Data center profile · Mount Holly Commerce Park, Moncks Corner, Berkeley County, South Carolina

Google Berkeley County expansion (Moncks Corner)

A $1.3 billion expansion of Google's first South Carolina data center, in service since 2007 in Moncks Corner; groundwater fights, no MW figure published.

Expanding, campus operating. Google has run this campus since 2007, announced a $1.3 billion expansion in Sept. 2024 and said in Oct. 2025 that new funding would expand it. No MW figure, construction milestone or campus-specific power agreement for the expansion is on record.
$1.3B
expansion investment
announced Sept. 26, 2024 by the Governor's Office
2007
year the campus opened
Google's first in South Carolina
Not published
MW added by the expansion
state and company releases give dollars and jobs only
OperatorGoogle (owner and operator)
CustomerNone named beyond Google
First building in serviceIn service since 2007
Next stepNone published
Power

Power and the grid

Energized, size not disclosed

Sources on record, size not disclosed

Getting on the grid

Permits

Permits checklist

1 pending · 2 granted · 1 checked, nothing on file

Approvals on record for the campus, and what we could not find.

Risks

What could slow it down

Money

Money on record

$1.3B
expansion investment (state announcement)
Sept. 2024; part of a $3.3B announcement that also covered two Dorchester County campuses State agency · Sept. 2024
$600M+
earlier expansion pitch seeking a tax break (press)
code name Project Linden, 2019 News report · 2019
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. 2007
    Site Google's first South Carolina data center opens in Moncks Corner State agency · Sept. 2024
  2. Dec. 2010
    Money County fee-in-lieu-of-taxes agreement formalized (press) News report · Oct. 2026
  3. 2019
    Money Google, under the code name Project Linden, seeks a tax break for at least $600M more investment (press) News report · 2019
  4. Oct. 9, 2019
    Permits State gives final approval to triple the campus's groundwater withdrawal to 549M gallons a year News report · Oct. 2019
  5. Sept. 26, 2024
    Site Governor's Office announces Google's $1.3B expansion of the campus State agency · Sept. 2024
  6. Oct. 13, 2025
    Money Google says a new $9B statewide program through 2027 will fund the campus expansion Company · Oct. 2025
Construction activity

Building activity by quarter

Since Jan. 2015: 4 FAA filings (Jan. 2015 to Feb. 2020): tallest permanent building 81 ft (filed Dec. 2019) and tallest crane 240 ft (Feb. 2020).

FAA filings
’15
’16
’17
’18
’19
’20
Dot size: records in the quarter, largest = 2. Two-digit years mark each first quarter.
The buildings

Specs

549M gallons a year groundwater withdrawal the state permitted in 2019 (press). News report · Oct. 2019

Who is involved

Owners, partners and builders

Owner
  • Google: owner and operator
  • Maguro Enterprises: company Google used to negotiate the original pitch and the Project Linden expansion (press)
Power
  • Berkeley Electric Cooperative: power partner (press)
  • Santee Cooper: state utility building new 230 kV transmission in the county
Government
  • Berkeley County: host county and tax agreement
  • South Carolina Governor's Office: announced the 2024 expansion
Still unknown

Open questions

Where this comes from

33 records from 12 documents

Drawn from state agency records, news reports, utility regulator dockets and company statements, each kept with its date and source. The bar shows documents by type.

