Data center profile · 300 Jones Road, near I-85 northeast of Spartanburg, Spartanburg County, South Carolina

LightHouse Data Centers Spartanburg (300 Jones Road)

LightHouse and Lightstone's 152-acre former bitcoin-mining site in Spartanburg County, South Carolina: 60 MW of grid rights, zoning appeal lost, one-year moratorium.

Zoning denied, moratorium. The county zoning board upheld the denial of LightHouse's 200,000 sq ft data center in Aug. 2026, and the county passed a one-year moratorium in Sept. 2026. LightHouse owns the site, but no construction, tenant or utility filing on record.
60 MW
grid service rights bought with the site
utility load; due to be available Sept. 2026 per the seller's SEC filing
$18M
cash price at closing, Dec. 2025
plus up to $18M in earnout payments
152 acres
two parcels at 300 Jones Road
former Greenidge bitcoin-mining property
Appeal denied
county zoning board, Aug. 25, 2026
a one-year moratorium followed in Sept. 2026
OperatorLightHouse Data Centers (with The Lightstone Group), through 300 Jones Road Associates LLC
CustomerNone named
Planned IT capacity48 MW for the first phase; full build-out not stated (our estimate from the company or utility power figure)
Next stepEnd of the county's one-year data-center moratorium, passed Sept. 22, 2026
Permits

Permits checklist

1 denied · 2 checked, nothing on file

Approvals the campus needs, and where each stands.

Risks

Why it stopped, what could revive it

Power

Power and the grid

60 MW contracted

Grid service rights (60 MW)Rights assigned
60 MW
assigned by the seller at closing, expected to be available Sept. 2026; the developer says it contacted Duke Energy; no service agreement or regulator filing located SEC filing · Dec. 2025
Contracted

Getting on the grid

Money

Money on record

$18M
cash paid at closing
Dec. 11, 2025 (seller's SEC filing) Company · Dec. 2025
Up to $18M
earnout to the seller
$180,000 per MW of capacity above 60 MW delivered before 2031; seller consideration, not campus capacity Company · Dec. 2025
$12.1M
earlier sale to another buyer, terminated
Data Journey deal of Nov. 2024, ended Aug. 2025 Company · Aug. 2025
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Nov. 27, 2024
    Site Greenidge agrees to sell the site and its power rights to Data Journey Company · Aug. 2025
  2. Aug. 24, 2025
    Site Data Journey terminates the purchase agreement Company · Aug. 2025
  3. Nov. 26, 2025
    Site Greenidge agrees to sell the site to a Lightstone and LightHouse affiliate SEC filing · Dec. 2025
  4. Dec. 11, 2025
    Money Sale closes for $18M cash, with rights to 60 MW of grid service assigned SEC filing · Dec. 2025
  5. Jan. 14, 2026
    Site Partner Wharton Digital lists a 60 MW I-85 corridor facility with LightHouse due in 2026 (press) News report · Jan. 2026
  6. March 16, 2026
    Site Residents raise concerns about the proposal at a public county meeting News report · June 2026
  7. April 28, 2026
    Permits Application fees for the county permit are paid News report · June 2026
  8. June 15, 2026
    Permits County council votes to draft a one-year data-center moratorium News report · June 2026
  9. Aug. 25, 2026
    Permits County zoning board upholds the denial of LightHouse's data center News report · Aug. 2026
  10. Sept. 22, 2026
    Permits Council passes the one-year moratorium on new data centers, 5-1 News report · Sept. 2026
The buildings

Specs

200,000 sq ft data center LightHouse sought to build (press). News report · Aug. 2026

Who is involved

Owners, partners and builders

Owner
  • LightHouse Data Centers LLC: developer
  • 300 Jones Road Associates LLC: buyer and landholder
  • Lightstone Parent LLC (The Lightstone Group): guarantor and partner
  • Wharton Digital: investor and partner in LightHouse (press)
Seller
  • Greenidge Generation Holdings: former owner, through 300 Jones Road LLC
Government
  • Spartanburg County Council: moratorium
  • Spartanburg County Board of Zoning Appeals: upheld the denial
Earlier buyer
  • Data Journey LLC: terminated its 2024 purchase agreement
Still unknown

Open questions

Where this comes from

38 records from 16 documents

Drawn from news reports, company statements and securities filings, each kept with its date and source. The bar shows documents by type.

