Google's 403-acre campus in Hermantown, Minnesota, with a 15-year Minnesota Power contract (adds 300 MW wind, 400 MW storage); city permit vote nears.

Permit vote pending. Hermantown adopted the environmental review Oct. 5, 2026; the special use permit goes to the Planning and Zoning Commission Oct. 20 and the City Council Oct. 26. Minnesota Power's service contract with Google awaits state approval. No MW figure disclosed.
403 acres
campus site
Google confirmed the project Mar. 3, 2026 (press)
15 years
Minnesota Power service contract term
filed for state approval April 2026
300 MW
new wind on Minnesota Power's system under the deal
plus 400 MW of battery storage; grid resources, not campus load
$600M-$800M
benefit to existing customers the utility estimates
over the 15-year term
OperatorGoogle (Mortenson filed the original permit applications)
CustomerGoogle (own use)
First building in serviceOur estimate: 2028 (range 2027 to 2030).
Next deadlineOct. 2026: Planning and Zoning Commission takes up the special use permit; City Council set to vote Oct. 26
Power

Power and the grid

Contracted, size not disclosed

Sources on record, size not disclosed
Related generation and energy contracts (context, not added to campus supply)

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. March 3, 2026
    Service contract announced
    Google says its contract with Minnesota Power will see 700 MW of clean-energy resources developed (wind plus storage). News report · March 2026
  2. April 2026
    Filed with state regulators
    Minnesota Power asks the state utility commission to approve the 15-year contract and related rate changes. see Permits
  3. Not set
    State decision: pending
    No decision was found as of Oct. 2026; the Attorney General's office has filed comments. Utility regulator · Oct. 2026
Permits

Permits checklist

2 withdrawn · 2 pending · 2 granted

City approvals, environmental review and the utility contract on record.

Risks

What could slow it down

Lawsuits

1 case on record

Money

Money on record

$5M
Google energy-impact funding for lower-income customers
in the service contract Utility regulator · April 2026
$600M-$800M
utility-estimated benefit to existing customers
$42M+
for local schools in the dropped tax-break draft
over 28 years; Google withdrew the request Oct. 2026 (press) News report · Oct. 2026
~$650M
first phase, per chamber-cited reporting; full build possibly billions
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Oct. 20, 2025
    Permits Council rezones residential land for 'Project Loon', 4-0, before Google is named; about 300 people crowd the hearing News report · Oct. 2025
  2. Nov. 5, 2025
    Legal City receives a lawsuit over the project; a state petition had sought an environmental worksheet Local government · Nov. 2025
  3. Nov. 10, 2025
    Permits Mortenson withdraws the permit applications for more public engagement Local government · Nov. 2025
  4. March 3, 2026
    Power Google confirms the project and a service contract with Minnesota Power Local government · Oct. 2026
  5. April 2026
    Power Minnesota Power files the 15-year contract for state approval Utility regulator · April 2026
  6. May 4, 2026
    Money Council tables the project agreements after a public hearing Local government · May 2026
  7. Oct. 5, 2026
    Permits Council adopts the final environmental review Local government · Oct. 2026
  8. Oct. 15, 2026
    Money Google drops its request for city tax breaks (press) News report · Oct. 2026
  9. Oct. 2026
    Permits Planning and Zoning Commission takes up the special use permit News report · Oct. 2026
  10. Oct. 26, 2026
    Permits City Council to consider the permit and related agreements News report · Oct. 2026
The buildings

Specs

403 acres
campus site (press)
5 to 10 years
full build-out estimate (press)
Who is involved

Owners, partners and builders

Owners
  • Google: owner and user
  • Mortenson: builder that filed the first applications
Decision-makers
  • Hermantown City Council and Planning and Zoning Commission
  • Minnesota Public Utilities Commission: service contract
  • Minnesota Environmental Quality Board: transmission review
Power partners
  • Minnesota Power (ALLETE): serving utility
Advisers
  • Braun Intertec: third-party technical review of the environmental study
Still unknown

Open questions

Where this comes from

26 records from 7 documents

Drawn from news reports, local government records and utility regulator dockets, each kept with its date and source. The bar shows documents by type.

