The site from above
The site
Latest clear satellite view, May 16, 2025.
Power and the grid
1,000 MW contracted
- Diesel backup generators Planned, no air permit found156 units tested monthly; outage use only; no on-site prime power News report · Feb. 2026
- New renewables for the campus (clean capacity agreement) Contracted, not built1,600 MW; up to 1,600 MW of renewables plus 480 MW of batteries that DTE builds and owns, paid for by Google; in the grid, not on site Utility regulator · Oct. 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Jan. 6, 2026Will-serve letterDTE tells the developer it can serve the project through a dedicated, customer-paid substation. Local government · Jan. 2026
- March 17, 2026Contracts filedDTE files two special contracts with Google at the state regulator, the day Google confirms it is the end user. News report · Oct. 2026
- Oct. 1, 2026Regulator approves, unanimouslyThe Public Service Commission approves both contracts after Michigan's first contested hyperscale case, with conditions that keep costs off other customers. Utility regulator · Oct. 2026
- Dec. 2027First power dueDTE expects the campus to start taking service in Dec. 2027, reaching full load by Dec. 2028. Utility regulator · Oct. 2026
- Contract terms: 20 years instead of the usual 5, an 80% minimum bill instead of 50% to 65%, an early-termination payment of at least 15 years of minimum charges, and parent-guarantee and letter-of-credit collateral (amounts sealed). Utility regulator · Oct. 2026
- DTE says the contracts will give other customers a $1.7B benefit over 20 years; that is the utility's contention, not a finding. Utility regulator · Oct. 2026
Grid upgrades
What the grid is building for this load: the asset, its cost, who pays and when it is due to be energized. An upgrade may serve a later phase, not the first building.
- The earliest grid upgrade tied to this campus is due to be energized by Jan. 2027. News report · Oct. 2026
- ITCTransmission is building this campus's grid connection: a new 345-kV switching station (Cannoli station) plus two 345-kV feeds connecting to ITC's Brownstown-Wayne No. 1 and No. 2 lines; station construction Q1 2028… News report · Oct. 2026
Permits checklist
1 pending · 5 granted · 1 checked, nothing on file
Every gating approval is in hand; the generator air permit is the open item.
- ◷Substation and switching station site plan PendingVan Buren Township Planning Commission · April 13, 2026: reviewed with the final plan; separate approval not confirmed Local government · April 2026
- ✓Special power contracts (PSA and clean capacity agreement) GrantedMichigan Public Service Commission · Oct. 1, 2026: unanimous, with mandatory ratepayer protections Utility regulator · Oct. 2026
- ✓Wetlands and stream permit GrantedMichigan EGLE · Aug. 2026: press reports August approval; the state record was not retrieved News report · Oct. 2026
- ✓Final site plan GrantedVan Buren Township Planning Commission · Oct. 14, 2026: 5-1; preliminary plan approved 5-2 on Feb. 11, 2026; land is zoned light industrial, which allows data processing News report · Oct. 2026
- ✓Industrial facilities tax exemption (PA 198) GrantedVan Buren Township and Wayne County · Oct. 1, 2026: township approved May 19; county passed Sept. 15; veto overridden Oct. 1 News report · Oct. 2026
- ✓Aviation hazard determinations GrantedFAA · Oct. 1, 2026: no hazard for buildings and a 200 ft construction crane FAA · Sept. 2026
- –Checked, nothing on file: Air permit for backup generators
What could slow it down
- MediumRecall and political backlashOrganizers are collecting signatures to recall the entire township board, and the county executive vetoed the tax break before the override. News report · Oct. 2026
- MediumState action on tax breaksLawmakers in Lansing are weighing bills that would curb data centers, including repealing tax breaks. News report · Oct. 2026
- MediumWetlands and watershed impactThe campus permanently removes about 13.55 acres of wetlands, and the Huron River Watershed Council filed technical comments on the permit application. News report · Oct. 2026
- WatchSchedule is tightFirst power is due Dec. 2027, but a secondary factsheet of utility filings puts the new 345 kV switching station at Q1 2028 construction and Q3 2028 completion; ITC is building the underground line (press). News report · Oct. 2026
- WatchBackup generator air permitNo air permit for 156 diesel generators has been found, though the township says one may be needed. Local government · Oct. 2026
Money on record
Not on record: capex or project financing: self-funded by Google, no official cost figure News report · Oct. 2026
What happened, and what is due
- Dec. 11, 2025Site Panattoni and DTE hold the first public open house for an unnamed 'Fortune 50' client. News report · Dec. 2025
- Feb. 11, 2026Permits Planning commission grants preliminary site plan approval, 5-2. News report · Feb. 2026
- March 17, 2026Power Google confirms it is the end user; DTE files the power contracts with the state. News report · March 2026
- May 19, 2026Money Township board approves the property tax exemption. News report · May 2026
- June 16, 2026Permits State holds its wetlands permit hearing. State agency · June 2026
- Aug. 3, 2026Power Michigan's attorney general files a brief asking for stronger contract terms. Utility regulator · Aug. 2026
- Aug. 2026Construction Utility and site work starts and the state approves wetlands permits (press); residents report dust and long work hours. News report · Oct. 2026
- Sept. 25, 2026Money County executive vetoes the tax break; the county had passed it on Sept. 15. News report · Oct. 2026
- Oct. 1, 2026Power State regulators approve the contracts; the county commission overrides the veto. News report · Oct. 2026
- Oct. 14, 2026Permits Planning commission approves the final site plan, 5-1. News report · Oct. 2026
- Dec. 2027Power DTE expects first power in Dec. 2027. Utility regulator · Oct. 2026
- Dec. 2028Power Maximum contracted load expected by Dec. 2028. Utility regulator · Oct. 2026
Building activity by quarter
Since Sept. 2011: 4 FAA filings (Sept. 2026 to Oct. 2026): tallest permanent structure 200 ft (filed Sept. 2026); 73 satellite captures. The chart starts in the first quarter of 2021; 4 earlier records are not drawn.