State agency 4News report 4Utility regulator 3Company 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (1)
  • Google signed a 600 MW solar PPA with EnergyRe in South Carolina in 2025
    “Earlier this year, in South Carolina, Google signed a 600MW solar PPA with EnergyRe, and a water sustainability agreement with Arable.”
Money and contracts (6)
  • Project identity: Google data center campus, Mount Holly Commerce Park, Moncks Corner, Berkeley County, SC - operating since 2007 (Google's first South Carolina campus); $1.3B expansion of the existing campus announced S
    “In Berkeley County, Google will invest $1.3 billion to expand its existing data center campus, located in the Mount Holly Commerce Park in Moncks Corner, and support continued job growth.”
  • Investment announced: 1300000000 USD
    “In Berkeley County, Google will invest $1.3 billion to expand its existing data center campus, located in the Mount Holly Commerce Park in Moncks Corner, and support continued job growth.”
  • Mapping (inferred): the Cross-Wassamassaw line serves Berkeley County load growth where Google's Moncks Corner campus expansion (Project Linden) is the county's concentrated new data center load. The PSC notice names no
    “This project will provide additional transmission capacity to support the load growth, and it will also provide increased electric reliability to residents and businesses throughout South Carolina”
  • The Oct 2025 $9 billion is a statewide figure through 2027 covering Berkeley plus two Dorchester campuses and workforce programs; it must not be attributed to this campus alone
    “Google is announcing a new $9 billion investment in South Carolina through 2027.”
  • Governor's Office put the Berkeley-specific share of the 2024 combined announcement at $1.3 billion
    “In Berkeley County, Google will invest $1.3 billion to expand its existing data center campus, located in the Mount Holly Commerce Park in Moncks Corner”
  • Earlier expansion pitch under the code name 'Project Linden': Google sought a property tax break for an investment of at least $600M, negotiated by Maguro Enterprises; a related groundwater permit request (1.5 million ga
    “Records filed with Berkeley County, first spotted by The Post and Courier, note that Google is hoping to invest $600m in the facility, but is seeking a property tax break first.”
Permits and government (9)
  • FAA OE/AAA archive case, Crane "10402: Determined - No Hazard
    “ASN 2020-ASO-6648-OE: 10402 - MNK, crane, 190 ft AGL, 237 ft AMSL, 33.06417,-80.03861, Determined - No Hazard, submitted 2020-02-28”
    FAA · Feb. 2020 · grade A
  • FAA OE/AAA archive case, Crane "MNK 7A", 240 ft AGL / 283 ft AMSL at 33.06439,-: Determined - No Hazard
    “ASN 2020-ASO-5679-OE: MNK 7A, crane, 240 ft AGL, 283 ft AMSL, 33.06439,-80.03906, Determined - No Hazard, submitted 2020-02-19”
    FAA · Feb. 2020 · grade A
  • FAA OE/AAA archive case, Building "MNK 7A", 81 ft AGL / 124 ft AMSL at 33.06439: Determined - No Hazard
    “ASN 2019-ASO-35733-OE: MNK 7A, building, 81 ft AGL, 124 ft AMSL, 33.06439,-80.03906, Determined - No Hazard, submitted 2019-12-04”
    FAA · Dec. 2019 · grade A
  • FAA OE/AAA archive case, Tower crane "MNK6A", 209 ft AGL / 254 ft AMSL at 33.06: Determined - No Hazard
    “ASN 2015-ASO-615-OE: MNK6A, tower crane, 209 ft AGL, 254 ft AMSL, 33.06239,-80.04182, Determined - No Hazard, submitted 2015-01-23”
    FAA · Jan. 2015 · grade A
  • Santee Cooper letter of intent filed Dec 23, 2025 for a CECPCN to build the Cros: application filed (letter of intent)
    “As indicated by the Letter of Intent filed by the Applicant with the Commission on December 23, 2025, Santee Cooper proposes to construct and operate a new 230 kV transmission line of 18.5 miles”
  • PSC notice of filing and public hearing for Santee Cooper's CECPCN application f: notice of filing and public hearing issued
    “Application of South Carolina Public Service Authority (Santee Cooper) for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of the Cross to Wassamassaw 230 kV Transmission Lines”
  • Santee Cooper project page: construction over a 1-year period starting mid-2026;: construction scheduled; in-service date stated
    “Santee Cooper plans to construct this transmission line over a 1-year period, starting in mid-2026 and the line will be in service by June 1, 2027”
  • Google filed for a state permit to draw 1.5 million gallons per day from an aquifer (Middendorf/Charleston aquifer) to cool the campus; the application drew opposition from residents, environmental groups, and other aqui
    “Google filed for a permit to draw 1.5 million gallons per day from an aquifer to cool the data center”
  • Historic opposition to Google's Berkeley groundwater withdrawal request (tripling to 549 MG/yr): public and conservation opposition, a BCD Council of Governments advisory recommendation to deny, and DHEC final permit app
    “The request was met with swift and strong opposition from the public and the conservation community.”
Site and other (2)
  • County code: 45015
    “Established in 2007, the Berkeley County operation was the company's first in South Carolina.”
  • Project status: expanding operating campus
    “This funding will expand our Berkeley County data center campus and support the continued construction of two new sites in Dorchester County”