Permits checklist
1 pending · 2 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- ◷Conditional rezoning to light industrial (five parcels) PendingGaines Charter Township Planning Commission · April 15, 2026: tabled 7-0 so Microsoft and staff can answer concerns; staff endorsed approval; the board decides Dataset · April 2026
- –Checked, nothing on file: Site plan, Air permit to install
Why it stopped, what could revive it
- HighRezoning tabled amid oppositionThe rezoning has not advanced since April, after a hearing where 67 people spoke, the overwhelming majority opposed (press). News report · April 2026
- MediumTransparency concernsResidents cite the township's nondisclosure agreement with Microsoft and a records-fee dispute. Local government · April 2026
- MediumMoratorium requestsResidents repeatedly asked for a one-year moratorium; none has been adopted. Local government · April 2026
Power and the grid
- Consumers Energy supply Proposed, no utility filingidentified supplier; MW not disclosed; Microsoft proposes to pay for needed grid upgrades Dataset · April 2026
- Backup generators Proposed conditionMicrosoft's proposed condition limits them to grid emergencies; backup only News report · April 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- As of Oct. 2026No state utility caseNo Michigan Public Service Commission case names a Consumers Energy contract for the campus; the project is stalled at township rezoning. Dataset · Oct. 2026
Money on record
What happened, and what is due
- Oct. 2024Site Microsoft buys 316 acres at Patterson Avenue and 76th Street from Steelcase for $45.3 million (press) News report · Oct. 2024
- Dec. 18, 2025Permits First rezoning hearing adjourns when turnout overwhelms the venue Dataset · April 2026
- April 15, 2026Permits Planning commission tables the rezoning 7-0 after a 5.5-hour hearing Local government · April 2026
- April 16, 2026Legal A resident appeals a records-fee decision and cites the township's nondisclosure agreement with Microsoft Local government · April 2026
- Aug. 10, 2026Construction Township trustees vote 7-0 to hire an acoustics firm for a baseline noise study, paid by Microsoft's escrow (press) News report · Aug. 2026
- Oct. 2026Site Press reports the project on hold for several weeks News report · Oct. 2026
Specs
150 ft setbacks, 65 dB limit conditions Microsoft proposed for the rezoning (not an executed agreement). News report · April 2026
- No tax abatements: Microsoft proposes not to seek local property tax abatements News report · April 2026
Owners, partners and builders
- Microsoft Corporation: applicant and land owner
- Steelcase Inc.: seller of the first 316 acres
- Gaines Charter Township Planning Commission: tabled the rezoning
- Gaines Charter Township Board: funded the noise study
- Consumers Energy: identified power supplier
Open questions
- Campus MW and investment.
- Rezoning decision.
- Final site size (316, 356 or 436 acres reported).
- Utility contract.
31 records from 11 documents
Drawn from news reports, local government records and public and commercial datasets, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (3)
- A resident FOIA appeal heard by the Board on Apr. 16, 2026 disputes a $645.24 fee for records on the Microsoft rezoning and cites resident concern over the NDA signed between township officials and Microsoft; no project“residents are highly concerned about the transparency of this process, the NDA that was signed between Township officials and Microsoft, and how this entire request has been handled”Local government · April 2026 · grade B
- No MW on any basis (mw it, mw utility, mw campus stated, mw generation onsite) is disclosed in the township filings, the hearing notice, the minutes or press found“That rezoning request - still pending - saw Microsoft confirming its plans to establish a data center at the site, though details about project timelines and scale remain sparse”News report · April 2026 · grade C
- Microsoft's proposed conditional-rezoning commitments (PROPOSED conditions, not an executed agreement): no local property tax abatements; setbacks of at least 150 feet; approximately 9.5 acres donated for open space and“Not seek local property tax abatements from Gaines Township; Use setbacks of at least 150 feet from property lines; Improve and donate approximately 9.5 acres of land for open space and trail connections”News report · April 2026 · grade C
Money and contracts (4)
- Microsoft has established an escrow account with the township to cover all administrative and consulting expenses, per the Township Treasurer as reported Aug. 10, 2026; the baseline noise survey cost is $5,676.97“Microsoft has already established an escrow account with the township to cover all administrative and consulting expenses. The cost to perform the survey is $5,676.97”News report · Aug. 2026 · grade C
