Data center profile · Ward County, Texas

Ionic Digital Cedarvale (Nscale Ward County)

Data center campus proposed by Nscale in Ward County, Texas, on grid power; about 187 MW of IT capacity planned.

Project company registered. Utility and grid approval granted. A utility regulator has approved service. Newest record Sept. 2026.
The campus, Lower-resolution satellite image, Sept. 28, 2026
234 MW
utility load on file
facility power, not split into IT capacity
4
data center buildings planned
2029
first building in service, our estimate
range 2027 to 2032; no company target on record
OperatorNscale
CustomerNscale
Planned IT capacity187 MW at full build-out (our estimate from the company or utility power figure)
First building in serviceOur estimate: 2029 (range 2027 to 2032).
The site

The site from above

Satellite overview
Lower-resolution satellite image, Sept. 28, 2026.
Power

Power and the grid

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. Oct. 14, 2025
    Utility MW on record
Permits

Permits checklist

1 granted · 4 checked, nothing on file

Approvals a campus like this normally needs, and what we found.

Money

Money on record

$2.0B
Data center lease
Full facility: 234 MW current capacity Company · Oct. 2025
$14M
Land purchase
Undeveloped Barstow site acquisition by Ionic's predecessor News report · Feb. 2026
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Oct. 14, 2025
    Site Project first appears in the public record
  2. Sept. 10, 2026
    Power Interconnection queue approved by ERCOT. News report · Sept. 2026
Construction activity

Since Sept. 2026: 1 satellite capture. Satellite · Sept. 2026

Who is involved

Owners, partners and builders

Owners and developers
  • Ionic Digital, owner
  • Celsius Mining, developer
  • Hut 8, developer
Customers
  • Nscale, tenant
  • Nscale Ward County, tenant
  • Microsoft, tenant
Still unknown

Open questions

Where this comes from

23 records from 8 documents

Drawn from news reports, company statements and satellite captures, each kept with its date and source. The bar shows documents by type.

News report 5Company 2Satellite 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (7)
  • Utility service: 234 MW
    “Under the general terms of the Agreement, Nscale will lease the full 234 MW capacity of the facility”
  • Project status: Built and energized as a bitcoin-mining facility (first two of four 50 MW buildings energized Aug and Oct 2024); cryptomining at the site has since been decommissioned. The full 234 MW is leased to Nscale
    “Crytptomining at the site has been decommissioned. AI cloud firm Nscale, spun out of crypto firm Arkon Energy, is leasing the site for 10 years in a $2 billion deal”
  • Utility service: 89 MW
    “Nscale is also leasing a further 89MW from 2027”
  • Ionic is seeking to expand the Barstow/Cedarvale site to 700 MW total energized capacity by the end of 2027; Expansion is sought, not delivered.
    “Ionic is also seeking to expand the Barstow site to 700MW by the end of 2027”
  • interconnection queue (ERCOT): provisional Base Load classification granted
    “The 700 MW figure represents aggregate site demand rather than critical IT load, contracted customer capacity or energized load”
  • County code: 48475
    “we committed to providing Nscale with the full amount of the 234 megawatts ("MW") of current energy capacity at our Ward County property”
  • Building count: 4
    “The reborn Ionic energized the first of four 50MW buildings at the Barstow site in August 2024, energizing the second building in October that year”
Money and contracts (4)
  • Announced: Oct. 14, 2025
    “today announced a landmark lease agreement (the “Agreement”) with Nscale, a vertically integrated AI cloud provider, for Ionic Digital’s Cedarvale facility in Barstow, Texas (“Cedarvale”)”
  • data center lease (triple-net): Full facility: 234 MW current capacity (plus 89 MW from 2027 under the lease tranches) 2000000000 USD
    “The Agreement is structured as a 10-year, triple-net lease with total contracted revenues of approximately $2 billion”
  • A February 2026 amendment to the Nscale lease reportedly raises total contracted revenues from ~$2B toward $2.6B (press summary of Ionic's disclosures).
    “$2 billion for the Ionic Digital lease covering the Cedarvale data center in Texas, with a February amendment potentially raising the total to $2.6 billion”
  • land purchase: Undeveloped Barstow site acquisition by Ionic's predecessor 14000000 USD
    “Ionic predecessor Celsius acquired the then-undeveloped Barstow site from Core Scientific in September 2023, for $14 million”
Site and other (1)
  • Campus name: Ionic Digital Cedarvale (Nscale Ward County)
    “for Ionic Digital's Cedarvale facility in Barstow, Texas ("Cedarvale")”

Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).