News report 5Local government 1Utility regulator 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (2)
  • Minnesota Power is the contracted supplier (ESA in PUC Docket 26-159). The expected power draw of the Hermantown campus has not been stated by Google, Minnesota Power or the PUC filing summary - the only MW in this recor
    “The expected power draw of the data center has not been stated.”
  • Minnesota Power-Google Electric Service Agreement: 700 MW of NEW CLEAN-ENERGY RESOURCES (300 MW wind and 400 MW battery storage) developed without increasing costs to existing customers. These are grid resource figures,
    “Google has also revealed that it has signed an electric service agreement with Minnesota Power, which will see 700MW of clean energy resources developed”
Money and contracts (5)
  • electric service agreement: 15-year ESA term; all transmission network upgrades for the data center paid through the Facilities Construction Agreement; Large Power Surcharge protections for other customers 15 years (init
    “A 15-year ESA with Google”
  • electric service agreement - clean energy / community clauses: ESA will result in 300 MW wind and 400 MW storage on Minnesota Power's system; Google contributes $5 million in energy impact funding for low-to-moderate-inc
    “the ESA will result in 300 MW wind and 400 MW storage on MP’s system”
  • Google will no longer seek tax breaks for the Hermantown data center, city officials announced in October 2026; the April draft would have returned most city property tax over 28 years in exchange for over $42 million to
    “Google will no longer seek tax breaks for its proposed Hermantown data center, city officials announced Wednesday, following months of community concerns.”
  • Electric Service Agreement: clean energy resources to be developed (mw generation onsite basis - generation/storage resources, NOT a campus load figure) 700 MW
    “Google has also revealed that it has signed an electric service agreement with Minnesota Power, which will see 700MW of clean energy resources developed”
  • Tenant is Google itself (owner-occupied; First phase was estimated at about $650M in chamber-cited reporting, with full build-out potentially into the billions; those investment figures are kept in this signal, not campu
    “Google has confirmed it is the company behind the 403-acre data center campus project in Hermantown, Minnesota.”
Permits and government (5)
  • City of Hermantown City Council:
    “At the October 5, 2026, Hermantown City Council meeting, the 2026 Final Alternative Urban Areawide Review (AUAR) was adopted by the Hermantown City Council.”
  • MN PUC April 2026 newsletter: Minnesota Power filed the Electric Service Agreeme: ESA filed for approval (Docket 26-159, Minnesota Power-Google)
    “Minnesota Power filed the Electric Service Agreement with Google for the Hermantown Data Center and requests approval of:”
  • Project status: announced; SUP withdrawn Nov 2025; AUAR adopted Oct 5 2026
    “At the October 5, 2026, Hermantown City Council meeting, the 2026 Final Alternative Urban Areawide Review (AUAR) was adopted by the Hermantown City Council.”
  • The project's Special Use Permit request was scheduled to go before the Planning and Zoning Commission on Oct 20, 2026, with the City Council scheduled to consider the permit and related agreements Oct 26, 2026
    “The project's special use permit request is scheduled to go before the Planning and Zoning Commission on Oct. 20. The City Council is scheduled to consider the permit and related agreements Oct. 26”
  • City of Hermantown City Council:
    “On October 20, weeks after the details leaked but months before Google would be identified, the Hermantown City Council voted unanimously to rezone residential land as commercial to accommodate Project Loon.”
Legal (1)
  • Decisive B6 items (city record): the city received a lawsuit regarding this project on Nov 5, 2025, and the EQB received a petition on Oct 17, 2025 requesting an Environmental Assessment Worksheet be prepared for the pro
    “The City of Hermantown received a lawsuit regarding this project on November 5.”
Site and other (1)
  • County code: 27137