Power and the grid
None energized or contracted yet
Permits checklist
1 granted · 1 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- ✓Zoning code limiting data centers to industrial districts GrantedGallatin City Council · Sept. 1, 2026: adopted on second reading; applies to new projects News report · Sept. 2026
- –Checked, nothing on file: Utility service
What could slow it down
- HighExpansion power is not securedOnly about 40 MW was available in 2022, and the 100 MW-plus plan depends on utility and TVA transmission upgrades with no upgraded-capacity agreement announced. News report · May 2022
- MediumHigher TVA costs for new data center loadTVA's Aug. 2026 rate change adds an upfront capacity charge of about $1.5 million per MW for new or expanded data center load above the first 5 MW. News report · Aug. 2026
- MediumPartner exit and no named customerArcher left in Dec. 2024, and no tenant has been named. News report · Oct. 2026
- WatchNew local data center limitsA moratorium and a new zoning code apply to new applications; any expansion adding square footage could be caught by them. Local government · Sept. 2026
Money on record
What happened, and what is due
- May 12, 2022Site Evoque and Archer announce a joint venture for a 100 MW-plus, 500,000 sq ft campus anchored by Archer's existing shell News report · May 2022
- June 16, 2023Construction Evoque says crews will be on site within 45 days to fit out its first 12 MW building (press) Local government · June 2023
- Dec. 18, 2024Money Archer announces it sold its stake and exited the Gallatin project News report · Dec. 2024
- Aug. 20, 2026Power TVA board approves wholesale rate changes for data center load, including an upfront capacity charge for new load News report · Aug. 2026
- Sept. 1, 2026Permits Gallatin council adopts a zoning code limiting data centers to industrial districts; this campus predates it News report · Sept. 2026
- Sept. 15, 2026Permits Council approves on first reading a 12-month moratorium on new data center applications, exempting approved sites Local government · Sept. 2026
Specs
Owners, partners and builders
- Evoque Data Center Solutions: current owner side (press)
- Archer Datacenters: original developer and operator, exited Dec. 2024
- Gallatin Department of Electricity: municipal distributor
- Tennessee Valley Authority: wholesale supplier
- Gallatin City Council: zoning and moratorium
Open questions
- How much of the planned capacity is built and energized.
- A TVA or GDE agreement for the expansion.
- A named customer.
65 records from 21 documents
Drawn from news reports, local government records, company statements, securities filings, public and commercial datasets and court filings, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (18)
- 2025-1 and 2025-2; 2025-3 and 2025-4; 2025-5 and 2025-6) (EDGAR ABS-15G; EDGAR depositor name Phoenix Data Center Acquisitions LLC); Collateral is Centersquare's colocation portfolio; per-property schedules are not publi“with the proposed offering of Centersquare Issuer, LLC and Centersquare Co-Issuer, LLC Secured Data Center Revenue Term Notes, Series 2024-1 and Series 2024-2”SEC filing · Sept. 2024 · grade A
- Announced: May 12, 2022“Leading data center provider Evoque, a portfolio company of Brookfield Infrastructure Partners has entered a joint venture with Archer Datacenters to bring to market over 100MW of power capacity”Company · May 2022 · grade A
- Project status: shell - phase 1 powered shell exists; the over-100 MW expansion remains announced only, with no evidence of expansion construction as of Oct 2026; operator rebranded to Centersquare (Csquare) in 2024 and“One year ago, Dallas-based Evoque stepped in as the senior partner in a joint venture on a 61-acre site in Gallatin, where the shell of one data center stands now”Local government · June 2023 · grade B
- In Jun 2023 Evoque's CEO said crews would be on site within 45 days to install equipment in the first building (12 MW power capacity) and that three companies each wanted the full building; no later source retrieved conf“Crews will be on-site within 45 days to install equipment in Evoque's first building, which has power capacity of 12 megawatts.”Local government · June 2023 · grade B
