Data center profile · Gateway Drive, Gallatin Industrial Center, Gallatin, Sumner County, Tennessee

Evoque Gallatin Campus (former Archer joint venture)

Gallatin, Tennessee data center campus on existing 82,000 sq ft shell with about 40 MW available; planned 100 MW-plus buildout needs utility and TVA upgrades.

Existing shell, buildout unconfirmed. An existing 82,000 sq ft shell with over 40 MW available anchored the 2022 joint venture; in June 2023 Evoque planned a first 12 MW fit-out. No record shows how much of the 100 MW-plus plan is built or in service.
40 MW+
available power today at the 2022 announcement
from the Gallatin Department of Electricity's adjacent substation, serving the existing shell
100 MW+
full-buildout capacity, as announced in 2022
conditioned on future utility and TVA transmission upgrades; Evoque's CEO said in 2023 the site could do 150 MW if customers fill it
12 MW
first Evoque building to be fitted out (June 2023, press)
about $132M at the quoted cost per MW
$200M
investment announced in 2022 (press)
equity commitment for the joint venture
OperatorEvoque Data Center Solutions (Archer Datacenters operated the original site and exited in Dec. 2024)
CustomerNone named; targets cloud providers and large companies
Planned IT capacity80 MW at full build-out (our estimate from the company's 0.1 GW campus power figure)
First building in serviceOur estimate: 2027 (range 2026 to 2027).
Next stepNone published; final Gallatin moratorium vote pending
Power

Power and the grid

None energized or contracted yet

Gallatin Department of Electricity substation (TVA power)Existing capacity; expansion not secured
40 MW
over 40 MW available at the 2022 announcement for the existing shell; the 100 MW-plus buildout needs future GDE and TVA upgrades Company · May 2022
Proposed
Permits

Permits checklist

1 granted · 1 checked, nothing on file

Approvals a campus like this normally needs, and what we found.

Risks

What could slow it down

Money

Money on record

$200M
joint venture equity commitment (press)
announced May 2022 News report · May 2022
$132M
first building cost (press)
quoted by Evoque in June 2023; a full buildout could cost $500 million to $1 billion or more if customers fill it News report · June 2023
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. May 12, 2022
    Site Evoque and Archer announce a joint venture for a 100 MW-plus, 500,000 sq ft campus anchored by Archer's existing shell News report · May 2022
  2. June 16, 2023
    Construction Evoque says crews will be on site within 45 days to fit out its first 12 MW building (press) Local government · June 2023
  3. Dec. 18, 2024
    Money Archer announces it sold its stake and exited the Gallatin project News report · Dec. 2024
  4. Aug. 20, 2026
    Power TVA board approves wholesale rate changes for data center load, including an upfront capacity charge for new load News report · Aug. 2026
  5. Sept. 1, 2026
    Permits Gallatin council adopts a zoning code limiting data centers to industrial districts; this campus predates it News report · Sept. 2026
  6. Sept. 15, 2026
    Permits Council approves on first reading a 12-month moratorium on new data center applications, exempting approved sites Local government · Sept. 2026
The buildings

Specs

82,000 sq ft
existing data center shell on the original 28.5 acres
61 acres
planned campus, with over 500,000 sq ft of data center space
Who is involved

Owners, partners and builders

Owners and developers
  • Evoque Data Center Solutions: current owner side (press)
  • Archer Datacenters: original developer and operator, exited Dec. 2024
Power
  • Gallatin Department of Electricity: municipal distributor
  • Tennessee Valley Authority: wholesale supplier
Decision-makers
  • Gallatin City Council: zoning and moratorium
Still unknown

Open questions

Where this comes from

65 records from 21 documents

Drawn from news reports, local government records, company statements, securities filings, public and commercial datasets and court filings, each kept with its date and source. The bar shows documents by type.