- Aug 10, 2026: the Board of Trustees voted 7-0 to hire Memtech Acoustics for a baseline noise study (USD 5,676.97), paid from a Microsoft-funded escrow account the company established with the township for administrative“According to Township Treasurer Laurie Lemke, Microsoft has already established an escrow account with the township to cover all administrative and consulting expenses. The cost to perform the survey is $5,676.97.”News report · Aug. 2026 · grade C
- Approximately 600 people attended the Apr 15, 2026 hearing with 67 public comments, the overwhelming majority opposed (press tally of the tabling vote: 7-0). Residents repeatedly demanded a one-year moratorium; no Gaines“On April 15, 2026, the Planning Commission voted 7-0 to table Microsoft's rezoning request after a 5.5-hour hearing with 67 public comments and nearly 600 attendees.”News report · April 2026 · grade C
- Oct 2024: Microsoft acquired 316 acres at Patterson Avenue and 76th Street from Steelcase Inc. for USD 45.3 million; holdings were later reported at 356 acres (including a 40.5-acre parcel from Republic National Distribu“The site, on the corner of Patterson Avenue and 76th Street, was acquired from furniture seller Steelcase Inc. for $45.3 million for a potential data center development.”News report · Oct. 2024 · grade C
Permits and government (9)
- Residents asked the Planning Commission for a one-year moratorium at both the Apr. 15 hearing and the Apr. 23, 2026 meeting; no Gaines Township moratorium ordinance was found in force as of Oct. 2026“Tammy of 5140 N. Morgan Lane explained that she is not in support of the Microsoft project and is also asking for a one-year moratorium”Local government · April 2026 · grade B
- The Microsoft rezoning remains pending: the Planning Commission tabled it on Apr. 15, 2026 and no later rezoning decision was found through Oct. 2026; no site plan has been filed, with building height detail deferred to“further detail will be provided during site plan review”Local government · April 2026 · grade B
- Microsoft's application includes rezoning conditions covering sound, light, emissions, water use, decommissioning, screening and low vibrational sounds, stated to be enforceable by contract and zoning law“Mills stated that the application includes several rezoning conditions which will be enforceable by contract and zoning law”Local government · April 2026 · grade B
- Apr 15, 2026: the Planning Commission tabled Microsoft's five-parcel conditional rezoning request (motion by Haagsma, supported by Wiersema) so Microsoft and township staff could answer commission concerns. Township staf“Motion by Haagsma, supported by Wiersema, to table the request for a conditional rezoning and allow Microsoft and Township staff to provide answers to concerns posed by the Planning Commission.”Local government · April 2026 · grade B
- Gaines Charter Township Planning Commission:“Motion by Haagsma, supported by Wiersema, to table the request for a conditional rezoning and allow Microsoft and Township staff to provide answers to concerns posed by the Planning Commission”Local government · April 2026 · grade B
- Gaines Charter Township Board of Trustees:“At their Aug. 10 meeting, trustees voted 7-0 to hire Rochester Hills-based Memtech Acoustics to map out current baseline sound levels before any construction might begin”News report · Aug. 2026 · grade C
- Microsoft's rezoning request (PUD/agricultural to light industrial for its Patte: Rezoning request TABLED 7-0 (April 15, 2026) after 5.5-hour hearing; project put on hold“On April 15, 2026, the Planning Commission voted 7-0 to table Microsoft's rezoning request after a 5.5-hour hearing with 67 public comments and nearly 600 attendees”Dataset · April 2026 · grade C
- Contentious: nearly 600 people attended the five-and-a-half-hour Apr. 15, 2026 hearing and 67 spoke, the overwhelming majority opposed per press; residents also repeatedly requested a one-year moratorium, which was not a“On April 15, nearly 600 people out for a five-and-a-half-hour Gaines Planning Commission special meeting on April 15 in the South Christian High School auditorium. And 67 of them spoke during a public hearing”News report · April 2026 · grade C
- Consumers Energy is the identified power supplier for Gaines Township, publicly associated with ratepayer-protection commitments ahead of the April 2026 hearing - but every state-level step (MPSC special contract or larg“5-point community plan: 150 ft setbacks, ≤65 dB, 9.5 acres donated open space; Consumers Energy to supply power with ratepayer protections”Dataset · April 2026 · grade C
Site and other (2)
- Project status: proposed“Microsoft has proposed building the data center on a 436-acre site at 7147 Patterson Avenue, south of 68th Street.”News report · Aug. 2026 · grade C
- County code: 26081“Crain's reports Microsoft has acquired 316 acres of property in Gaines Charter Township in Kent County, south of Grand Rapids.”News report · April 2026 · grade C