- Utility service status: GDE adjacent Industrial Substation energized by Apr 2022 (50 MVA); 40+ MW available to the existing shell; no campus service agreement public; expansion beyond that contingent on GDE/TVA transmiss“The new Industrial Substation that is located beside the proposed data center site has been energized and is serving load within the Industrial Park.”Court filing · April 2022 · grade B
- The 82,000 sq ft shell exists with 40 MW available from GDE, and a Jun 2023 fit-out of the 12 MW first building was announced“The design capacity is not a statement of vacant power.”News report · Oct. 2026 · grade C
- Current guides still market the site as Csquare Nashville at 1398 Gateway Drive in Gallatin with a 100 MW design across 500,000 square feet and an 82,500 sq ft first phase - a design/marketing figure, not commissioned ca“Csquare Nashville is at 1398 Gateway Drive in Gallatin. The campus has a 100 MW design across 500,000 square feet.”News report · Oct. 2026 · grade C
- Evoque's initial building costed at $132M; site can reach 150 MW if customer demand fills it, at $500M-$1B+ total investment (Evoque's Mullee, Jun 2023)“On this site, we can do 150 megawatts if we want to. It's a wide range, but we're talking $500 million to $1 billion or more, if we have enough customers to fill it”News report · June 2023 · grade C
- Source record“On this site, we can do 150 megawatts if we want to. It's a wide range, but we're talking $500 million to $1 billion or more”News report · June 2023 · grade C
- June 2023: crews due on site within 45 days to fit out the first building (12 MW, about $132M at $10-12M per MW); three prospects each wanted the full building; 25-30 on-site jobs expected at build-out“Crews will be on-site within 45 days to install equipment in Evoque's first building, which has power capacity of 12 megawatts.”News report · June 2023 · grade C
- Stated campus size: 100 MW“The company's Gallatin campus will ultimately cover more than 61 acres, with over 500K SF of total data center space and over 100 MW of capacity.”News report · May 2022 · grade C
- Site acres: 61 acres“The company's Gallatin campus will ultimately cover more than 61 acres, with over 500K SF of total data center space and over 100 MW of capacity.”News report · May 2022 · grade C
- Building sq ft: 500000 sq ft“The company's Gallatin campus will ultimately cover more than 61 acres, with over 500K SF of total data center space and over 100 MW of capacity.”News report · May 2022 · grade C
- Power reality vs headline: only 'over 40 MW of available power today' exists, from Gallatin Department of Electricity's adjacent substation, serving Archer's existing powered shell. The headline 100+ MW is a full-buildou“with over 40 MW of available power today from A Gallatin Department of Electricity (GDE) substation... The campus could reach more than 100MW at full buildout through updated transmission capacity of GDE and Tennessee Valley Authority (TVA)”News report · May 2022 · grade C
- Evoque-Archer JV announced May 2022: $200M equity commitment, 500,000 sq ft campus plan on the Gallatin site by Meta's campus“Evoque is partnering with Archer Datacenters on a 100MW campus in Gallatin, Tennessee, as the company pivots its focus toward hyperscalers.”News report · May 2022 · grade C
- The existing 82,000 sq ft shell had over 40 MW of available power from GDE's adjacent substation at the May 2022 announcement“The original 28.5 acre campus is anchored by an 82,000 square foot data center shell, with over 40MW of available power today from Gallatin Department of Electricity's adjacent substation.”News report · May 2022 · grade C
- The 100+ MW buildout was expressly contingent on GDE/TVA transmission capacity being updated; no source retrieved shows that upgrade contracted or the expansion phases under construction.“The long-term expandability of 100+MW is possible in concert with the continuously updated transmission capacity of GDE and Tennessee Valley Authority ("TVA").”News report · May 2022 · grade C
- Queue MW 100 VERIFIED as campus design total: over 100 MW and over 500K SF at full build; first building 12 MW; 40 MW available from Gallatin Department of Electricity adjacent substation at JV announcement“That footprint will incorporate a 28.5-acre site on which Archer already operates an 82K SF data center shell with 40 MW of available power.”News report · May 2022 · grade C
Money and contracts (5)
- Entity and property-code keys“Phoenix Infrastructure LLC 3100 Olympus Boulevard, Suite 510 Coppell, Texas 75019”SEC filing · Nov. 2025 · grade A