News report 12Company 3SEC filing 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (7)
  • Utility service: 60 MW
    “to assign to the Purchaser the Company's rights to 60 megawatts (MW) of electrical service (the Initial Load), which is expected to be made available to the Property in September 2026”
  • Project identity: LightHouse Data Centers campus at 300 Jones Road, Spartanburg, SC - approximately 152-acre former Greenidge Generation property, acquired by 300 Jones Road Associates LLC (an affiliate of The Lightstone
    “announced the closing of the sale of its 152-acre property located in Spartanburg, South Carolina to an affiliate of The Lightstone Group and LightHouse Data Centers”
  • Its 450 MW power station received SCDES air quality permitting and its SC PSC Siting Act docket (2026-158-E) is not LightHouse's; none of those records belong to 300 Jones Road.
    “The development's 450-megawatt power station recently received air quality permitting from the South Carolina Department of Environmental Services”
  • Wharton Digital partner materials described an initial 60 MW phase that could eventually expand to about 160 MW
    “The project could eventually expand to about 160 megawatts, according to company materials.”
  • Company materials said Wharton Digital/LightHouse contacted Duke Energy and planned an initial 60 MW phase, expandable to about 160 MW. No Duke service agreement, PSC filing, or SCDES permit was located; the figures are
    “The company also said it contacted Duke Energy and planned to begin construction this year with an initial 60-megawatt phase”
  • Partner Wharton Digital lists an I-85 corridor facility with LightHouse on 151 acres with the first 60 MW phase due live in 2026; LightHouse's launch coverage also describes a 2 GW company pipeline - portfolio marketing,
    “Set on 151-acres, the first 60MW phase is due live in 2026.”
  • Greenidge bought the property in 2021 for $15M and in 2023 sold 23 subdivided acres and its 44 MW cryptocurrency mining facilities on the site to NYDIG for $28M - the 44 MW was the sold-off mining facility, not this camp
    “In 2023, it sold 23 subdivided acres and its 44MW cryptocurrency mining facilities to NYDIG for $28m.”
Money and contracts (4)
  • Sale consideration was $18.0 million cash at closing plus Success Payments of up to $18.0 million at $180,000 per MW for capacity above the 60 MW Initial Load made available before Dec 31, 2030, secured by an irrevocable
    “any Success Payments will be made by the Purchaser to the Company no later than three months after any such additional energization in excess of the Initial Load at a rate of $180,000 per MW”
  • purchase and sale (closed): consideration 18000000 USD cash at closing
    “The consideration for the Transaction consists of $18.0 million in cash at closing (subject to upward adjustment) and the right to receive up to $18.0 million in additional earnout payments.”
  • purchase and sale (closed): earnout up to 18000000 USD
    “The earnout payments are payable at $180,000 per megawatt (MW) of power capacity made available to the property before 2031, to the extent such capacity exceeds the 60 MW Greenidge previously secured for delivery by September 2026.”
  • purchase and sale (TERMINATED): termination 12100000 USD cash plus 8% profit participation interest
    “the Company agreed to sell Data Journey two parcels containing approximately 152 acres of land located in Spartanburg, South Carolina (the 'Property'), together with the power rights to the Property”
Permits and government (6)
  • One-year moratorium on new data center development passed third reading 5-1 (Coker opposed); it did not include the NorthMark/Valara facility under construction on South Pine Street, a separate campus
    “The vote in favor of the moratorium was 5-1.”
  • County zoning officials denied LightHouse's appeal to build its 200,000 sq ft da: zoning appeal denied (denial upheld)
    “County zoning officials on Tuesday denied an appeal by LightHouse as it sought permission to build its 200,000-square-foot center on 150 acres near Interstate 85, northeast of the city of Spartanburg”
  • Project status: announced permit application filed paused by moratorium
    “The moratorium pauses the proposed data center at 300 Jones Road, first reported by FOX Carolina in March.”
  • County officials said a permit application for the 300 Jones Road site was received and application fees were paid April 28, 2026; Council acted because of a 60-day window to respond to applications
    “Application fees for the 300 Jones Road project were paid April 28, according to county officials.”
  • Residents had raised the 300 Jones Road proposal publicly since March 2026 (including at a March 16 public meeting) and questioned Council's claim to have only recently learned of it; in March a Council member said the c
    “On March 16, Spartanburg County resident Courtney McClain spoke at length about her concerns regarding the proposed data center during a public meeting.”
  • Spartanburg County Council voted June 15, 2026 to draft a one-year moratorium on new data center development, and passed the moratorium Sep 22, 2026; the county also paused new data center tax-incentive decisions. LightH
    “Spartanburg County Council voted on June 15 to instruct administrators to draft a one-year moratorium on the development of new data centers in the county”
Site and other (1)
  • County code: 45083
    “two parcels of land totaling approximately 152 acres located in Spartanburg, South Carolina”