Specs
- One open-loop building: the other two use closed-loop or forced air cooling Local government · Jan. 2026
Owners, partners and builders
- Google: end user and future owner-operator
- Panattoni Development Company: developer, construction manager and permit applicant
- Triple Creek Associates LLC: current landowner
- DTE Electric: supplier, and builder of the renewables for Google
- ITC Transmission: building the underground line (press)
- Michigan Public Service Commission: approved the contracts
- Walbridge Construction: general contractor (press)
- Van Buren Township board and planning commission
- Wayne County Commission, which overrode County Executive Warren Evans
- Michigan Attorney General Dana Nessel: intervened for stronger terms
- Residents behind the board recall effort
- Huron River Watershed Council: filed technical comments on the wetlands permit
Open questions
- IT capacity in MW.
- A final air permit decision for the generators.
- Whether building construction has started.
- Full contract texts (filed under seal).
- 4 unconfirmed county land records near the site: the buyer or location could not be tied to this campus.
375 records from 31 documents
Drawn from news reports, public and commercial datasets, utility regulator dockets, state agency records, local government records, securities filings, our own analysis, company statements and satellite captures, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (36)
- Interconnection status: MPSC-approved Oct 1, 2026 (Case No. U-22058); service expected Dec 2027 with maximum load by Dec 2028; the CCAA adds up to 1,600 MW of renewables and 480 MW of storage, paid for by Google and buil“the CCAA terms require Google to pay for DTE Electric to develop up to 1,600 megawatts (MW) of renewable energy and 480 MW of battery energy storage to serve the data center.”Utility regulator · Oct. 2026 · grade A
- large load interconnection request: special contracts approved (primary supply agreement + clean capacity accelerator agreement)“The Michigan Public Service Commission today approved special contracts between DTE Electric Co. and Google LLC for the utility to provide electricity for a data center in Wayne County's Van Buren Township”Utility regulator · Oct. 2026 · grade A
- large load interconnection request: application filed (contested case)“On March 17, 2026, DTE Electric Company (DTE Electric) filed an application in this docket, with supporting testimony and exhibits, for approval of special contracts for electric service (application).”Utility regulator · Oct. 2026 · grade A
- Grid operator: MISO“other incremental MISO transmission-related oversight and system management costs pertaining to the new data centers”Utility regulator · Aug. 2026 · grade A
- Utility service: 1,000 MW“In March, DTE Energy submitted energy contracts to the Michigan Public Service Commission (MPSC) to support Google's planned 1 gigawatt (GW) data center in Van Buren Township”SEC filing · April 2026 · grade A
- Utility service: 1,000 MW“In March, DTE Energy submitted energy contracts to the Michigan Public Service Commission (MPSC) to support Google's planned 1 gigawatt (GW) data center in Van Buren Township”SEC filing · April 2026 · grade A
- DTE Energy disclosed in its Q1 2026 earnings release (April 30, 2026) that in March 2026 it submitted energy contracts to the Michigan Public Service Commission to support Google's planned 1 GW data center in Van Buren T“In March, DTE Energy submitted energy contracts to the Michigan Public Service Commission (MPSC) to support Google's planned 1 gigawatt (GW) data center in Van Buren Township”SEC filing · April 2026 · grade A
- Stated campus size: 1,000 MW“Per the developer this project is being developed as an approximately 1 gigawatt data center”Local government · Jan. 2026 · grade A
- On-site generation: not stated“There is no fulltime onsite power generation proposed as a part of the project”Local government · Jan. 2026 · grade A
- On-site power technology: Diesel backup generators only (Tier 4 Final, ultra-low sulfur diesel, exhaust scrubbers); no prime on-site generation“The only power generation items that are proposed on-site are a series of on-site backup generators which are intended to be used during outages”Local government · Jan. 2026 · grade A
- Cooling: Mixed: 1 of 3 data center buildings open-loop water cooling; 2 buildings closed-loop and/or forced air“One building is proposed to be cooled using an open loop method and the other two buildings are proposed to be cooled using closed loop and/or forced air methods”Local government · Jan. 2026 · grade A
- Power plan: grid“DTE has provided the developer with a will serve letter for the project confirming they can provide power to the site”Local government · Jan. 2026 · grade A
- County code: 26163“campus anchor (reference centroid of reported bounds): Wayne County MI (26163) per FCC point-in-county lookup; the planned substation is inside the same 282-acre tract”Dataset · Oct. 2026 · grade B
- Nearest power line of 345 kV or more: 2.43 kmMeasured on OpenStreetMap map data.
