Power and the grid
None energized or contracted yet
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- May 5, 2026Energy center plans filedPowerConneX files plans for an 800 MW gas-fired energy center to supply the data center (press). News report · May 2026
- Sept. 10, 2026State siting hearingThe Ohio Power Siting Board holds the adjudicatory hearing in Case 26-0196-EL-BGN; no decision yet. see Permits
- Not setGrid utility: none namedNo grid utility or state utility commission service docket for the campus was found as of Oct. 2026. Utility regulator · Oct. 2026
- The village's stipulation in the siting case recommends 40-plus conditions, including an 800 MW output cap; the cap limits generation and is not a campus load figure. News report · Oct. 2026
- Documents obtained by a local paper described a 1.8 GW substation and a 200 MW gas turbine center; the case as filed describes up to 800 MW, and the 200 MW may reflect an early phase (unverified). News report · Oct. 2026
- If the energy center ever connects to the grid, the deal says the parties will evaluate connecting to the village's municipal power utility. Local government · April 2026
Permits checklist
1 contested · 1 denied · 2 pending
State and village actions on record.
- !Development and supply agreement term summary (Resolution 06-2026) ContestedAshville Village Council · April 6, 2026: approved 5-1 as an emergency measure; referendum Nov. 3 Local government · April 2026
- ✕Annexation of about 400 acres DeniedAshville Village Council · Feb. 2, 2026: 4-2; does not affect the in-village parcel News report · Feb. 2026
- ◷Certificate for the Ashville Energy Center (26-0196-EL-BGN) PendingOhio Power Siting Board · Sept. 10, 2026: hearing held; village stipulation with 40-plus conditions; intervenors include residents Utility regulator · Sept. 2026
- ◷Air permit for the energy center PendingOhio EPA · Oct. 2026: considered separately; no permit number or decision found News report · Oct. 2026
What could slow it down
- HighReferendumVoters decide on Nov. 3 whether to overturn the village's approval of the development framework. News report · Oct. 2026
- HighPower plant not certifiedThe gas plant still needs a state siting certificate and a separate air permit, and residents have intervened. News report · Oct. 2026
- MediumLocal oppositionResidents cite higher utility bills, noise and environmental harm (press). News report · Oct. 2026
- WatchNo tenantNo data-center tenant is named in the agreement or press. Local government · Feb. 2026
1 case on record
- Decided Aug. 7, 2026 State ex rel. McNamara-Smith v. GrubeOhio Supreme Court Court filing · Aug. 2026the village fiscal officer had no authority to refuse to certify the referendum petition
Money on record
- Disputed: tax abatement (press says a 30-year full abatement is sought; the filed term summary shows only a contingent 15-year abatement for annexed land) News report · Oct. 2026
What happened, and what is due
- Feb. 2, 2026Permits Village council denies annexing about 400 acres of farmland for the project, 4-2 News report · Feb. 2026
- Feb. 26, 2026Money EdgeConneX's term summary offers up to $102M in community support Local government · Feb. 2026
- April 6, 2026Permits Council approves the development agreement framework 5-1 as an emergency measure Local government · April 2026
- May 5, 2026Power PowerConneX's plans for an 800 MW gas-fired energy center are reported News report · May 2026
- Aug. 7, 2026Legal Ohio Supreme Court rules the village could not refuse to certify the referendum petition Court filing · Aug. 2026
- Aug. 24, 2026Permits County elections board votes 4-0 to put the referendum on the Nov. 3 ballot News report · Aug. 2026
- Sept. 10, 2026Power State siting board holds its hearing on the gas plant Utility regulator · Sept. 2026
- Oct. 8, 2026Money Village receives a $3.5M payment from EdgeConneX weeks before the vote News report · Oct. 2026
- Oct. 12, 2026Permits A council attempt to repeal the resolution fails for lack of a second, keeping the referendum on the ballot News report · Oct. 2026
- Nov. 3, 2026Permits Referendum on the development agreement framework News report · Oct. 2026
Since May 2026: 1 FAA filing (May 2026): a 340 ft crane. FAA · May 2026
Specs
- Limited Industrial: existing zoning, where data centers are a permitted use (press) News report · Oct. 2026
Owners, partners and builders
- EdgeConneX Inc.: developer (owned by EQT)
- PowerConneX, Inc.: affiliate applying for the gas plant
- Ashville Village Council
- Ohio Power Siting Board
- Ohio EPA: air permit
- Village voters: Nov. 3 referendum
- Village of Ashville, Harrison Township and Teays Valley Local School District: community support payments
- Teays Valley Community Alliance and residents: intervenors and referendum petitioners
Open questions
- Data-center IT capacity and tenant.
- Siting board decision and final plant size.
- Referendum outcome.
