site”State agency · July 2026 · grade B
- Developer: Amentum (consortium lead), selected by NNSA to enter negotiations for a phased lease; DC BLOX is the digital infrastructure partner / lead data-center developer in the consortium“announced the selection of Amentum to enter negotiations for a phased lease to develop an artificial intelligence data center and dedicated on-site energy generation source”State agency · July 2026 · grade B
- Stated campus size: 1,000 MW“The project includes a 1-gigawatt data center and approximately 2-gigawatts of on-site energy generation consisting of natural gas bridging to nuclear energy”State agency · July 2026 · grade B
- On-site generation: 2,000 MW“The project includes a 1-gigawatt data center and approximately 2-gigawatts of on-site energy generation consisting of natural gas bridging to nuclear energy”State agency · July 2026 · grade B
- Power plan: onsite“the proposed project pairs new AI infrastructure with dedicated on-site energy generation, helping ensure the project electricity needs are met without shifting costs to existing utility customers”State agency · July 2026 · grade B
- On-site power technology: natural gas (bridge) transitioning to advanced nuclear (proposed); no reactor vendor, design or SMR supplier named“approximately 2-gigawatts of on-site energy generation consisting of natural gas bridging to nuclear energy”State agency · July 2026 · grade B
- Acres: 3103 acres“NNSA has identified 10 tracts of land totaling 3,103 acres at SRS for AI infrastructure projects and seeks applications that integrate innovative energy generation and storage projects with AI data centers”State agency · Sept. 2025 · grade B
- Interconnection status: none secured; RFP-AI-1 requires the selected partner to secure utility interconnection agreements - none announced as of Oct. 18, 2026“Partners must secure utility interconnection agreements”State agency · Sept. 2025 · grade B
- DOE designated four sites to move forward - INL, Oak Ridge, Paducah and Savannah River; site-specific solicitations to follow“DOE has selected four sites - Idaho National Laboratory, Oak Ridge Reservation, Paducah Gaseous Diffusion Plant and Savannah River Site - to move forward”State agency · July 2025 · grade B
- Buildings: not stated“The project includes a 1-gigawatt data center and approximately 2-gigawatts of on-site energy generation”State agency · Oct. 2026 · grade C
- Square feet: not stated“The project includes a 1-gigawatt data center and approximately 2-gigawatts of on-site energy generation”State agency · Oct. 2026 · grade C
- ENR reported expected costs wer“Expected costs of the Paducah and Savannah River Site data center-power projects were not disclosed”News report · July 2026 · grade C
- Acres data center tract: 250-450 acres“There are ten tracts of land potentially capable of supporting a data center and/or power generation facilities, with the size of the data center ranging between 250 and 450 acres”News report · July 2026 · grade C
- Site grid supply: Dominion Energy South Carolina feeds SRS on three 115 kV lines; the on-site grid is DOE-owned and leased to Dominion for operations and maintenance“fed by Dominion Energy South Carolina on three 115 KV lines. All of the grid within Savannah River is owned by DOE. It is currently under lease to Dominion Energy”News report · Dec. 2025 · grade C
- Substation kV: 115 kV“fed by Dominion Energy South Carolina on three 115 KV lines”News report · Dec. 2025 · grade C
- SRS today peaks at about 50 MW (300,000 MWh/yr); the 20 MW biomass plant generates ~85,000 MWh/yr; two commercially owned 75 MW solar farms with BESS are in development for 2029 (~115,000 MWh/yr each). Site context only“The site currently uses about 50MW at peak with an annual consumption of 300,000 megawatt hours”News report · Dec. 2025 · grade C
- SRS Community Reuse Organization and regional economic-development officials publicly welcomed the RFP and the prospect of SMR/gas generation at SRS“Robbie Bennett, President and CEO of the SRS Community Reuse Organization (SRSCRO), told ABD that having the opportunity to house a data center at the site can open the door”News report · Oct. 2025 · grade C
Money and contracts (25)
- Phased land lease (prospective, not executed): term FINDING: lease term (years) is not stated in the SAM.gov record, the NNSA releases, or the company releases - the RFP says only long-term“solicit proposals from entities interested in entering a long-term Lease covering a portion of identified real property located at SRS in South Carolina”State agency · Oct. 2026 · grade A
- Source record“ESPC AWARD: $795 million; ESPC LENGTH: 19 years; JOINT PROJECT BY: U.S. DOE, Ameresco”State agency · Oct. 2026 · grade A