- Tenant: none named“The campus will help meet the growing needs of data center space in the region, including serving cloud providers and large companies, Evoque says.”News report · Oct. 2026 · grade C
- JV partner exit / stake sale: sale of Archer's stake in its first Tennessee data center project“Archer Datacenters has sold its stake in its first data center project in Tennessee and acquired land for a new site in Minnesota.”News report · Dec. 2024 · grade C
- Announced investment: 200 USD millions“Evoque Data Center Solutions plans to invest $200M in a new campus in Gallatin, Tennessee”News report · May 2022 · grade C
- joint venture / development partnership: JV to bring the Gallatin campus to market; $200M earmarked by Evoque 200 USD millions“Evoque announced a joint venture with Archer Datacenters to bring to market over 100MW of power capacity and over 500,000 square feet of data center space in Gallatin, Tennessee”News report · May 2022 · grade C
Permits and government (6)
- The 2026 Gallatin moratorium draft exempts approved site plans/permits and non-expanding amendments - the existing Evoque/Centersquare campus is therefore not frozen by the moratorium as drafted“Amendments to existing approved Data Centers, provided that they do not request additional data center space (in square feet) than what was previously approved.”Local government · Sept. 2026 · grade B
- Gallatin City Council:“The City Council of the City of Gallatin does hereby enact a 12-month moratorium on accepting and processing new applications for data center development.”Local government · Sept. 2026 · grade B
- Gallatin City Council:“RESOLUTION OF THE CITY COUNCIL OF THE CITY OF GALLATIN, SUMNER COUNTY, TENNESSEE DIRECTING THE GALLATIN MUNICIPAL PLANNING COMMISSION TO EVALUATE A POTENTIAL MORATORIUM ON DATA CENTERS”Local government · July 2026 · grade B
- Retail service to the Gallatin campus is provided by the Gallatin Department of : service framework: municipal TVA distributor (GDE); no state retail docket exists“The long-term expandability of 100+MW is possible in concert with the continuously updated transmission capacity of GDE and Tennessee Valley Authority ("TVA").”Company · May 2022 · grade B
- Gallatin City Council:“On second reading Sept. 1, Gallatin City Council adopted a comprehensive zoning ordinance (ZOCO) as amended”News report · Sept. 2026 · grade C
- Per TVA's release and a PowerCompute Form 8-K summary (Oct 6, 2026): the change : TVA Board approved wholesale rate structure changes for data center load, Aug 20, 2026 - in effect as of Oct 19, 2026; Gallatin Department“On August 20, 2026, the TVA Board approved changes to its wholesale rate structure that, in TVA's words, protect residential and manufacturing customers from subsidizing costs tied to data center load growth”News report · Aug. 2026 · grade C
Site and other (7)
- County code: 47165“Gallatin is a city in and the county seat of Sumner County, Tennessee, United States.”Dataset · Oct. 2026 · grade B
- Project status: operating shell expanding“Archer operates the site and built the original infrastructure, which was expected to be completed earlier in 2022”News report · Dec. 2024 · grade C
- Site address: 1398 Gateway Dr, Gallatin, TN 37066“At the time of the partnership, the 28.5-acre campus at 1398 Gateway Dr featured an 82,000 square-foot (7,600 sqm) data center shell”News report · Dec. 2024 · grade C
- Archer Datacenters SOLD its stake and exited its inaugural Gallatin project in Dec 2024 (announced with its Faribault MN land purchase); content agrees the exit is Dec 2024 (spot-check s.4 item 12).]“In the same LinkedIn post, Archer said it had exited its inaugural project in the Gallatin area of Nashville, Tennessee.”News report · Dec. 2024 · grade C
- Archer sold its stake and exited the Gallatin project (disclosed Dec 18, 2024 alongside its Faribault, Minnesota land purchase); current ownership is the Evoque side“Archer Datacenters has sold its stake in its first data center project in Tennessee”News report · Dec. 2024 · grade C
- Site location: 1398 Gateway Drive, Gallatin, Tennessee, adjacent to Meta's Gallatin campus“Archer already operates a data center on the site, which sits next to a hyperscale campus being developed by Facebook parent company Meta.”News report · May 2022 · grade C
- Existing shell sq ft: 82000 sq ft“The original 28.5 acre campus is anchored by an 82,000 square foot data center shell”News report · May 2022 · grade C