News report 12Local government 3Company 3SEC filing 2Dataset 1Court filing 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (18)
  • 2025-1 and 2025-2; 2025-3 and 2025-4; 2025-5 and 2025-6) (EDGAR ABS-15G; EDGAR depositor name Phoenix Data Center Acquisitions LLC); Collateral is Centersquare's colocation portfolio; per-property schedules are not publi
    “with the proposed offering of Centersquare Issuer, LLC and Centersquare Co-Issuer, LLC Secured Data Center Revenue Term Notes, Series 2024-1 and Series 2024-2”
  • Announced: May 12, 2022
    “Leading data center provider Evoque, a portfolio company of Brookfield Infrastructure Partners has entered a joint venture with Archer Datacenters to bring to market over 100MW of power capacity”
  • Project status: shell - phase 1 powered shell exists; the over-100 MW expansion remains announced only, with no evidence of expansion construction as of Oct 2026; operator rebranded to Centersquare (Csquare) in 2024 and
    “One year ago, Dallas-based Evoque stepped in as the senior partner in a joint venture on a 61-acre site in Gallatin, where the shell of one data center stands now”
  • In Jun 2023 Evoque's CEO said crews would be on site within 45 days to install equipment in the first building (12 MW power capacity) and that three companies each wanted the full building; no later source retrieved conf
    “Crews will be on-site within 45 days to install equipment in Evoque's first building, which has power capacity of 12 megawatts.”
  • Utility service status: GDE adjacent Industrial Substation energized by Apr 2022 (50 MVA); 40+ MW available to the existing shell; no campus service agreement public; expansion beyond that contingent on GDE/TVA transmiss
    “The new Industrial Substation that is located beside the proposed data center site has been energized and is serving load within the Industrial Park.”
  • The 82,000 sq ft shell exists with 40 MW available from GDE, and a Jun 2023 fit-out of the 12 MW first building was announced
    “The design capacity is not a statement of vacant power.”
  • Current guides still market the site as Csquare Nashville at 1398 Gateway Drive in Gallatin with a 100 MW design across 500,000 square feet and an 82,500 sq ft first phase - a design/marketing figure, not commissioned ca
    “Csquare Nashville is at 1398 Gateway Drive in Gallatin. The campus has a 100 MW design across 500,000 square feet.”
  • Evoque's initial building costed at $132M; site can reach 150 MW if customer demand fills it, at $500M-$1B+ total investment (Evoque's Mullee, Jun 2023)
    “On this site, we can do 150 megawatts if we want to. It's a wide range, but we're talking $500 million to $1 billion or more, if we have enough customers to fill it”
  • Source record
    “On this site, we can do 150 megawatts if we want to. It's a wide range, but we're talking $500 million to $1 billion or more”
  • June 2023: crews due on site within 45 days to fit out the first building (12 MW, about $132M at $10-12M per MW); three prospects each wanted the full building; 25-30 on-site jobs expected at build-out
    “Crews will be on-site within 45 days to install equipment in Evoque's first building, which has power capacity of 12 megawatts.”
  • Stated campus size: 100 MW
    “The company's Gallatin campus will ultimately cover more than 61 acres, with over 500K SF of total data center space and over 100 MW of capacity.”
  • Site acres: 61 acres
    “The company's Gallatin campus will ultimately cover more than 61 acres, with over 500K SF of total data center space and over 100 MW of capacity.”
  • Building sq ft: 500000 sq ft
    “The company's Gallatin campus will ultimately cover more than 61 acres, with over 500K SF of total data center space and over 100 MW of capacity.”
  • Power reality vs headline: only 'over 40 MW of available power today' exists, from Gallatin Department of Electricity's adjacent substation, serving Archer's existing powered shell. The headline 100+ MW is a full-buildou
    “with over 40 MW of available power today from A Gallatin Department of Electricity (GDE) substation... The campus could reach more than 100MW at full buildout through updated transmission capacity of GDE and Tennessee Valley Authority (TVA)”
  • Evoque-Archer JV announced May 2022: $200M equity commitment, 500,000 sq ft campus plan on the Gallatin site by Meta's campus
    “Evoque is partnering with Archer Datacenters on a 100MW campus in Gallatin, Tennessee, as the company pivots its focus toward hyperscalers.”
  • The existing 82,000 sq ft shell had over 40 MW of available power from GDE's adjacent substation at the May 2022 announcement
    “The original 28.5 acre campus is anchored by an 82,000 square foot data center shell, with over 40MW of available power today from Gallatin Department of Electricity's adjacent substation.”