- RFP-AI-1 solicitation (DOE/NNSA): status Solicitation issued Sept. 30, 2025; offers due Dec. 5, 2025 5:00 PM EST; notice inactive Dec. 6, 2025; SAM.gov Notice ID RFP-AI-1“Request for Proposals: Artificial Intelligence Infrastructure and Energy Generation on DOE Land at Savannah River Site”State agency · Sept. 2025 · grade A
- RFP-AI-1 solicitation (DOE/NNSA): scope Long-term lease of a portion of SRS real property to design, finance, permit, develop, construct, install, own, maintain, operate and decommission AI data center and energy generat“The Lease Agreement with the Government is for the purposes of designing, financing, permitting, developing, constructing, installing, owning, maintaining, operating, and decommissioning AI data center and energy generation infrastructure”State agency · Sept. 2025 · grade A
- Tenants: not stated“Selection for negotiations does not constitute a final lease award”State agency · Oct. 2026 · grade B
- Tenant status: none named“Selection for negotiations does not constitute a final lease award”State agency · Oct. 2026 · grade B
- Land control: none - no lease executed; Amentum holds only a selection to negotiate“Selection for negotiations does not constitute a final lease award. Any agreement will be subject to successful negotiations and all applicable permitting requirements, safety and security evaluations, and other federal approvals”State agency · Oct. 2026 · grade B
- Stage: selected for lease negotiation only - no lease award, no financing, no tenant, no COD; a paper project at the federal-selection stage, one step past a bare announcement“Selection for negotiations does not constitute a final lease award”State agency · Oct. 2026 · grade B
- Phased land lease (prospective, not executed): termination FINDING: no termination, cancellation or default clause is public - no lease has been executed and no draft lease terms have been published as of Oct. 18, 2026“Selection for negotiations does not constitute a final lease award”State agency · Oct. 2026 · grade B
- Phased land lease (prospective, not executed): rent FINDING: rent / consideration is not stated in any public document opened as of Oct. 18, 2026“Additional information about the project and lease negotiations will be released through the appropriate channels as it becomes available”State agency · Oct. 2026 · grade B
- As of this pass: no lease execution, NEPA notice, tenant, financing, COD or construction milestone has been announced by DOE, NNSA, Amentum or DC BLOX since the July 20, 2026 selection“Additional information about the project and lease negotiations will be released through the appropriate channels as it becomes available”State agency · Oct. 2026 · grade B
- Land use authority: Federal (DOE/NNSA) - SRS is a federal reservation; Aiken County zoning and permitting do not apply and no county approval has been sought or given; every gating approval is federal (lease, NEPA, safet“Any agreement will be subject to successful negotiations and all applicable permitting requirements, safety and security evaluations, and other federal approvals”State agency · July 2026 · grade B
- Selection for lease negotiations (no lease): status Amentum selected July 20, 2026 to enter negotiations for a phased lease; negotiations open as of Oct. 18, 2026; NO lease executed“today announced the selection of Amentum to enter negotiations for a phased lease to develop an artificial intelligence data center and dedicated on-site energy generation source”State agency · July 2026 · grade B
- Selection for lease negotiations (no lease): conditions precedent Selection is not a lease award; any agreement requires successful negotiations plus all applicable permitting, safety and security evaluations and other f“Selection for negotiations does not constitute a final lease award. Any agreement will be subject to successful negotiations and all applicable permitting requirements, safety and security evaluations, and other federal approvals”State agency · July 2026 · grade B
- Developer edgar footprint: fund feeder Form Ds only“Form D filed 2026-04-29 by BGA Private Opportunities Fund, LLC - DC BLOX 2 Series”SEC filing · April 2026 · grade B
- RFP-AI-1 solicitation (DOE/NNSA): scope 10 tracts totaling 3,103 acres offered; one or more long-term leases may result acres“U.S. private sector partners will submit proposals to potentially enter into one or more long-term leasing agreements at the site”State agency · Sept. 2025 · grade B
- RFP-AI-1 solicitation (DOE/NNSA): conditions precedent Lessee is responsible for building, operating and decommissioning, and must secure utility interconnection agreements; proposals evaluated on technological readiness“will be responsible for building, operating, and decommissioning each infrastructure project. Partners must secure utility interconnection agreements”State agency · Sept. 2025 · grade B
- Incentives: not stated“Any agreement will be subject to successful negotiations and all applicable permitting requirements, safety and security evaluations, and other federal approvals”State agency · Oct. 2026 · grade C