55 records from 12 documents
Drawn from news reports, local government records, state agency records, utility regulator dockets and court filings, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (5)
- Project status: Proposed; site zoned Limited Industrial (data centers a permitted use under the 2024 zoning code); Development and Supply Agreement term summary approved Apr 6, 2026 but subject to a voter referendum on t“The Ohio Power Siting Board is reviewing the generating facility, while the Ohio Environmental Protection Agency will separately consider its air permit.”News report · Oct. 2026 · grade C
- The Village of Ashville's joint stipulation in the OPSB case recommends 40+ conditions including an 800-megawatt output cap on the Energy Center. Basis: a stipulated cap on the generating facility's output as summarized“signed a joint stipulation recommending more than 40 conditions involving water, noise, air quality, traffic, emergency response and an 800-megawatt output cap”News report · Oct. 2026 · grade C
- Village Resolution 06-2026 (the development/supply framework) goes to a Nov 3, 2026 referendum: the Ohio Supreme Court ruled Aug 7, 2026 that the resolution's emergency declaration was improperly justified and ordered th“The project — two data center buildings and a natural-gas power plant on about 195 acres — is headed for a Nov. 3 referendum after the Ohio Supreme Court ordered a citizen petition challenging the village's approval onto the ballot.”News report · Oct. 2026 · grade C
- Developer: EdgeConneX (data centers); PowerConneX (affiliated onsite generation company)“A related company, PowerConneX, is separately seeking Ohio Power Siting Board approval to build a natural gas-fired power plant of up to 800 megawatts on about 110 acres of the same property to supply the data centers”News report · Aug. 2026 · grade C
- On-site generation: 800 MW“A related company, PowerConneX, is separately seeking Ohio Power Siting Board approval to build a natural gas-fired power plant of up to 800 megawatts on about 110 acres of the same property to supply the data centers”News report · Aug. 2026 · grade C
Money and contracts (13)
- development and supply agreement: community support total 102000000 USD“To memorialize the Company's offer of up to $102,000,000 in support to the Village, Harrison Township ("Township") and Teays Valley Local School District ("Teays Valley"), plus new community authority ("NCA") charges.”Local government · April 2026 · grade A
- development and supply agreement: infrastructure escrow 35000000 USD“up to $35,000,000 escrow for EPA-mandated water/sewer/road improvements”Local government · April 2026 · grade A
- development and supply agreement: school payment 64000000 USD“$64,000,000 to Teays Valley contingent on school-board support + final OPSB permit + certificates of occupancy”Local government · April 2026 · grade A
- development and supply agreement: fire department support 3000000 USD“up to $3,000,000 Township Fire Dept.”Local government · April 2026 · grade A
- development and supply agreement: tax abatement contingent 10000000 USD“then as compensation for a 15-year, [75%] CRA Agreement approved by Village, the Company will: (a) contribute $10,000,000 to the Township”Local government · April 2026 · grade A
- development and supply agreement: grid connection evaluation“If the Energy Center connects to the electric grid, the Energy Center and Village will cooperate in good faith to evaluate connecting to the Village's municipal power utility”Local government · April 2026 · grade A
- Development and supply agreement (term summary): community support commitment 102000000 USD“To memorialize the Company's offer of up to $102,000,000 in support to the Village, Harrison Township ("Township") and Teays Valley Local School District ("Teays Valley"), plus new community authority ("NCA") charges.”Local government · Feb. 2026 · grade B
- EdgeConneX offer of up to $102 million in support to the Village, Harrison Township and Teays Valley, plus a possible additional $74 million tied to future annexation“To identify the possibility of an additional $74,000,000 to the Village, Township, and Teays Valley as compensation for future mutually agreed upon incentives”Local government · Feb. 2026 · grade B
- Press reports EdgeConneX 'seeking a 30-year full tax abatement' and a '$105 million to Teays Valley Schools over 15 years through the PILOT program' - neither figure appears in the filed term summary (which shows a conti“The company is also currently seeking a 30-year full tax abatement for the campus, located north of State Route 752 toward Weigand Road.”News report · Oct. 2026 · grade C
- Company seeking a 30-year full tax abatement for the campus north of State Route 752 toward Weigand Road“The company is also currently seeking a 30-year full tax abatement for the campus, located north of State Route 752 toward Weigand Road.”News report · Oct. 2026 · grade C
- Source record“The donation arrives weeks before Pickaway County voters decide the fate of the development agreement that would let EdgeConneX and an affiliated company build two data centers”News report · Oct. 2026 · grade C
- Village received a $3.5 million donation from EdgeConneX on Oct. 8, 2026 ($1M parks, $900k wastewater pump station, $1.6M South Metershed engineering)“The Village of Ashville received a $3.5 million donation from EdgeConneX Inc. on the morning of Oct. 8, the same company whose proposed data center development in the village is headed to a Nov. 3 referendum”News report · Oct. 2026 · grade C