- Nearest gas pipeline: 10.35 kmMeasured on OpenStreetMap map data.
- IT capacity: not stated“Documented absence: no source opened discloses an IT-load figure or an IT/utility split for this campus”Utility regulator · Oct. 2026 · grade B
- Original target date: not stated“Documented absence: no original building COD was ever published; the only schedule in the record is DTE's service schedule (first power Dec 2027, max load Dec 2028)”Utility regulator · Oct. 2026 · grade B
- Utility service: 1,000 MW“the data center is expected to begin taking service in December 2027 with a maximum load achieved by December 2028”Utility regulator · Oct. 2026 · grade B
- Utility: DTE Electric Company“approved special contracts between DTE Electric Co. and Google LLC”Utility regulator · Oct. 2026 · grade B
- Rate class: Special contracts (PSA + CCAA) approved in lieu of standard D11 large-load rate terms“A contract length of 20 years, compared to 5-year contracts normally required under DTE Electric's large-load D11 rate”Utility regulator · Oct. 2026 · grade B
- Electric service agreement signed: Oct. 1, 2026“The Michigan Public Service Commission today approved special contracts between DTE Electric Co. and Google LLC”Utility regulator · Oct. 2026 · grade B
- Current target date: First power Dec 2027; maximum contracted load Dec 2028 (DTE service schedule)“According to DTE Electric, the data center is expected to begin taking service in December 2027 with a maximum load achieved by December 2028”Utility regulator · Oct. 2026 · grade B
- utility special contract approval: approved (unanimous, with conditions)“The Michigan Public Service Commission today approved special contracts between DTE Electric Co. and Google LLC”Utility regulator · Oct. 2026 · grade B
- DTE contends the approved contracts produce a $1.7B benefit to other customers over the 20-year term as Google pays fixed system costs (utility contention, not a finding)“DTE Electric contends that approval of the data center special contracts will result in a $1.7 billion benefit”Utility regulator · Oct. 2026 · grade B
- Developed acres: 150 acres“Plans call for six buildings, parking lots, a substation, and equipment yards on 150 acres. The rest stays open space”News report · Oct. 2026 · grade C
- Nearest substation of 345 kV or more: none mapped within 16 kmMeasured on OpenStreetMap map data.