- Financing: none arranged or disclosed; financial framework still under negotiation as of the Amentum Q3 FY2026 earnings call (Aug. 11, 2026)“The financial framework remains under negotiation, though Amentum expects the economics to be generally consistent with a 2-gigawatt nuclear project”News report · Aug. 2026 · grade C
- Project financing framework: status Financial framework remains under negotiation (Amentum Q3 FY2026 earnings call, Aug. 11, 2026); no financing, lender, instrument or capital commitment disclosed“The financial framework remains under negotiation, though Amentum expects the economics to be generally consistent with a 2-gigawatt nuclear project”News report · Aug. 2026 · grade C
- Amentum Q3 FY2026 earnings call: the consortium financial framework is still under negotiation; management framed its own economics as consistent with a 2 GW nuclear project producing over $1B of revenue over its life -“The financial framework remains under negotiation, though Amentum expects the economics to be generally consistent with a 2-gigawatt nuclear project”News report · Aug. 2026 · grade C
- Stated capital cost: not stated“Expected costs of the Paducah and Savannah River Site data center-power projects were not disclosed”News report · July 2026 · grade C
- Consortium roles (per company statements): scope Role split as summarized by Nuclear Engineering International from the announcements“While Amentum manages federal operations, technical integration, and overall consortium leadership, DC BLOX provides the direct technical blueprint for the technology campus”News report · July 2026 · grade C
- Consortium roles (per company statements): scope Amentum: consortium leadership, federal operations and technical integration. DC BLOX: digital infrastructure partner / lead data-center developer (technical blueprint for“DC BLOX has been selected as the digital infrastructure partner in a consortium with Amentum chosen by the U.S. Department of Energy National Nuclear Security Administration”Company · July 2026 · grade C
- DOE Office of Energy Dominance Financing (renamed Loan Programs Office) told industry-day attendees that federal loans are available for nuclear and data-center projects - programmatic availability, not a commitment to t“Peter Mandelstam at the Energy Office of Energy Dominance Financing said that loans were available for nuclear projects and other power efforts”News report · Dec. 2025 · grade C
Permits and government (13)
- Federal land lease solicitation: proposals due (as amended); notice inactive“Updated Inactive Date: Jan 10, 2026”State agency · Jan. 2026 · grade A
- Federal land lease solicitation: amendment: Q&A Parts 2 and 3 released“SRS RFP Questions and Answers PART 3 (Cleared for Release).pdf”State agency · Dec. 2025 · grade A
- Federal land lease solicitation: amendment: industry-day package, Appendix A Rev 1, utility and regulator points of contact“Dominion Energy Point of Contact.pdf”State agency · Dec. 2025 · grade A
- Federal land lease solicitation: proposals due (corrected date); no award“Offers due 2026-01-09”State agency · Dec. 2025 · grade A
- Federal land lease solicitation: offer due date extended“Updated Date Offers Due: Jan 09, 2026 05:00 pm EST”State agency · Dec. 2025 · grade A
- Federal land lease solicitation: solicitation issued“Request for Proposals: Artificial Intelligence Infrastructure and Energy Generation on DOE Land at Savannah River Site”State agency · Sept. 2025 · grade A
- FAA airspace cases within 5 nautical miles: 0 cases“FAA OE/AAA returned no cases within 5 NM of either anchor; the identical query returns cases at other batch campuses (positive recall).”FAA · Oct. 2026 · grade B
- Federal land lease: selectee announced; negotiations opened - NO lease executed“Selection for negotiations does not constitute a final lease award”State agency · Oct. 2026 · grade B
- NEPA review: none found“Any agreement will be subject to successful negotiations and all applicable permitting requirements, safety and security evaluations, and other federal approvals”State agency · Oct. 2026 · grade B
- NNSA / Savannah River Site (RFP-AI-1 Industry Day): Correction to the SRS industry-day presentation: permitted surface water withdrawal figure restated“During the live Industry Day presentation, the permitted SRS surface water withdrawal amount was incorrectly stated”Dataset · Dec. 2025 · grade B
- Reactor licensing / authorization: none found“It is unclear whether the partners plan to deploy traditional nuclear or advanced nuclear reactors on the site”News report · Oct. 2026 · grade C
- NNSA / Savannah River Site (RFP-AI-1 Industry Day): SRS presentation to prospective offerors: tracts, site power and water briefing; DOE attendee list published (~115 organizations)“A number of large tech companies and hyperscalers attended a meeting about building a data center on Department of Energy (DOE) land”News report · Dec. 2025 · grade C