- EdgeConneX donated $3.5 million to the Village on Oct 8, 2026 for parks, wastewater pump station and South Metershed engineering“The Village of Ashville received a $3.5 million donation from EdgeConneX Inc. on the morning of Oct. 8”News report · Oct. 2026 · grade C
Permits and government (11)
- Project identity: EdgeConneX data center, Village of Ashville, Pickaway County, OH - Pickaway County Parcel 01300350000100, approximately 195.368 acres within village limits, north of State Route 752 toward Weigand Road“The Company intends to obtain permits through the Village for authority to construct and operate two data center buildings (the "Data Center") with ancillary buildings and infrastructure on certain property within the Village”Local government · April 2026 · grade A
- Village of Ashville Council:“Jesse Burke-yay; Ron Teeters-yay; Jeremy Scoby-yay; Dave Rainey-yay; Darryl Glick-yay; Jeff Martin-no Adopted this the 6 th day of April, 2026”Local government · April 2026 · grade A
- Applicant is PowerConneX, Inc., an EdgeConneX affiliate. The Energy Center would: Application for a Certificate of Environmental Compatibility and Public Need (PowerConneX Ashville Energy Center, behind-the-meter natural“In the Matter of the Application of PowerConneX, Inc. for a Certificate of Environmental Compatibility and Public Need to Construct the PowerConneX Ashville Energy Center”Utility regulator · Sept. 2026 · grade B
- OE/AAA case for a 340-ft mobile crane filed as 'EDC CMH 11 and 12' at (39.73459,: Determined - No Hazard“ASN 2026-AGL-7257-OE: EDC CMH 11 and 12, Mobile Crane, 340 ft AGL, 1040 ft AMSL, 39.73459,-82.96788, Determined - No Hazard, submitted 2026-05-26”FAA · May 2026 · grade B
- FAA OE/AAA records a 340-ft mobile crane filed as 'EDC CMH 11 and 12' (ASN 2026-AGL-7257-OE, submitted May 26, 2026) at the documented Ashville parcel area - EdgeConneX's filer designation at the campus's own site, and the“ASN 2026-AGL-7257-OE: EDC CMH 11 and 12, Mobile Crane, 340 ft AGL, 1040 ft AMSL, 39.73459,-82.96788, Determined - No Hazard, submitted 2026-05-26”FAA · May 2026 · grade B
- Ohio EPA will separately consider the project's air permit; no permit number or : Air permit - to be considered separately“The Ohio Power Siting Board is reviewing the generating facility, while the Ohio Environmental Protection Agency will separately consider its air permit.”News report · Oct. 2026 · grade C
- Ohio EPA considers the generating facility's air permit separately from the OPSB: Air permit for the Ashville Energy Center under separate Ohio EPA consideration (no permit number or decision in retrieved sources)“The Ohio Power Siting Board is reviewing the generating facility, while the Ohio Environmental Protection Agency will separately consider its air permit.”News report · Oct. 2026 · grade C
- Referendum on Resolution 06-2026 stays on the Nov. 3, 2026 ballot: a later repeal resolution (16-2026) failed for lack of a second in October 2026; petition drive gathered 669 valid signatures vs 498 required“The council member said the village's referendum on Resolution 06-2026 will remain on the Nov. 3 ballot after a later repeal resolution failed for lack of a second.”News report · Oct. 2026 · grade C
- Onsite natural-gas generation facility of up to 800 MW on about 110 acres of the: Application under review (PowerConneX Ashville Energy Center)“The village has intervened in the siting case and signed a joint stipulation recommending more than 40 conditions involving water, noise, air quality, traffic, emergency response and an 800-megawatt output cap.”News report · Sept. 2026 · grade C
- Pickaway County Board of Elections:“The Pickaway County Board of Elections voted 4-0 Monday night to allow a referendum on Ashville's data center development agreement to appear on the Nov. 3 ballot, according to the advocacy group that organized the petition drive.”News report · Aug. 2026 · grade C
- Village of Ashville Council:“By a 4-2 vote, council members denied the annexation of approximately 400 acres of farmland sought in connection with the EdgeConneX data center project.”News report · Feb. 2026 · grade C
Legal (1)
- Resident referendum to overturn Resolution 06-2026 will appear on the Nov 3 ballot after the Ohio Supreme Court ruled the emergency declaration was improperly justified“Residents opposed to the project gathered signatures for a referendum petition anyway, and the dispute reached the Ohio Supreme Court, which ruled Aug. 7 that the emergency declaration was improperly justified”News report · Oct. 2026 · grade C
Site and other (4)
- County code: 39129“currently Pickaway County Parcel Number 01300350000100 consisting of approximately 195.368 acres”Local government · April 2026 · grade A
- Data center buildings: 2“construct and operate two data center buildings (the "Data Center") with ancillary buildings and infrastructure”Local government · April 2026 · grade A
- Village administrator said the company was working to annex part of the land, with construction ideally starting in spring of the following year“Village administrator Bert Cline told WBNS that the company was currently working to annex part of the land, with construction ideally starting in spring of next year.”News report · Oct. 2026 · grade C
- Residents cited increased utility bills, noise pollution and environmental impact“Residents have expressed their displeasure with the potential data center, citing concerns about increased utility bills, noise pollution, and their environmental impact.”News report · Oct. 2026 · grade C