- Paper or real: Real commitments: approved 20-yr power contracts with termination/collateral teeth; executed tax package surviving a veto override; issued state wetlands permit; final site plan approved; utility construct“approved special contracts between DTE Electric Co. and Google LLC”Utility regulator · Oct. 2026 · grade C
- Stated campus size: 1,000 MW“Google expects the site to start drawing power by December 2027, and it aims to reach 1 gigawatt within a year”News report · Oct. 2026 · grade C
- Site description: 282-acre site east of Haggerty Road and north of the Interstate 94 North Service Drive, Van Buren Township (T3S R8E Section 13); fields, woods and wetlands; six buildings, parking, a substation and equi“The proposed data center, called Project Cannoli, is set to be located on a 282-acre site situated between I-94 and I-275, a few miles west of the Detroit Metro Airport”News report · Oct. 2026 · grade C
- Interconnection status: Special contracts approved; new 345-kV switching station and two 345-kV feeds planned (feed 1 late 2027, feed 2 late 2028); ITC building an underground transmission line to the site“Transmission: New 345-kV switching station and two 345-kV feeds”News report · Oct. 2026 · grade C
- Substation kV: 345 kV“new electric infrastructure is being planned specifically for the development, including a 345-kilovolt switching station”News report · Oct. 2026 · grade C
- utility special contract application: application filed“DTE filed its application for the two Google contracts on March 17”News report · Oct. 2026 · grade C
- Grid upgrade due to be energized by: 2027“The first feed is expected to enter service in late 2027. The second is expected in late 2028.”News report · Oct. 2026 · grade C
- ITCTransmission is building this campus's grid connection: a new 345-kV switching station (Cannoli station) plus two 345-kV feeds connecting to ITC's Brownstown-Wayne No. 1 and No. 2 lines; station construction Q1 2028 t“ITCTransmission is developing the grid connection. The plan includes a new 345-kilovolt switching station and two 345-kV transmission feeds.”News report · Oct. 2026 · grade C
- Grid power partnership: Google-DTE Energy agreement to bring 2.7 GW of new clean resources to the local grid (off-site grid supply, not on-site generation)“Google is partnering with DTE Energy to bring 2.7GW of "new, clean resources" to the local grid, which will be used to power the data center”News report · March 2026 · grade C
- Backup generators: 156 generators“the project's 156 diesel backup generators will be tested once a month for 15 minutes”News report · Feb. 2026 · grade C
Money and contracts (36)
- Tenants: Google LLC (self-use)“two special contracts between DTE and Google LLC concerning the operation of a data center in Van Buren Township, Michigan”Utility regulator · Aug. 2026 · grade A
- power supply agreement (PSA), special contract: collateral Parent guarantee and bank letter of credit terms exist in the PSA (and CCAA); the Attorney General asked the Commission to reject limitations on them“reject any limitations on the parent guarantee and bank letter of credit collateral terms in the PSA and CCAA”Utility regulator · Aug. 2026 · grade A
- power supply agreement (PSA), special contract: demand response PSA contains demand-response provisions; AG sought separate accounting and rate crediting of DR non-performance penalties (recommendation; adoption not con“any penalties assessed to the Customer for non performance under the DR program should be accounted for separately”Utility regulator · Aug. 2026 · grade A
- power supply agreement (PSA), special contract: other clause PSA Section 5.1.3 contains an affordability backstop provision (referenced in AG briefing; substance not public)“Affordability Backstop (PSA Section 5.1.3)”Utility regulator · Aug. 2026 · grade A
- Tenant status: Google (self-use), named by the utility in an SEC-furnished release“Secured agreement to power Google's new data center in Michigan: In March, DTE Energy submitted energy contracts to the Michigan Public Service Commission (MPSC) to support Google's planned 1 gigawatt (GW) data center in Van Buren Township”SEC filing · April 2026 · grade A
- water purchase / municipal water service: scope All cooling/process water purchased from the Township via GLWA transmission main; developer pays all infrastructure costs; Township may pay only for a meter pit at the GLWA“The only thing the Township may pay for is a meter pit for the new connection to the GLWA transmission main”Local government · Jan. 2026 · grade A
- water purchase / municipal water service: discharge limit Sanitary sewer discharge limited to approximately 750,000 gallons per day, monitored by the Township gallons/day“We have limited the applicant's sewer discharge to approximately 750,000 gallons per day and we will monitor the volume”Local government · Jan. 2026 · grade A
- utility will-serve letter: commitment DTE will-serve letter confirming it can serve the project load; power via a dedicated substation paid for by the customer, connected to existing high-voltage transmission lines“DTE has provided the developer with a will serve letter for the project confirming they can provide power to the site”Local government · Jan. 2026 · grade A