- Local support: SRS Community Reuse Organization (SRSCRO) and regional economic developers publicly supportive“Part of the reason this is so exciting is that DOE sites have the ability to move the nuclear permitting a little bit faster”News report · Oct. 2025 · grade C
Legal (1)
- Regional reporting flags concerns over electricity, water use, environmental impacts and public participation for SC data centers including SRS; no SRS-specific organized opposition, petition or suit identified“the story notes concerns about electricity, water consumption, environmental impacts and public participation”News report · Oct. 2026 · grade C
Site and other (17)
- SEC filing mention: not stated“Unconstrained EDGAR search "Savannah River" "data center" returned 122 documents”SEC filing · Oct. 2026 · grade A
- Procurement classification: PSC X1PC Lease/Rental of Unimproved Real Property (Land); NAICS 51821; no set-aside; place of performance Aiken SC 29802“Product Service Code: X1PC - LEASE/RENTAL OF UNIMPROVED REAL PROPERTY (LAND)”State agency · Dec. 2025 · grade A
- Address: Savannah River Site, Aiken, SC (federal reservation; no campus street address exists)“solicit proposals from entities interested in entering a long-term Lease covering a portion of identified real property located at SRS in South Carolina”State agency · Sept. 2025 · grade A
- Construction stage: not stated“Selection for negotiations does not constitute a final lease award”State agency · Oct. 2026 · grade B
- Original target date: not stated“Additional information about the project and lease negotiations will be released through the appropriate channels as it becomes available”State agency · Oct. 2026 · grade B
- Current target date: not stated“Additional information about the project and lease negotiations will be released through the appropriate channels as it becomes available”State agency · Oct. 2026 · grade B
- Construction stage: lease negotiation“selected by the U.S. Department of Energy’s National Nuclear Security Administration (NNSA) to enter negotiations for a phased lease”Company · July 2026 · grade B
- Developer selection: NNSA selected Amentum consortium (DC BLOX as digital infrastructure partner) on July 20, 2026 to negotiate a phased lease; no lease executed“DC BLOX, a leading provider of connected data center and fiber network solutions, today announced its selection as a digital infrastructure partner in a development consortium with Amentum”Company · July 2026 · grade B
- Announced: July 20, 2026“today announced the selection of Amentum to enter negotiations for a phased lease”State agency · July 2026 · grade B
- Phases: phased lease contemplated by NNSA; number and size of phases not stated“announced the selection of Amentum to enter negotiations for a phased lease”State agency · July 2026 · grade B
- NNSA selected the Amentum-led consortium (with DC BLOX) to enter negotiations for a phased lease - selection expressly is not a lease award“Selection for negotiations does not constitute a final lease award”State agency · July 2026 · grade B
- Water use stated: 10950 million gallons/month“The correct units are millions of gallons per month, which is roughly equivalent to 250,000 gallons per minute”Dataset · Dec. 2025 · grade B
- DOE site designation date: July 24, 2025“On July 24, 2025, Secretary Wright and DOE announced the site selection for AI Data Center and energy infrastructure development on federal lands”State agency · July 2025 · grade B
- DOE request for information identified 16 federal sites, including SRS, as candidates for AI data center and energy development“In April 2025, DOE identified 16 federal sites that could support the construction of AI data centers and associated energy infrastructure”State agency · April 2025 · grade B
- Opposition: Regional coverage reports concerns about electricity, water consumption, environmental impacts and public participation; no organized opposition group, petition or litigation specific to the SRS campus identi“the story notes concerns about electricity, water consumption, environmental impacts and public participation”News report · Oct. 2026 · grade C
- County: Aiken County“The two companies will now enter negotiations for a phased lease for the site, which, if successful, will lay the foundation for the campus development in Aiken County”News report · July 2026 · grade C
- RFP industry day drew ~115 organizations including Microsoft, Google, Meta, CoreWeave, QTS, Digital Realty, Oracle and Crusoe (Amazon absent), plus nuclear developers Oklo, GE Vernova, Terrestrial Energy and The Nuclear“Among those in attendance were Microsoft, CoreWeave, Google, QTS, Meta, Digital Realty, Oracle, Crusoe”News report · Dec. 2025 · grade C
Imagery and records: Satellite imagery: Maxar via Esri World Imagery Wayback.