  • The 100+ MW buildout was expressly contingent on GDE/TVA transmission capacity being updated; no source retrieved shows that upgrade contracted or the expansion phases under construction.
    “The long-term expandability of 100+MW is possible in concert with the continuously updated transmission capacity of GDE and Tennessee Valley Authority ("TVA").”
  • Queue MW 100 VERIFIED as campus design total: over 100 MW and over 500K SF at full build; first building 12 MW; 40 MW available from Gallatin Department of Electricity adjacent substation at JV announcement
    “That footprint will incorporate a 28.5-acre site on which Archer already operates an 82K SF data center shell with 40 MW of available power.”
Money and contracts (5)
  • Entity and property-code keys
    “Phoenix Infrastructure LLC 3100 Olympus Boulevard, Suite 510 Coppell, Texas 75019”
  • Tenant: none named
    “The campus will help meet the growing needs of data center space in the region, including serving cloud providers and large companies, Evoque says.”
  • JV partner exit / stake sale: sale of Archer's stake in its first Tennessee data center project
    “Archer Datacenters has sold its stake in its first data center project in Tennessee and acquired land for a new site in Minnesota.”
  • Announced investment: 200 USD millions
    “Evoque Data Center Solutions plans to invest $200M in a new campus in Gallatin, Tennessee”
  • joint venture / development partnership: JV to bring the Gallatin campus to market; $200M earmarked by Evoque 200 USD millions
    “Evoque announced a joint venture with Archer Datacenters to bring to market over 100MW of power capacity and over 500,000 square feet of data center space in Gallatin, Tennessee”
Permits and government (6)
  • The 2026 Gallatin moratorium draft exempts approved site plans/permits and non-expanding amendments - the existing Evoque/Centersquare campus is therefore not frozen by the moratorium as drafted
    “Amendments to existing approved Data Centers, provided that they do not request additional data center space (in square feet) than what was previously approved.”
  • Gallatin City Council:
    “The City Council of the City of Gallatin does hereby enact a 12-month moratorium on accepting and processing new applications for data center development.”
  • Gallatin City Council:
    “RESOLUTION OF THE CITY COUNCIL OF THE CITY OF GALLATIN, SUMNER COUNTY, TENNESSEE DIRECTING THE GALLATIN MUNICIPAL PLANNING COMMISSION TO EVALUATE A POTENTIAL MORATORIUM ON DATA CENTERS”
  • Retail service to the Gallatin campus is provided by the Gallatin Department of : service framework: municipal TVA distributor (GDE); no state retail docket exists
    “The long-term expandability of 100+MW is possible in concert with the continuously updated transmission capacity of GDE and Tennessee Valley Authority ("TVA").”
  • Gallatin City Council:
    “On second reading Sept. 1, Gallatin City Council adopted a comprehensive zoning ordinance (ZOCO) as amended”
  • Per TVA's release and a PowerCompute Form 8-K summary (Oct 6, 2026): the change : TVA Board approved wholesale rate structure changes for data center load, Aug 20, 2026 - in effect as of Oct 19, 2026; Gallatin Department
    “On August 20, 2026, the TVA Board approved changes to its wholesale rate structure that, in TVA's words, protect residential and manufacturing customers from subsidizing costs tied to data center load growth”
Site and other (7)
  • County code: 47165
    “Gallatin is a city in and the county seat of Sumner County, Tennessee, United States.”
  • Project status: operating shell expanding
    “Archer operates the site and built the original infrastructure, which was expected to be completed earlier in 2022”
  • Site address: 1398 Gateway Dr, Gallatin, TN 37066
    “At the time of the partnership, the 28.5-acre campus at 1398 Gateway Dr featured an 82,000 square-foot (7,600 sqm) data center shell”
  • Archer Datacenters SOLD its stake and exited its inaugural Gallatin project in Dec 2024 (announced with its Faribault MN land purchase); content agrees the exit is Dec 2024 (spot-check s.4 item 12).]
    “In the same LinkedIn post, Archer said it had exited its inaugural project in the Gallatin area of Nashville, Tennessee.”
  • Archer sold its stake and exited the Gallatin project (disclosed Dec 18, 2024 alongside its Faribault, Minnesota land purchase); current ownership is the Evoque side
    “Archer Datacenters has sold its stake in its first data center project in Tennessee”
  • Site location: 1398 Gateway Drive, Gallatin, Tennessee, adjacent to Meta's Gallatin campus
    “Archer already operates a data center on the site, which sits next to a hyperscale campus being developed by Facebook parent company Meta.”
  • Existing shell sq ft: 82000 sq ft
    “The original 28.5 acre campus is anchored by an 82,000 square foot data center shell”