- Conditions of approval: MPSC approval conditioned on mandatory ratepayer protections (costs confined to Google); EGLE wetlands permit requires mitigation (credits in Huron watershed + ~1,174 ft new stream channel) and a“conditioned on mandatory protections to prevent other customers from having to bear any costs associated with the project”Utility regulator · Oct. 2026 · grade B
- Name: Google Van Buren Township (Project Cannoli)“approved special contracts between DTE Electric Co. and Google LLC for the utility to provide electricity for a data center in Wayne County's Van Buren Township”Utility regulator · Oct. 2026 · grade B
- Tenant status: signed (end user; DTE PSA + CCAA approved by MPSC Oct 1, 2026; Google to be owner-operator)“The Commission approved a primary supply agreement (PSA) governing the terms of electric service to the data center and a clean capacity accelerator agreement (CCAA)”Utility regulator · Oct. 2026 · grade B
- Minimum bill terms: 80% of contract capacity (minimum monthly billing demand)“A minimum billing demand of 80%, compared to 50%-65% in the general D11 rate”Utility regulator · Oct. 2026 · grade B
- power supply agreement (PSA), special contract: scope Electric service to the Van Buren Township data center; ~1,000 MW contract capacity“The Commission approved a primary supply agreement (PSA) governing the terms of electric service to the data center”Utility regulator · Oct. 2026 · grade B
- power supply agreement (PSA), special contract: term 20 years“A contract length of 20 years, compared to 5-year contracts normally required under DTE Electric's large-load D11 rate”Utility regulator · Oct. 2026 · grade B
- power supply agreement (PSA), special contract: minimum bill 80% minimum monthly billing demand of contract capacity“A minimum billing demand of 80%, compared to 50%-65% in the general D11 rate”Utility regulator · Oct. 2026 · grade B
- power supply agreement (PSA), special contract: termination Early termination payment guaranteeing at least 15 years of minimum monthly charges“An early termination payment requiring Google to ultimately pay for at least 15 years of minimum monthly charges”Utility regulator · Oct. 2026 · grade B
- power supply agreement (PSA), special contract: collateral Credit and collateral requirements, including parent guarantee and bank letter of credit terms (amounts confidential, filed under protective seal)“Credit and collateral requirements to cover costs in the event Google were to cease operating the data center sooner than planned”Utility regulator · Oct. 2026 · grade B
- clean capacity accelerator agreement (CCAA), special contract: scope DTE to develop up to 1,600 MW of renewable energy and 480 MW of battery storage to serve the data center; developed, owned and operated by DTE MW“the CCAA terms require Google to pay for DTE Electric to develop up to 1,600 megawatts (MW) of renewable energy and 480 MW of battery energy storage”Utility regulator · Oct. 2026 · grade B
- clean capacity accelerator agreement (CCAA), special contract: cost responsibility Google pays for the CCAA resources; no costs passed to DTE's other customers“which will be paid for by Google and developed, owned and operated by DTE Electric”Utility regulator · Oct. 2026 · grade B
- special contracts (PSA + CCAA): missing clause finding FINDING: full contract texts are filed under protective seal and public versions are heavily redacted; termination/cancellation language beyond the approved summary“intervenors including the Michigan Department of Attorney General had full access to all documents filed in the case, including confidential documents filed under protective seal”Utility regulator · Oct. 2026 · grade B
- Financing: not stated“Documented absence: no project-level financing disclosed in any source opened; self-funded hyperscaler development (Panattoni build for Google owner-occupation); the $2B figure in coverage is Kramer's claim about construction contract value to county businesses, not financing or capex”News report · Oct. 2026 · grade C
- Stated capital cost: not stated“Documented absence: no official capex figure published for this campus in sources opened”News report · Oct. 2026 · grade C
- Stage: approved / pre-construction, all gating approvals in hand (MPSC contracts Oct. 1, 2026; EGLE wetlands permit Aug. 2026; tax package final Oct. 1, 2026; final site plan Oct. 14, 2026); utility site work underway s“Construction-related utility work is already underway, with additional activity expected into 2027”News report · Oct. 2026 · grade C
- tax exemption (PA 198 industrial facilities tax): jobs floor Google guaranteed at least 51 full-time jobs“Google also agreed to guarantee at least 51 full-time jobs”News report · Oct. 2026 · grade C
- operational agreement: scope Operational agreement signed covering issues outside Planning Commission scope (noise and other community-impact commitments)“Panattoni signed an operational agreement with the township, he said, and that deal covers issues outside the commission's reach”News report · Oct. 2026 · grade C
- operational agreement: missing clause finding FINDING: the operational agreement's text, term and termination/cancellation clauses are not public in any source opened; only its existence and general scope are documented“Panattoni signed an operational agreement with the township”News report · Oct. 2026 · grade C
