Data center profile · Cameron County, Texas

Fluidstack Cameron County Campus

Data center campus developed by Fluidstack in Cameron County, Texas, on grid power; about 1.2 GW of IT capacity planned for the first phase.

Site work under way. Building permit granted; FAA airspace clearance pending. A utility power agreement or capacity reservation is on record, but no signed service agreement yet. Newest record Oct. 2026.
The campus, Lower-resolution satellite image, Oct. 17, 2026
1,500 MW
campus power the company states, first phase
facility power, not split into IT capacity
1,100
acres in the site
2029+
first building in service, our estimate
no dated power path yet; no company target on record
OperatorFluidstack
CustomerNone named
Planned IT capacity1.2 GW for the first phase; full build-out not stated (our estimate from the company or utility power figure)
First building in serviceOur estimate: 2029 or later (no dated power path yet).
The site

The site from above

Satellite overview
Lower-resolution satellite image, Oct. 17, 2026.
Power

Power and the grid

The plan on record is a grid connection. An interconnection study is under way.

We checked utility filings, regulator dockets and air-permit records for this campus.

Permits

Permits checklist

1 pending · 1 granted · 4 checked, nothing on file

Approvals a campus like this normally needs, and what we found.

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Sept. 10, 2026
    Permits Building permit issued by Cameron County. Local government · Sept. 2026
  2. Oct. 2026
    Power FAA OE/AAA holds a 22-case transmission tower series described as 'Power line for datacenter. FAA · Oct. 2026
Construction activity

Satellite captures by quarter

Since Sept. 2025: 3 satellite captures.

Satellite
’26
Dot size: records in the quarter, largest = 1. Two-digit years mark each first quarter.
Who is involved

Owners, partners and builders

Owners and developers
  • Fluidstack, developer
Power and utilities
  • AEP Texas, utility
Still unknown

Open questions

Where this comes from

39 records from 6 documents

Drawn from state agency records, local government records, company statements, satellite captures, news reports and public and commercial datasets, each kept with its date and source. The bar shows documents by type.

State agency 1Local government 1Company 1Satellite 1News report 1Dataset 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (3)
  • Stated campus size: 1,500 MW
    “This is planned to support up to 1.5 GW of capacity”
  • County code: 48061
    “in the unincorporated area of Cameron County near Valley International Airport in Harlingen, Texas”
  • Site acreage: 1100 acres
    “The 1,100-plus-acre campus sits east of FM 509 and west of FM 106, near Valley International Airport in Harlingen”
Money and contracts (3)
  • Project status: under construction
    “We've begun construction on the $4 billion first phase of our AI data center campus in Cameron County, Texas”
  • Announced investment: 4000000000 USD
    “We've begun construction on the $4 billion first phase of our AI data center campus”
  • Cameron County states it is not providing a tax abatement for this development.
    “Cameron County is not providing a tax abatement for this development”
Permits and government (26)
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 01”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 16”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 15”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 14”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 13”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 12”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 11”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 10”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 09”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 08”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 07”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 06”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 05”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 04”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 03”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 02”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 17”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 16”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 15”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 14”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 13”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA: filed
    “Power line for datacenter and BESS 05”
    FAA · Oct. 2026 · grade A
  • FAA OE/AAA holds a 22-case transmission tower series described as 'Power line for datacenter and BESS' within 5 km of the site reference point (110 ft towers, ASNs 2026-ASW-1174-OE through 2026-ASW-1313-OE in the retriev
    “Power line for datacenter and BESS”
    FAA · Oct. 2026 · grade A
  • building permit: issued
    “Future permits will be required for Fluidstack to begin building construction”
  • Campus name: Fluidstack Cameron County AI data center campus
    “a worksite permit has been issued to Fluidstack for the construction of a closed-loop-technology data center facility”
  • Announced: Sept. 10, 2026
    “Cameron County is providing notice to the public that a worksite permit has been issued to Fluidstack for the construction of a closed-loop-technology data center facility”

Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).