- Incentives: PA 198 industrial facilities tax exemption: 50% property tax reduction for 12 years, value >$125M; Township Board approved May 19, 2026; Wayne County passed Sep 15, 2026; County Executive veto Sep 25, 2026 ov“Officials with Van Buren Township and Wayne County agreed to give Google a $125 million tax break for the project. County officials overrode the veto of Wayne County Executive Warren Evans”News report · Oct. 2026 · grade C
- tax exemption (PA 198 industrial facilities tax): exemption 50% property tax reduction for 12 years; value >$125M; project still pays an estimated ~$124M in taxes over the period“The incentives would reduce certain local property taxes associated with the development by 50% for 12 years”News report · Oct. 2026 · grade C
- community benefits agreement: community payment $15M to Wayne County and $15M to Van Buren Township (reported) USD“Google has agreed to provide $15 million each to both the county and the township”News report · Oct. 2026 · grade C
- Panattoni's Kramer claimed site construction will bring $2B in contracts to Wayne County businesses and >9M construction hours for local contractors; ~1,500 construction jobs; tens of millions spent on redesigns to reduc“Kramer said site construction would bring $2 billion in contracts to businesses in Wayne County”News report · Oct. 2026 · grade C
- Buildings: 5 buildings“It will be comprised of five buildings, including three data processing buildings ranging from 87,000 square feet to 300,000 square feet, according to township planning documents”News report · Oct. 2026 · grade C
- Square feet: 1500000 sq ft“approve plans for the nearly 1.5 million-square-foot data center campus on 282 acres”News report · Oct. 2026 · grade C
- power supply agreement (PSA), special contract: condition Approval conditioned on mandatory protections so no project costs fall on other DTE customers; order imposes reporting and cost-tracking obligations (per seconda“requiring financial protections (80% minimum billing, termination payments, collateral) and reporting and modeling updates to ensure other customers are not subsidizing the project”News report · Oct. 2026 · grade C
- tax exemption (PA 198 industrial facilities tax): revocation / clawback Township can revoke the tax benefits if Google breaks its commitments (noise reduction, landscaping, water use terms negotiated by the Township)“The township can revoke the benefits for Google if the company breaks its promises”News report · Oct. 2026 · grade C
- clean capacity accelerator agreement (CCAA), special contract: term 20 years“The 20-year Primary Supply Agreement and the related Clean Capacity Accelerator Agreement come with conditions meant to protect existing customers”News report · Oct. 2026 · grade C
- Source record“the company and developer Panattoni committed to $15.4 million upfront for local infrastructure, at least 51 full-time jobs, local hiring preferences”News report · May 2026 · grade C
Permits and government (29)
- FAA OE/AAA aeronautical case: Determined: No Hazard to Air Navigation“Project Cannoli - Building 4 | Building | AGL 42 ft | 42.22553081,-83.43582075 | submitted 10/01/2026 | Determined - No Hazard”FAA · Oct. 2026 · grade A
- FAA OE/AAA aeronautical case: Determined: No Hazard to Air Navigation“Project Cannoli Data Center | Mobile Construction Equipment | AGL 200 ft | 42.22361111,-83.43111111 | submitted 09/29/2026 | Determined - No Hazard”FAA · Sept. 2026 · grade A
- FAA OE/AAA aeronautical case: Determined: No Hazard to Air Navigation“Project Cannoli - Building 2 | Building | AGL 72 ft | 42.22361111,-83.43111111 | submitted 09/29/2026 | Determined - No Hazard”FAA · Sept. 2026 · grade A
- Developer: Panattoni Development Company, Inc.“Panattoni Development Company, Inc. has asked the Michigan Department of Environment, Great Lakes, and Energy (EGLE) for a permit”State agency · June 2026 · grade A
- Wetlands/stream permit application (Part 303 / Section 404): Application received; public hearing held June 16, 2026; comment record closed June 26, 2026; NO issuance found as of Oct. 18, 2026 (decision pending)“Panattoni Development Company, Inc. has asked EGLE for a permit to do work that would affect wetlands and streams in Van Buren Township; look up reference number HQH-Q48N-1818Y”State agency · June 2026 · grade A
- wetlands / stream permit (NREPA Parts 303/301): application public notice and hearing“The project would permanently impact 13.55 acres of wetlands, place eight culverts in regulated streams, and build six stormwater ponds”State agency · June 2026 · grade A
- Township site-plan review: Preliminary review (Plan Review #2, Apr 13, 2026); substation reviewed as one project with the data center final site plan“proposes the construction of a high-voltage substation/switching station on a 9-acre area located within the boundaries of Project Cannoli Data Center”Local government · April 2026 · grade A
- PA 207 of 2024 framework: state sales/use tax exemptions for large data centers are conditioned on ratepayer cost protections, municipal water use, and procurement of clean energy equal to 90% of forecasted annual usage“The Public Act requires that a data center procure clean energy to 90% of the data center's forecasted electricity usage on an annual basis”Local government · Jan. 2026 · grade A
- Michigan Public Service Commission: Order approving DTE Electric / Google LLC special contracts (PSA + CCAA), Case No. U-22058“The Michigan Public Service Commission today approved special contracts between DTE Electric Co. and Google LLC”Utility regulator · Oct. 2026 · grade B
- Tallest structure filed with the FAA (ft): 72 ft“ASN 2026-AGL-15158-OE: Project Cannoli - Building 2, Building, 72 ft AGL, 745 ft AMSL, 42.22361,-83.43111, Determined - No Hazard, submitted 2026-09-29”FAA · Sept. 2026 · grade B
- FAA OE/AAA filings under the campus's own project name evidence vertical construction at the Google Project Cannoli campus (Van Buren Township MI): a 200-ft mobile construction equipment case and two building cases ('Pro“ASN 2026-AGL-14885-OE: Project Cannoli Data Center, Mobile Construction Equipment, 200 ft AGL, 866 ft AMSL, 42.22361,-83.43111, Determined - No Hazard, submitted 2026-09-29”FAA · Sept. 2026 · grade B
- air permit to install (PTI): none found“Backup diesel generators are required to meet emission standards set by the Environmental Protection Agency (EPA) and may require an Air Permit from EGLE”Local government · Oct. 2026 · grade C
- Huron River Watershed Council submitted technical comments to EGLE on the wetlands application; HRWC discloses funding received through Google's Water Stewardship Portfolio for watershed work“HRWC has received a grant from Bonneville Environmental Foundation, one of seven awarded nationally through Google's Water Stewardship Portfolio”News report · Oct. 2026 · grade C
- Site plan approval date: Oct. 14, 2026“The Van Buren Township Planning Commission voted 5-1 Wednesday, Oct. 14, to approve plans for the nearly 1.5 million-square-foot data center campus”News report · Oct. 2026 · grade C
- Opposition: Sustained resident opposition at township and county meetings; recall effort targeting the entire Township Board (organizers approved to collect signatures by ~Jul 2026, organizer Jenn Smith); a resident was“Opposition to the Van Buren Township project has sparked a recall effort targeting the entire township board”News report · Oct. 2026 · grade C
- wetlands / stream permit (NREPA Parts 303/301): approved“In August, state environmental regulators approved wetland permits for the project”News report · Oct. 2026 · grade C
- Recall campaign against the entire Van Buren Township Board of Trustees: organizers approved to collect signatures by July 2026 (organizer Jenn Smith), citing the board's data center approvals“organizers were approved to collect signatures to recall the township's entire board of trustees”News report · Oct. 2026 · grade C
- MPSC directed DTE to include Google's expected load in its Integrated Resource Plan and Clean Energy Plan filings, listed separately and assessed alongside other large-load customers (per secondary coverage of related pr“the Michigan Public Service Commission directed DTE to include Google's expected load in its Integrated Resource Plan and Clean Energy Plan filings”News report · Oct. 2026 · grade C
- State lawmakers are weighing bills to curtail data center development, including repeal of the tax breaks; data center guardrails are a live issue in Michigan's gubernatorial campaign“Lawmakers in Lansing are also weighing multiple bills that would curtail data center development”News report · Oct. 2026 · grade C
- Wayne County Commission: Override of County Executive Warren Evans' Sep. 25, 2026 veto of the >$125M tax exemption package“The Wayne County commission unanimously overrode Evans' veto”News report · Oct. 2026 · grade C
- Van Buren Township Planning Commission: Final site plan approval for Project Cannoli“The Van Buren Township Planning Commission voted 5-1 Wednesday, Oct. 14, to approve plans”News report · Oct. 2026 · grade C
- Entitlement status: final site plan APPROVED 5-1 by the Van Buren Township Planning Commission on Oct 14, 2026; developer cleared to start utility installation and site work“members of the Van Buren Township Planning Commission voted 5-1 to approve a final site plan for the project”News report · Oct. 2026 · grade C
- Local approval status: Final site plan APPROVED 5-1 by the Van Buren Township Planning Commission on Oct 14, 2026 (preliminary site plan approved February 2026); approval clears Panattoni to start utility installation an“members of the Van Buren Township Planning Commission voted 5-1 to approve a final site plan for the project”News report · Oct. 2026 · grade C
- ITC is building an underground transmission line to connect the site to DTE; a new 345-kV switching station is planned (construction Q1 2028, completion Q3 2028 per a secondary factsheet of DTE filings)“ITC is building an underground transmission line to connect the site to DTE and state permits”News report · Oct. 2026 · grade C
- Wayne County Commission: County passage of the Project Cannoli tax incentive packages and community benefits agreement“the county voted to pass the packages Sept. 15”News report · Oct. 2026 · grade C
- Resident forcibly removed by police from the Township Board meeting after exceeding comment time while criticizing the project and the IFT exemptions“police escorting a woman from the chamber for exceeding her allotted public comment time while calling trustees grifters and liars”News report · May 2026 · grade C
- Van Buren Township Board of Trustees: Resolutions granting PA 198 Industrial Facilities Tax exemptions to Google for Project Cannoli“trustees advanced resolutions granting Industrial Facilities Tax exemptions to Google for Project Cannoli”News report · May 2026 · grade C
- Van Buren Township Planning Commission: Preliminary site plan approval, 3 data processing buildings, admin office, network building, 7-acre substation“the commission granted preliminary site approval in a 5-2 vote”News report · Feb. 2026 · grade C
- Developer open house (Panattoni / DTE, township officials attending): First public pitch of Project Cannoli; end user unnamed ('Fortune 50' client)“People flooded a catered open house for a proposed Van Buren Township data center Thursday”News report · Dec. 2025 · grade C
Site and other (19)
- Site location FAA: 42.223611,-83.431111 (Building 2 / construction equipment); 42.225531,-83.435821 (Building 4)“Project Cannoli - Building 4; 42.22553081,-83.43582075; Project Cannoli Data Center”FAA · Oct. 2026 · grade A
- Collateral: Credit and collateral requirements, including parent guarantee and bank letter of credit terms (amounts under protective seal)“reject any limitations on the parent guarantee and bank letter of credit collateral terms in the PSA and CCAA”Utility regulator · Aug. 2026 · grade A
- Address: Township 3 South, Range 8 East, Section 13, Van Buren Township, Wayne County, MI“The site is located in Township 3 South, Range 8 East, Section 13”State agency · June 2026 · grade A
- Code names: Project Cannoli“Project Cannoli is a proposed data center project which is located near the I-94/Haggerty Road area”Local government · Jan. 2026 · grade A
- Acres: 282 acres“Of the 282 acres of property, approximately 130 acres will remain undeveloped”Local government · Jan. 2026 · grade A
- Water use stated: 2.0 to 3.6 million gallons per day, purchased from the Township via a GLWA transmission main (Detroit River source); no groundwater, surface-water or aquifer withdrawals; sewer discharge capped at ~750,“the estimated water usage for the data center project is somewhere between 2 to 3.6 million gallons per day”Local government · Jan. 2026 · grade A
- Workforce estimate: ~1,500 construction jobs; 51+ permanent jobs (developer/township figures)“Creation of approximately 1,500 construction jobs and 51+ permanent jobs”Local government · Jan. 2026 · grade A
- Site acres: 282 acres“the data center will rise on 282 acres east of Haggerty Road and north of the Interstate 94 North Service Drive”News report · Oct. 2026 · grade C
- Time to service (months): 14 months“the data center is expected to begin taking service in December 2027”Utility regulator · Oct. 2026 · grade C
- Project status: site plan approved Oct 14, 2026; utility installation and site work cleared to begin; no vertical construction reported“The approval allows developer Panattoni to move forward with utility installation and site improvements”News report · Oct. 2026 · grade C
- Address: East of Haggerty Road, north of the I-94 North Service Drive, between I-94 and I-275, Van Buren Township, MI“the data center will rise on 282 acres east of Haggerty Road and north of the Interstate 94 North Service Drive”News report · Oct. 2026 · grade C
- Construction stage: site work / underground utility installation underway since ~Aug 2026; no building construction yet; groundbreaking expected before end of 2026“The approval allows developer Panattoni to move forward with utility installation and site improvements”News report · Oct. 2026 · grade C
- Utility/site work physically underway from ~August 2026, before final site plan approval: residents report crews working 6 a.m.-7 p.m., six to seven days a week, with dust complaints; underground utility work proceeds in“Dust has been coming into our homes since August and only getting worse”News report · Oct. 2026 · grade C
- Developer: Panattoni Development (Panattoni Data Center Group)“construction is being managed by industrial developer Panattoni”News report · Oct. 2026 · grade C
- Joint protest on the Rawsonville Road bridge (Van Buren/Ypsilanti township line) against both Project Cannoli and the U-M/Los Alamos computing facility“Public pushback against data centers is mounting in Michigan and nationwide”News report · Oct. 2026 · grade C
- Operator: Google - confirmed as the end user / owner-operator on Mar 17, 2026; construction managed by developer Panattoni“Google confirmed on Tuesday, March 17, that it was the company behind the project”News report · March 2026 · grade C
- Site plan approval date: Feb. 11, 2026“the commission granted preliminary site approval in a 5-2 vote”News report · Feb. 2026 · grade C
- Owner companies: Triple Creek Associates LLC (current landowner); Google LLC (intended owner-operator, purchase pending approvals)“The proposed data center site is owned by Triple Creek Associates LLC, according to township documents”News report · Feb. 2026 · grade C
- Announced: Dec. 11, 2025“People flooded a catered open house for a proposed Van Buren Township data center Thursday, with representatives of the Panattoni Development Co. and DTE Energy on hand”News report · Dec. 2025 · grade C
Imagery and records: Satellite imagery: Maxar via Esri World Imagery Wayback.